• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/740

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

740 Cards in this Set

  • Front
  • Back
'ABC'
'Activity Based Costing (ABC) - A methodology that measures the cost and performance of activities
'ABM'
'Activity Based Management (ABM) - The broad discipline that focuses on achieving customer value and company profit by way of the management of activities. It draws on activity-based costing as a major source of information.'
'ACWP'
'Actual Cost of Work Performed - (ACWP) Total costs incurred (direct and indirect) in accomplishing work during a given time period. ACWP is used in the earned value method of progress measurement. See also earned value analysis.'
'ADM'
'Arrow Diagram Method (ADM) - One of two conventions used to represent an activity in a project. Also known as Activity on Arrow method.'
'ALAP'
'As-Late-As-Possible (ALAP) - An activity for which the application sets the early dates as late as possible without delaying the early dates of any successor.'
'AMR'
'Advanced Material Release (AMR) - A document used by organizations to initiate the purchase of long-lead-time or time-critical materials prior to the final release of a design.'
'APR'
'Acquisition Plan Review (APR) - The control gate to approve the Acquisition Plan. The APR is the decision point to initiate the project and commit funding
'ATP'
'Acceptance Test Procedure (ATP) - Detailed step-by-step instructions for the setup
'Abstract Resource'
'Imaginary resource introduced so that its availability and activity requirement gives an extra means of control. For example
'Acquisition Evaluation'
'Review and analysis of responses to determine supplier#s ability to perform the work as requested. This activity may include an evaluation of suppliers financial resources
'Acquisition Plan'
'The document that describes the approach for acquisition. It defines competitive or sole source
'Actual and Scheduled Progress'
'A comparison of the observable work done at a given time with the work planned up to that time.'
'Added Value'
'The addition of some worthwhile quality or performance improvement as a result of some action taken
'Aggregation'
'Summation of parts. Typically used in reference to estimating.'
'Allowable Cost'
'A cost that meets the tests of: Reasonableness
'Assumption'
'There may be external circumstances or events that must occur for the project to be successful. If you believe such an event is likely to happen
'Attrition'
'The loss of a resource due to causes beyond the jurisdiction of the project manager such as the death or resignation of an employee
'Avoidance'
'Keeping away from. Typically used as a risk reduction strategy by adopting a Workaround.'
'BAC'
'Baseline at Completion (BAC) - Total completed cost of work as originally planned.'
'BCWP'
'Budgeted Cost of Work Performed (BCWP) - The sum of the budgets for completed portions of in-process work
'BCWS'
'Budgeted Cost of Work Scheduled (BCWS) - The sum of the budgets for work scheduled to be accomplished (including in-process work)
'BEC'
'Budgeted Elapsed Cost'
'BOOT'
'Build
'Backcharge'
'The cost of corrective action taken by the purchaser
'Backward Pass'
'Calculation of the latest finish times by working from finish to start for the uncompleted portion of a network of activities.'
'Balanced Matrix'
'An organizational matrix where functions and projects have the same priority.'
'Balanced Scorecard Approach'
'(BSA) - A business methodology designed to assess the performance of an enterprise in more than just financial terms
'Barriers'
'Obstacles in the way of progress
'Baseline Cost'
'The amount of money an Activity was intended to cost when the Baseline Plan was established.'
'Baseline Schedule'
'A fixed project schedule that is the standard by which project performance is measured. The current schedule is copied into the baseline schedule which remains frozen until it is reset. Resetting the baseline is done when the scope of the project has bee
'Baseline'
'The value or condition against which all future measurements will be compared.'
'Baseline
budget'
'Benchmarking'
'The search for industry best practices that lead to superior performance.'
'Benefits Management Plan'
'A project statement of who is responsible for achieving the benefits
'Best Practices'
'Techniques that agencies may use to help detect problems in the acquisition
'Blanket Purchase Agreement'
'(BPA) - A simplified method of filling anticipated repetitive needs for supplies or services by establishing charge accounts with qualified sources of supply.'
'Bottom Up Cost Estimate'
'An estimate derived by summing detailed cost estimates of individual work packages (labor and materials) and applying appropriate cost burdens.'
'Breadboarding'
'The creation of an experimental device to determine the feasibility of an idea
'Breakdown Structure'
'A hierarchical structure by which project elements are broken down
'Bribe'
'A price
'Burn Rate'
'The rate at which funds or man-hours are being expended on a project.'
'Burst Node'
'In a network diagram
'CMM'
'Capability Maturity Model (CMM) - A description of the stages through which organizations evolve as they define
'CPFF'
'Cost Plus Fixed Fee Contract (CPFF) - A type of contract where the buyer reimburses the seller for the seller#s allowable costs plus a fixed fee.'
'CPI'
'Cost Performance Index (CPI) - The cost efficiency factor representing the relationship between the actual costs expended and the value of the physical work performed.'
'CPIFC'
'Cost Plus Incentive Fee Contract (CPIFC) - A type of Contract where the buyer reimburses the seller for the seller#s allowable costs and the seller earns a profit if defined criteria are met.'
'CPPC'
'Cost Plus Percentage of Cost Contract (CPPC) - Provides reimbursement of allowable cost of services performed plus an agreed upon percentage of the estimated cost as profit.'
'CV'
'Cost Variance'
'Calendar Unit'
'The smallest unit of time used in scheduling the project. Calendar units are generally in hours
'Carryover Type 1'
'A project fiscal expenditure management term. The sum of contractual commitments that must be paid in the next fiscal period arising from outstanding obligations including associated engineering and support costs.'
'Carryover Type 2'
'A project fiscal expenditure management term. That portion of Planned Future Expenditures contractually committed plus associated support costs which may be paid in the next fiscal period which would extend into the next fiscal year if the planned future
'Cascade Chart'
'Bar chart on which the vertical order of activities is such that each activity is dependent only on activities higher in the list.'
'Cash Flow Analysis'
'The activity of establishing cash flow (dollars in and out of the project) by month and the accumulated total cash flow for the project for the measurement of actual versus the budget costs. This is necessary to allow for funding of the project at the l
'Change Control'
'The review
'Change Management Plan'
'A defined process for making changes to a project plan.'
'Chart of Accounts'
'Any numbering system used to monitor project costs by category
'Child'
'A lower-level element in a hierarchical structure.'
'Closed Projects'
'Projects that have either been completed
'Closeout'
'The completion of all work on a project.'
'Coaching'
'The process of assisting people to improve their performance.'
'Collaboration'
'Working together
'Collapsing'
'In an outline
'Commission and Handover'
'The completion
'Commissioning'
'Advancement of an installation from the stage of static completion to full working order and achievement of the specified operational requirements.'
'Communication Channels'
'The path along which the exchange of information takes place or is supposed to take place. Typically refers to the sequence of individuals in a chain of command.'
'Component-Based Development'
'(CBD) - The creation and deployment of software-intensive systems assembled from components as well as the development and harvesting of such components.'
'Compromise'
'Both sides agree such that each wins or loses a few points.'
'Conditional Risk'
'Risk that occurs under certain conditions or is accepted provided that certain conditions are met.'
'Conflict Management'
'Handling of conflicts between project participants or groups in order to create optimal project results.'
'Conflict Resolution'
'To seek a solution to a problem
'Constraint'
'A restriction that must be balanced with all other constraints to achieve project success. The four primary and universal project constraints are scope
'Consultant'
'One who provides some specialized service based on their special qualifications
'Contingencies'
'Specific provision(s) to mitigate random or unknown project risks from causing project failure or frequent baseline changes.'
'Contingency Allowance'
'Specific provision to cover variations which may occur in the expected values of elements of cost or schedule
'Contingency Plan'
'A fallback position
'Contingency Reserve'
'A provision held by the project sponsor for possible changes in project scope or quality. Scope and quality changes constitute changes in the project manager#s mandate and will affect the project#s cost and schedule.'
'Contract Closeout'
'Contract closeout activities which assure that the contractor has fulfilled all contractual obligations and has released all claims and liens in connection with work performed.'
'Contract Risk'
'The potential and consideration of risk in procurement actions. Generally the forces of supply and demand determine who should have the maximum risk of contract performance but the objective is to place on the supplier the maximum performance risk while
'Contraints'
'Mostly time
'Control Gate'
'A major project milestone at which the project sponsor has the opportunity at the end of one phase of exercising a
'Control Theory'
'The view that motivation by goal setting can be further extended by understanding and predicting how humans process information and make decisions about how much effort to put forth. Based on metacognitive theory of motivation
'Controllable Risks'
'Those risks to the project which
'Coordinated Matrix'
'An organizational structure where the project leader reports to the functional manager and doesn#t have authority over team members from other departments.'
'Corporate Constraints'
'Limitations to the activities of a corporation. These may be as a result of the corporation#s charter
'Corporate Responsibility Matrix'
'A responsibility matrix depicted at the corporate level and from the corporate perspective.'
'Cost Analysis'
'The analysis of the cost elements of a proposal or on-going work. It includes verification of cost data
'Cost Avoidance'
'An action taken in the present designed to decrease costs in the future.'
'Cost Baseline'
'A time-phased budget used to measure and monitor cost performance. It is developed by summing estimated costs by period and is usually displayed in the form of an S curve.'
'Cost Benefit Analysis'
'An analysis of the relationship between the costs of undertaking a task or project
'Cost Control Point'
'The point within a program at which costs are entered and controlled. Frequently
'Cost Control System'
'Any system of keeping costs within the bounds of budgets or standards based upon work actually performed. Cost Control is typically a level in the budget element breakdown structure.'
'Cost Curve'
'A graph plotted against a horizontal time scale and cumulative cost vertical scale.'
'Cost Estimate Classification System'
'A five-level cost estimate system based on the amount of project information available developed by the American Association of Cost Engineers
'Cost Plus Fixed Fee Contract'
'(CPFF) - A form of contractual arrangement in which the customer agrees to reimburse the contractor#s actual costs
'Cost Plus Incentive Fee Contract'
'(CPIFC) A type of Contract where the buyer reimburses the seller for the seller#s allowable costs and the seller earns a profit if defined criteria are met.'
'Cost Plus Percentage of Cost Contract'
'Provides reimbursement of allowable cost of services performed plus an agreed upon percentage of the estimated cost as profit.'
'Cost Reimbursable Contract'
'A contract that provides for payment of allowable incurred costs
'Cost Types'
'Four different cost types are typically associated with the scope of work in a cost class. They reflect whether a cost is authorized
'Cost Variance'
'(CV) - The difference between the budgeted and actual cost of work performed.'
'Cost-Benefit Analysis'
'An analysis
'Countermeasures'
'Preventive actions that are chosen by the project team to reduce either scope or schedule risk.'
'Crash Costs'
'The cost of reducing an Activity to its Crash Duration.'
'Crashing'
'Action to decrease the duration of an activity or project by increasing the expenditure of resources.'
'Critical Factors'
'Favorable or adverse conditions that may exist or be expected that may significantly impact the course of a project. See also Critical Success Factors.'
'Critical Path Analysis'
'Procedure for calculating the critical path and floats in a network.'
'Critical Path Method'
'(CPM) - A technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility. Early dates are figured by a forward pass using a specific start date and late dates are figured by using a bac
'Critical Path'
'The series of tasks that must finish on time for the entire project to finish on schedule. Each task on the critical path is a critical task. In a network diagram
'Critical Task'
'A task that must finish on time for the entire project to finish on time. If a critical task is delayed
'Cross-Stage Plan'
'A detailed plan showing activities that span more than one stage in the project life cycle.'
'Cybernetics'
'The study of man-machine relationships to optimize output performance. Generally given inadequate attention on projects. See also Method Study.'
'Dangle'
'An activity in a network which has neither predecessors nor successors.'
'Decomposing'
'The process of reducing a project scope into its various elements resulting in a work breakdown structure.'
'Dependency Arrow'
'A link arrow used in an activity on node network to represent the interrelationships of activities in a project.'
'Dependency Diagram'
'Another name for a network or precedence diagram that shows the dependencies (precedence) between tasks.'
'Discrete Milestone'
'A milestone that has a definite scheduled occurrence in time.'
'Dual Concern Model'
'A graphical display in which the five negotiating strategies are plotted with Concern about Own Outcomes (X-axis) against Concern for Other Side#s Outcomes (Y-axis).'
'Dummy Activity'
'An activity of zero duration used to show a logical relationship in the arrow diagramming method. Dummy activities are used when logical relationships cannot be completely described with regular activity arrows. Dummies are shown graphically as a dashed
'Duration Compression'
'Shortening the project schedule without reducing the project scope. Duration compression is not always possible and often requires an increase in project cost.'
'Dynamic Baseline Model
'(DBM) - A conceptual model framework for: Exploring the evolution of project management behaviors
'EAC'
'EAC - Estimate at Completion. A value expressed in either dollars and/or hours
'ECC'
'Estimated Cost to Complete (ECC) - The remaining costs to be incurred to satisfy the complete scope of a project at a specific data date. The difference between the cost to date and the forecast final cost.'
'ETC'
'Estimate to Complete (ETC) - The value expressed in either dollars or hours developed to represent the cost of the work required to complete a task. The ETC is calculated as BAC - BCWP.'
'EVMS'
'Earned Value Management System - (EVMS) A management system and related sub-systems implemented to establish a relationship between cost
'Earned Value Analysis'
'Analysis of project progress where the actual money budgeted and spent is compared to the value of the work achieved.'
'Earned Value'
'A measure of the value of work performed so far. Earned value uses original estimates and progress-to-date to show whether the actual costs incurred are on budget and whether the tasks are ahead or behind the baseline plan.'
'Effort-Driven Activity'
'An activity whose duration is governed by resource usage and availability. The resource requiring the greatest time to complete the specified amount of work on the activity will determine its duration.'
'Elaboration'
'The second phase of the Unified Process in which the concept developed in the conception phase is funded for problem domain analysis
'End Tranche Assessment'
'A review carried out at the outset of the benefits realization phase to verify the completion of all tranche projects and to plan for maximizing benefits from tranche projects and executing the next tranche.'
'Essentials of Project Management'
'The four essentials of project management are: Common Vocabulary
'Estimate Class A'
'An estimate based on complete contract documents and used as a control check on authorized expenditures prior to tendering.'
'Estimate Class B'
'An estimate based on completed preliminary design drawings. Upon acceptance
'Estimate Class C'
'An estimate based on completion of all work necessary to undertake preliminary design. This estimate must be based on knowledge of site conditions adequate to enable the identification of site related risks and the development of corresponding contingenc
'Estimate Class D'
'An Order of Magnitude estimate only. In all cases
'Event-on-Node'
'A network diagramming technique in which events are represented by boxes (or nodes) connected by arrows to show the sequence in which the events are to be completed. Used in the original Program Evaluation and Review Technique.'
'Exculpatory Language'
'Language in the contract documents which purports to release the liability of one party for certain actions which may occur during the performance of the work.'
'Expected Value'
'(EV) - A way for comparing the values/costs of different scenarios
'Expediting'
'Facilitating and accelerating progress by the removal of obstacles.'
'Expert Power'
'The ability (of a project manager) to gain support because project personnel perceive the project manager as possessing special knowledge or expertise (that functional personnel consider important.)'
'FTC'
'Forecast to Completion (FTC) - Forecast To Completion is the cost to completion based upon the actual performance to date and assumes that the rate of expenditure continues as at present i.e. FTC = ACWP x 100 / % complete'
'Fast Tracking'
'Compressing the project schedule by doing some or all of certain activities in parallel that would normally be done in sequence (such as design and construction).'
'Feasibility Study'
'The methods and techniques used to examine technical and cost data to determine the economic potential and the practicality of project applications. It involves the use of techniques such as the time value of money so that projects may be evaluated and c
'Finish to Finish Lag'
'The minimum amount of time that must pass between the finish of one activity and the finish of its successor(s). All lags are calculated when a project has its schedule computed. Finish-to Finish lags are often used with Start-to-Start lags.'
'Finish to Start Lag'
'The minimum amount of time that must pass between the finish of one activity and the start of its successor(s). The default finish-to-start lag is zero. All lags are calculated when a project has its schedule computed. In most cases
'Firm Fixed Price Contract'
'(FFP) - A contract where the buyer pays a set amount to the seller regardless of that seller#s cost to complete the work.'
'Floating Task'
'A task that can be performed earlier or later in the schedule without
'Forcing'
'The project manager uses his power to direct the solution. This is a type of win-lose agreement where one side gets its way and the other does not.'
'Formal Authority'
'The ability (of a project manager) to gain support because project personnel perceive the project manager as being officially empowered to issue orders.'
'Forward Pass'
'Calculating the earliest start dates moving from left to right along a network.'
'Free Float'
'The maximum amount by which an activity can be delayed beyond its early dates without delaying any successor activity beyond its early dates.'
'Free Riding'
'A situation where some project team members do less work than the others.'
'Free Slack'
'The amount of time a task can slip without delaying another task. For a task without successors
'GERT'
'Graphical Evaluation and Review Technique (GERT) - A network analysis technique that allows for conditional and probabilistic treatment of logical relationships (i.e.
'Gantt Chart'
'A chart using time lines and other symbols that illustrates multiple
'Goal Setting Theory'
'The view that when a manger sets clear
'Hammock Activity'
'An Activity that spans between two points in a network. It has no duration of its own but derives one from the time difference between the two points to which it is connected.'
'Hanger'
'An unintended break in a network path.'
'Hard Project'
'A project that has a well defined physical product as its outcome as distinct from a soft project
'Harmonization'
'The process and/or results of adjusting differences or inconsistency to bring significant aspects into agreement.'
'Histogram'
'A graph showing resource usage on the vertical axis against time on the horizontal axis.'
'Hold Point'
'A defined step during processing when work must stop so that authorized inspection can be conducted and the work approved and released for further progress.'
'INCOTERMS'
'A set of international terms defining conditions for delivery and shipping of equipment and materials.'
'Impact
risk'
'Implied Warranty'
'The legal theory that when an owner requires a contractor to execute a project in accordance with plans and specifications supplied by the owner
'Imposed Date'
'A predetermined calendar date set (usually externally) without regard to logical considerations of the network.'
'Imposed Finish'
'A finish date imposed on an activity by external constraints.'
'Independent Float'
'The degree of flexibility which an activity has which does not affect the float available on any preceding or succeeding activities.'
'Inexcusable Delays'
'Project delays that are attributable to negligence on the part of the contractor which lead in many cases to penalty payments.'
'Initiation'
'The process of preparing for
'Input Restraints'
'Imposed external restraints
'Intangible Capital'
'The market value of the knowledge
'IBR'
'Integrated Baseline Review (IBR) - A joint PM/Customer review to understand and assess the adequacy
'Interactive Project Planning'
'Project planning carried out in active cooperation between project participants. Forms a contrast to project planning centralized in the project manager.'
'Investment Life-Cycle'
'The lifetime of a project deliverable from inception to ultimate termination. Often there is uncertainty about the length of time over which a project will be operating and assumptions will have to be made.'
'Key Success Indicators'
'(KSI) - Those project management indicators that: are determined at the beginning of the project and listed in order of priority
'Kickback'
'Any money
'Ladder'
'Device for representing a set of overlapping activities in a network diagram.'
'Lag Time'
'The amount of time delay between the completion of one task and the start of its successor task.'
'Lag'
'The amount of time after one task is started or finished before the next task can be started or finished.'
'Legacy Thinking'
'Wedded to outmoded concepts and practices.'
'Level Float'
'The difference between the level finish and the late finish date.'
'Loop'
'A path in a network closed on itself passing through any node more than once on any given path. The network cannot be analyzed
'MIS Quality Requirements'
'The process of organizing a project#s objectives
'Management Reserve'
'(MR) - An amount of the owner#s total allocated budget withheld under the owner#s management control
'Management Styles - Authoritarian'
'Lets individuals know what is expected of them
'Management Styles - Combative'
'project manager that is marked by an eagerness to fight or be disagreeable over any given situation.'
'Management Styles - Conciliatory'
'A project manager that is friendly and agreeable; one that attempts to assemble and unite all project parties involved to provide a compatible working team.'
'Management Styles - Disruptive'
'A project manager that tends to break apart the unity of a group
'Management Styles - Ethical'
'A project manager that is honest
'Management Styles - Facilitating'
'The project manager is available to answer questions and give guidance when needed; he does not interfere with day to day tasks
'Management Styles - Intimidating'
'A project manager that frequently reprimands employees for the sake of an image as a tough guy
'Management Styles - Judicial'
'A project manager that exercises the use of sound judgment or is characterized by applying sound judgment to most areas of the project.'
'Management Styles - Promotional'
'Encourages subordinates to realize their full potential
'Management Styles - Secretive'
'A project manager that is not open or outgoing in speech activity
'Management by Exception'
'The issue of management reports to responsible managers only when action is called for. This helps the manager to avoid wading through voluminous reports where progress is going according to plan. However
'Management by Methods'
'(MBM) - Level 2 of a five level Dynamic Baseline Model in which those proficient in MBR build on their knowledge base
'Management by Objectives'
'(MBO) - A management theory that calls for managing people based on documented work statements mutually agreed to by manager and subordinate. Progress on these work statements is periodically reviewed
'Management by Politics'
'(MBP) - A potential Level 5 of a five level Dynamic Baseline Model structure. This is an extrapolation of the model which would lead to a management approach where the essential values of the corporation are a dynamic baseline. This would entail dealing
'Management by Project'
'A term that is gaining popularity
'Management by Rules'
'(MBR) - Level 1 of a five level Dynamic Baseline Model structure at which behavior
'Management by Threshold'
'A system approach in which deviation limits or thresholds for key parameters are set relative to the baseline plan. When thresholds are exceeded the system alerts management to review and take corrective action. Such a system is intended to avoid the nec
'Management by Values'
'(MBV) - Level 4 of a five level Dynamic Baseline Model structure in which an employee has the capacity to manipulate and evolve the objective throughout the project life cycle as appropriate to the overarching corporate values. MBV practitioners are expe
'Management by Walking Around'
'(MBWA) - Part of the Hewlett Packard legacy and popularized by management theorist Tom Peters. MBWA works on the assumption that a manager must circulate to fully understand the team#s performance and problems. The best managers
'Matrix Organization'
'A combination of the advantages of the pure functional (traditional) structure and the product organizational structure. The project manager has total responsibility and accountability for project success
'Maturity Model'
'A published framework as a basis for determining the degree of maturity of an organization
'Milestone'
'A point in time representing a key or important intermediate event in the life of a project. A milestone should be capable of validation by meeting all of the items prescribed in a defining checklist as agreed with the stakeholders.'
'Mixed Organization'
'This organizational structure includes functional groups
'Negative Float'
'The amount of time by which the early date of an activity exceeds its late date.'
'Network Diagram'
'A schematic display of the sequential and logical relationship of the activities which comprise the project. Two popular drawing conventions or notations for scheduling are arrow and precedence diagramming.'
'Network Logic'
'The collection of activity dependencies that make up a project network diagram.'
'Node'
'The start and end of activities in an activity on arrow network or the activity box in a precedence network.'
'Normal Probability Distribution'
'The continuous distribution most commonly used in statistics to make inferences about a population from sample data.'
'Object-Oriented Analysis'
'Analysis based on considering the system as a collection of objects (entities
'Order of Magnitude Estimate'
'(Accuracy -25
'Organizational Breakdown Structure'
'(OBS) - A hierarchical structure designed to pinpoint the area of an organization responsible for each part of a project.'
'Organizational Factors'
'The availability of expertise of personnel
'Overrun'
'An increase in the time or cost compared to the plan. A reduced scope without a corresponding reduction in the time or cost would be considered an overrun.'
'PMBoK'
'Project Management Body of Knowledge - (PMBoK) An inclusive term that describes the sum of knowledge within the profession of project management. As with other professions such as law and medicine
'Parametric Cost Estimating'
'Appraising the costs of a project based on knowledge gathered from similar
'Parametric Estimating'
'An estimating technique that uses a statistical relationship between historical data and other variables (e.g.
'Pareto Diagram'
'A histogram
'Project Life Cycle'
' The four sequential major time periods through which any project passes
'Project Log'
'A project diary. A chronological record of significant occurrences throughout the project.'
'Project Manager'
'(PM) - The person who heads up the project team and is assigned the authority and responsibility for conducting the project and meeting project objectives through project management.'
'Project Matrix'
'An organization matrix that is project based in which the functional structures are duplicated in each project.'
'Project Monitoring '
'Comparison of current project status with what was planned to be done to identify and report any deviations.'
'Project Office'
'A designated location where the administrative work of the project is conducted and the project management skills (resources) such as cost accounting
'Project Oriented'
'Typically organizations who have a predisposition to use projects as their corporate business approach
'Project Portfolio'
'The projects included in a particular program.'
'Project Progress Report'
'Formal statement that compares the project progress
'Project Records Management'
'The system and procedures established by the Company for the consistent and effective storage and retrieval of all project information for the efficient use by the project manager and his/her project Team.'
'Project Reporting'
'A planning activity involved with the development and issuance of (internal) TIME management analysis reports and (external) progress reports.'
'Project Risk Management'
'The process of identification
'Project Risk'
'The cumulative effect of the chances of uncertain occurrences which will adversely affect project objectives. It is the degree of exposure to negative events and their probable consequences. Project risk is characterized by three factors: risk event
'Project Schedule'
'Planned dates for starting and completing activities and milestones.'
'Project Scope Management'
'A subset of project management that includes initiation
'Project Scope'
'A concise and accurate description of the end products or deliverables to be expected from the project and that meet specified requirements as agreed between the Project
'Project Stakeholder'
'A person
'Project Standard'
'A norm
'Project Status Report'
'A report on the status of accomplishments and any variances to spending and schedule plans.'
'Project constraint'
'A factor that will limit the project management team#s options. For example
'Punishment of the Innocent'
'A humorous reference to what is perceived to happen when projects go wrong and scapegoats are found.'
'Purchasing Strategy'
'To the extent that there may be alternative approaches
'Qualitative Risk Analysis'
'A generic term for subjective methods of assessing risks.'
'Quality Assurance Plan'
'A plan that guarantees a quality approach and conformance to all customer requirements for all activities in a project.'
'Quality Assurance'
'All those planned and systematic actions necessary to provide adequate confidence that a product or service will satisfy given requirements for quality.'
'Quality Audit'
'A systematic and independent examination to determine whether quality activities and related results comply with planned arrangements and whether these arrangements are implemented effectively and are suitable to achieve objectives.'
'Quality Criteria'
'The characteristics of a product that determines whether it meets certain requirements.'
'Quality Plan'
'A document setting out the specific quality practices
'Quantitative Control'
'Any quantitative or statistically-based technique appropriate to analyze a software acquisition process
'RAM'
'Responsibility Assignment Matrix (RAM) - The RAM correlates the work required by a Contract Work Breakdown Structure (CWBS) element to the functional organization responsible for accomplishing the assigned tasks. The responsibility assignment matrix is
'RF'
'Remaining Float - The difference between the early finish and the late finish date.'
'RFP'
'Request for Proposal - A formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form the basis of a contract.'
'ROI'
'Return on Investment (ROI) - The financial return for a given outlay
'Re-baseline'
'Development of a revised implementation plan with new milestone schedules. Re-baselining is required in response to changed contract requirements
'Readiness Assessment'
'A meeting or series of meetings by selected members of the customer C/SCSC review team at a contractor
'Recovery Schedule'
'A special schedule showing special efforts to recover time lost compared to the master schedule.'
'Recurring Costs'
'Expenditures against specific tasks that would occur on a repetitive basis. Examples are sustaining engineering
'Reengineering'
'The process of redesigning a product
'Referent Power'
'The ability (of a project manager) to gain support because project personnel feel personally attracted to the manager or the project.'
'Regression Analysis'
'Where past data is insufficient for direct forecasting of future levels of activity it may still be possible to make assumptions based on relationships with other activities that can be forecast. This applies particularly to apportioned-effort tasks and
'Regulations'
'Rules or orders issued by an executive authority or regulatory agency of a government and having the force of law.'
'Remaining Available Resource'
'The difference between the resource availability pool and the level schedule resource requirements. Computed from the resource allocation process.'
'Replacement Theory'
'A statistical methodology for arriving at the optimum life of replaceable elements in a project. It considers replacement cost
'Requirement'
'A description of a condition or capability to which a system must conform; either derived directly from user needs
'Requirements Traceability Matrix'
'A document that maps the parent-child relationships of requirements.'
'Requirements Traceability'
'The management of the parent/child relationships of all system requirements.'
'Reserve'
'A provision in the project plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g.
'Residual Risks'
'Those risks which are not avoided
'Resource Constraint'
'Limitation due to the availability of a resource.'
'Resource Optimization'
'A generic term for resource leveling and resource smoothing.'
'Resourcing Plan'
'Part of the definition statement stating how the program will be resource loaded and what supporting services
'Response Planning'
'The process of formulating suitable risk management strategies for the project
'Risk & Readiness Assessment'
'An evaluation
'Risk Analysis'
'An examination of risk areas or events to assess the probable consequences for each event
'Risk Assessment'
'The process of identifying potential risks
'Risk Assumption'
'Risk assumption is an acknowledgment of the existence of a particular risk situation and a conscious decision to accept the associated level of risk
'Risk Avoidance'
'The process of planning activities so as to avoid identified risks by using an alternative method.'
'Risk Management Plan'
'A document defining how Project Risk Analysis and Management is to be implemented in the context of a particular project.'
'Risk Management'
'An organized assessment and control of project risks.'
'Risk Matrix'
'A matrix with risks located in rows
'Risk Mitigation Strategy'
'An overall plan for mitigating the risks in the investment activity.'
'Risk Mitigation'
'The act of revising the project#s scope
'Risk Quantification'
'Process of applying values to the various aspects of a risk.'
'Risk Response Plan'
'A plan (prepared towards the end of the risk review) for controlling the risks once implementation begins.'
'Risk Response'
'The planned or actual action in response to a risk event.'
'Risk Sharing'
'Diminution of a risk by sharing it with others
'Risk Transfer'
'A contractual arrangement between two parties for delivery and acceptance of a product where the liability for the costs of a risk is be transferred from one party to the other.'
'Risk'
'The probability of an undesirable outcome.'
'Rolling Wave'
'A term used in scheduling to imply detailed planning or scheduling over a short horizon. Each period
'Rough Order of Magnitude Estimate'
'(ROM) - Estimated cost based on approximate cost models or expert analysis. It is usually based on top level requirements or specifications
'Runaway Project'
'A term coined by the consultancy KPMG to identify mainly IT projects which resist termination. Typified by a constantly changing specification and absorption of much extra resource and cost in a desperate effort to get the project finished.'
'S Curve'
'A display of cumulative costs
'SC'
'Scheduled Cost (SC) - The total cost of work when completed as calculated according to the current schedule.'
'SF'
'Scheduled Finish (SF) - The date calculated by the resource scheduling program as the earliest date on which an activity can finish
'SOW'
'Statement of Work - A narrative description of the work to be performed.'
'SPI'
'Scheduled Performance Indicator (SPI) - The ratio of BCWP to BCWS i.e. SPI = BCWP / BCWS. A positive value (i.e. greater than 1) indicates that work is ahead of schedule. A negative value (i.e. less than 1) indicates that work is behind schedule.'
'SV'
'Schedule Variance (SV) - Either Any difference between the scheduled completion of an activity and the actual completion of that activity
'SWOT Analysis'
'A process whereby a group of people determine: Strengths - What Strengths do we have? (How can we take advantage of them?)
'Sample Size'
'The number of units of product in the sample selected for inspection.'
'Sampling Frequency'
'(f) - The sampling frequency
'Sampling'
'The technique of selecting a representative part of a population for the purpose of determining parameters or characteristics of the whole population. A small part selected as a sample for inspection or analysis.'
'Scanning'
'Investigating or examining thoroughly by checking point-by-point and often repeatedly.'
'Scenario Planning'
'The planning of responses
'Schedule Refinement'
'The rework
'Schedule Risk'
'The potential problems the team might encounter in meeting the deadlines for the final deliverable.'
'Scope Changes'
'Any change in the project#s deliverables from that which was originally intended
'Scope Constraints'
'Applicable restrictions which will affect the scope.'
'Scope Creep'
'On-going requirements increase without corresponding adjustment of approved cost and schedule allowances. As some projects progress
'Scope Criteria'
'Standards or rules composed of parameters to be considered in defining the project.'
'Scope Definition'
'Breaking down a deliverable in to smaller manageable parts to ensure better control.'
'Scope Management'
'The function of controlling a project in terms of its goals and objectives through the processes of conceptual development
'Scope Risk'
'The potential problems the team might encounter in creation of a final deliverable. Also known as technical risk.'
'Scope Verification'
'Ensuring all identified project deliverables have been completed satisfactorily.'
'Scope'
'The definition that describes the project#s product deliverables. See also Managing Scope.'
'Screening'
'Techniques used for reviewing
'Secondary Float'
'(SF) - The difference between the CPM calculated early finish and the imposed finish date.'
'Self-Inspection'
'A service by a company or organization that is responsible for inspection of its own work.'
'Show Stopper'
'An event or condition serious enough to halt or severely impede a project unless confronted and eliminated.'
'Slip Chart'
'A pictorial representation of the predicted completion dates of milestones (also referred to as Trend Chart.'
'Slippage'
'The amount of time a task has been delayed from its original baseline plan. The slippage is the difference between the scheduled start or finish date for a task and the baseline start or finish date. Slippage can occur when a baseline plan is set and th
'Smoothing'
'Differences between two groups are played down and the strong points of agreement are given the most attention.'
'Soft Project'
'A project which is intended to bring about some form of change
'Sole Sourcing'
'The acquisition of supplies or services after soliciting and negotiating with only one source.'
'Splitting'
'In resource scheduling
'Sponsor'
'The executive who manages
'Stabilization'
'The period of time between continuous operation and normal operation. This period encompasses those activities necessary to establish reliable operation at design conditions of capacity
'Stand Alone'
'A system which performs its function requiring little or no assistance from interfacing systems.'
'Standard Cost'
'The normal expected cost of an operation
'Standard Deviation'
'A measure of the dispersion of possible outcomes. Mathematically
'Standard Project Cost Accounting'
'The standards associated with a project cost accounting system. Unlike the Generally Accepted Accounting Principles (GAAP) of corporate accounting
'Standard'
'A specific statement of the rules and constraints governing the naming
'Standards'
'Established or accepted rules
'Statistical Quality Control'
'Various statistical methods and relationships are available for determining performance quality and the adjustment necessary to achieve specified results. Used particularly in the sampling of high volume materials such as steel and concrete strengths
'Statistics'
'The mathematical methods used to determine the best range of probable values for a project and to assess the degree of accuracy or allowance for unpredictable future events such as accidents
'Status Report'
'A written report given to both the project team and to a responsible person on a regular basis stating the position of an activity
'Steering Committee'
'Formal group representing the owner or client.'
'Storming'
'The second stage of team building where conflicts arise as members of the group try to exert leadership and exert influence over methods of operation.'
'Strategic Risk'
'Any risk event which has serious or catastrophic consequences even though the probability of occurrence may be quite low.'
'Sunk Costs'
'Costs which could not be avoided even if the project were to be terminated.'
'TAB'
'Total Allocated Budget (TAB) - The sum of all budgets allocated to a contract. Total Allocated Budget consists of the performance measurement baseline plus all management or contingency reserves. The TAB will reconcile directly to the Contract Budget Ba
'TAE'
'Total Anticipated Expenditures (TAE) - The sum of work-to-date plus obligations plus planned future expenditures
'TQM'
'Total Quality Management (TQM) - A strategic
'Team Building'
'The process of influencing a group of diverse individuals
'Termination for Convenience'
'A unilateral right of the buyer to terminate any or all of a contractual effort for any reason at any time.'
'Termination for Default'
'Buyer action to cancel a procurement that is not meeting contract requirements. Default relates to failure of the contractor to perform contract work within the specified time or any other provisions of the contract.'
'Test Plan'
'A description of the tests needed to complete a project properly.'
'Thresholds'
'Monetary
'Tiger Team'
'A team established to focus on visibility
'Time Box'
'The calendar limits within which an activity is required or expected to occur.'
'Top Down Cost Estimating'
'The preparation of a cost estimate by using judgment and experience to arrive at an overall total amount
'Tracking'
'Collecting actual time
'Tranche'
'A block of work within the program
'Transit Time'
'Dependency link that requires time and no other resources. It may be a negative time.'
'Transition Plan'
'Part of the program definition statement that describes how the transition from the current business operation to the new environment of the blueprint will be managed.'
'Trend Line'
'A line on a schedule or chart showing the pattern of progress that is being set over time
'Trial Balloon'
'A tentative plan offered to test the reaction of a particular audience.'
'Triple Constraint'
'The term used to describe the three key project objectives that must be simultaneously accomplished
'Turnaround Report'
'A report created especially for the various responsible managers to enter their progress status against a list of activities that are scheduled to be in progress during a particular time window.'
'Undistributed Budget'
'(UB) - Budget applicable to contract effort which has not yet been identified to specific cost accounts or work packages.'
'Usage Variance'
'The difference between the budgeted quantity of materials and the actual quantity used.'
'VAC'
'Variance at Completion - (VAC) The budget at completion less the estimate at completion. A negative result indicates that the project is over budget.'
'Value Analysis'
'An activity devoted to optimizing cost performance. It is the systematic use of techniques which identify the required functions of an item
'Variance Threshold'
'The amount of a variance which will require a formal problem analysis report
'Venn Diagram'
'A diagram in which closed circles represent separately identifiable sets and their logical commonality or distinction by the inclusion
'Virtual Collocation'
'An arrangement whereby project team members meet as often as necessary through teleconferencing. This arrangement has been made necessary for companies who operate globally
'WBS Dictionary'
'A document that describes each element in the WBS including a Statement of Work (SOW)
'WBS'
'Work Breakdown Structure (WBS) - A task oriented detailed breakdown
'Wet and Dry Test Runs'
'A procedure for testing plant and equipment prior to full commissioning. Dry test runs imply tests without product throughput
'What-If Analysis'
'The process of evaluating alternative strategies.'
'Work Acceptance'
'Work is considered accepted when it is conducted
'ABC'
'Activity Based Costing (ABC) - A methodology that measures the cost and performance of activities
'ABM'
'Activity Based Management (ABM) - The broad discipline that focuses on achieving customer value and company profit by way of the management of activities. It draws on activity-based costing as a major source of information.'
'ACWP'
'Actual Cost of Work Performed - (ACWP) Total costs incurred (direct and indirect) in accomplishing work during a given time period. ACWP is used in the earned value method of progress measurement. See also earned value analysis.'
'ADM'
'Arrow Diagram Method (ADM) - One of two conventions used to represent an activity in a project. Also known as Activity on Arrow method.'
'ALAP'
'As-Late-As-Possible (ALAP) - An activity for which the application sets the early dates as late as possible without delaying the early dates of any successor.'
'AMR'
'Advanced Material Release (AMR) - A document used by organizations to initiate the purchase of long-lead-time or time-critical materials prior to the final release of a design.'
'APR'
'Acquisition Plan Review (APR) - The control gate to approve the Acquisition Plan. The APR is the decision point to initiate the project and commit funding
'ATP'
'Acceptance Test Procedure (ATP) - Detailed step-by-step instructions for the setup
'Abstract Resource'
'Imaginary resource introduced so that its availability and activity requirement gives an extra means of control. For example
'Acquisition Evaluation'
'Review and analysis of responses to determine supplier#s ability to perform the work as requested. This activity may include an evaluation of suppliers financial resources
'Acquisition Plan'
'The document that describes the approach for acquisition. It defines competitive or sole source
'Actual and Scheduled Progress'
'A comparison of the observable work done at a given time with the work planned up to that time.'
'Added Value'
'The addition of some worthwhile quality or performance improvement as a result of some action taken
'Aggregation'
'Summation of parts. Typically used in reference to estimating.'
'Allowable Cost'
'A cost that meets the tests of: Reasonableness
'Assumption'
'There may be external circumstances or events that must occur for the project to be successful. If you believe such an event is likely to happen
'Attrition'
'The loss of a resource due to causes beyond the jurisdiction of the project manager such as the death or resignation of an employee
'Avoidance'
'Keeping away from. Typically used as a risk reduction strategy by adopting a Workaround.'
'BAC'
'Baseline at Completion (BAC) - Total completed cost of work as originally planned.'
'BCWP'
'Budgeted Cost of Work Performed (BCWP) - The sum of the budgets for completed portions of in-process work
'BCWS'
'Budgeted Cost of Work Scheduled (BCWS) - The sum of the budgets for work scheduled to be accomplished (including in-process work)
'BEC'
'Budgeted Elapsed Cost'
'BOOT'
'Build
'Backcharge'
'The cost of corrective action taken by the purchaser
'Backward Pass'
'Calculation of the latest finish times by working from finish to start for the uncompleted portion of a network of activities.'
'Balanced Matrix'
'An organizational matrix where functions and projects have the same priority.'
'Balanced Scorecard Approach'
'(BSA) - A business methodology designed to assess the performance of an enterprise in more than just financial terms
'Barriers'
'Obstacles in the way of progress
'Baseline Cost'
'The amount of money an Activity was intended to cost when the Baseline Plan was established.'
'Baseline Schedule'
'A fixed project schedule that is the standard by which project performance is measured. The current schedule is copied into the baseline schedule which remains frozen until it is reset. Resetting the baseline is done when the scope of the project has bee
'Baseline'
'The value or condition against which all future measurements will be compared.'
'Baseline
budget'
'Benchmarking'
'The search for industry best practices that lead to superior performance.'
'Benefits Management Plan'
'A project statement of who is responsible for achieving the benefits
'Best Practices'
'Techniques that agencies may use to help detect problems in the acquisition
'Blanket Purchase Agreement'
'(BPA) - A simplified method of filling anticipated repetitive needs for supplies or services by establishing charge accounts with qualified sources of supply.'
'Bottom Up Cost Estimate'
'An estimate derived by summing detailed cost estimates of individual work packages (labor and materials) and applying appropriate cost burdens.'
'Breadboarding'
'The creation of an experimental device to determine the feasibility of an idea
'Breakdown Structure'
'A hierarchical structure by which project elements are broken down
'Bribe'
'A price
'Burn Rate'
'The rate at which funds or man-hours are being expended on a project.'
'Burst Node'
'In a network diagram
'CMM'
'Capability Maturity Model (CMM) - A description of the stages through which organizations evolve as they define
'CPFF'
'Cost Plus Fixed Fee Contract (CPFF) - A type of contract where the buyer reimburses the seller for the seller#s allowable costs plus a fixed fee.'
'CPI'
'Cost Performance Index (CPI) - The cost efficiency factor representing the relationship between the actual costs expended and the value of the physical work performed.'
'CPIFC'
'Cost Plus Incentive Fee Contract (CPIFC) - A type of Contract where the buyer reimburses the seller for the seller#s allowable costs and the seller earns a profit if defined criteria are met.'
'CPPC'
'Cost Plus Percentage of Cost Contract (CPPC) - Provides reimbursement of allowable cost of services performed plus an agreed upon percentage of the estimated cost as profit.'
'CV'
'Cost Variance'
'Calendar Unit'
'The smallest unit of time used in scheduling the project. Calendar units are generally in hours
'Carryover Type 1'
'A project fiscal expenditure management term. The sum of contractual commitments that must be paid in the next fiscal period arising from outstanding obligations including associated engineering and support costs.'
'Carryover Type 2'
'A project fiscal expenditure management term. That portion of Planned Future Expenditures contractually committed plus associated support costs which may be paid in the next fiscal period which would extend into the next fiscal year if the planned future
'Cascade Chart'
'Bar chart on which the vertical order of activities is such that each activity is dependent only on activities higher in the list.'
'Cash Flow Analysis'
'The activity of establishing cash flow (dollars in and out of the project) by month and the accumulated total cash flow for the project for the measurement of actual versus the budget costs. This is necessary to allow for funding of the project at the l
'Change Control'
'The review
'Change Management Plan'
'A defined process for making changes to a project plan.'
'Chart of Accounts'
'Any numbering system used to monitor project costs by category
'Child'
'A lower-level element in a hierarchical structure.'
'Closed Projects'
'Projects that have either been completed
'Closeout'
'The completion of all work on a project.'
'Coaching'
'The process of assisting people to improve their performance.'
'Collaboration'
'Working together
'Collapsing'
'In an outline
'Commission and Handover'
'The completion
'Commissioning'
'Advancement of an installation from the stage of static completion to full working order and achievement of the specified operational requirements.'
'Communication Channels'
'The path along which the exchange of information takes place or is supposed to take place. Typically refers to the sequence of individuals in a chain of command.'
'Component-Based Development'
'(CBD) - The creation and deployment of software-intensive systems assembled from components as well as the development and harvesting of such components.'
'Compromise'
'Both sides agree such that each wins or loses a few points.'
'Conditional Risk'
'Risk that occurs under certain conditions or is accepted provided that certain conditions are met.'
'Conflict Management'
'Handling of conflicts between project participants or groups in order to create optimal project results.'
'Conflict Resolution'
'To seek a solution to a problem
'Constraint'
'A restriction that must be balanced with all other constraints to achieve project success. The four primary and universal project constraints are scope
'Consultant'
'One who provides some specialized service based on their special qualifications
'Contingencies'
'Specific provision(s) to mitigate random or unknown project risks from causing project failure or frequent baseline changes.'
'Contingency Allowance'
'Specific provision to cover variations which may occur in the expected values of elements of cost or schedule
'Contingency Plan'
'A fallback position
'Contingency Reserve'
'A provision held by the project sponsor for possible changes in project scope or quality. Scope and quality changes constitute changes in the project manager#s mandate and will affect the project#s cost and schedule.'
'Contract Closeout'
'Contract closeout activities which assure that the contractor has fulfilled all contractual obligations and has released all claims and liens in connection with work performed.'
'Contract Risk'
'The potential and consideration of risk in procurement actions. Generally the forces of supply and demand determine who should have the maximum risk of contract performance but the objective is to place on the supplier the maximum performance risk while
'Contraints'
'Mostly time
'Control Gate'
'A major project milestone at which the project sponsor has the opportunity at the end of one phase of exercising a
'Control Theory'
'The view that motivation by goal setting can be further extended by understanding and predicting how humans process information and make decisions about how much effort to put forth. Based on metacognitive theory of motivation
'Controllable Risks'
'Those risks to the project which
'Coordinated Matrix'
'An organizational structure where the project leader reports to the functional manager and doesn#t have authority over team members from other departments.'
'Corporate Constraints'
'Limitations to the activities of a corporation. These may be as a result of the corporation#s charter
'Corporate Responsibility Matrix'
'A responsibility matrix depicted at the corporate level and from the corporate perspective.'
'Cost Analysis'
'The analysis of the cost elements of a proposal or on-going work. It includes verification of cost data
'Cost Avoidance'
'An action taken in the present designed to decrease costs in the future.'
'Cost Baseline'
'A time-phased budget used to measure and monitor cost performance. It is developed by summing estimated costs by period and is usually displayed in the form of an S curve.'
'Cost Benefit Analysis'
'An analysis of the relationship between the costs of undertaking a task or project
'Cost Control Point'
'The point within a program at which costs are entered and controlled. Frequently
'Cost Control System'
'Any system of keeping costs within the bounds of budgets or standards based upon work actually performed. Cost Control is typically a level in the budget element breakdown structure.'
'Cost Curve'
'A graph plotted against a horizontal time scale and cumulative cost vertical scale.'
'Cost Estimate Classification System'
'A five-level cost estimate system based on the amount of project information available developed by the American Association of Cost Engineers
'Cost Plus Fixed Fee Contract'
'(CPFF) - A form of contractual arrangement in which the customer agrees to reimburse the contractor#s actual costs
'Cost Plus Incentive Fee Contract'
'(CPIFC) A type of Contract where the buyer reimburses the seller for the seller#s allowable costs and the seller earns a profit if defined criteria are met.'
'Cost Plus Percentage of Cost Contract'
'Provides reimbursement of allowable cost of services performed plus an agreed upon percentage of the estimated cost as profit.'
'Cost Reimbursable Contract'
'A contract that provides for payment of allowable incurred costs
'Cost Types'
'Four different cost types are typically associated with the scope of work in a cost class. They reflect whether a cost is authorized
'Cost Variance'
'(CV) - The difference between the budgeted and actual cost of work performed.'
'Cost-Benefit Analysis'
'An analysis
'Countermeasures'
'Preventive actions that are chosen by the project team to reduce either scope or schedule risk.'
'Crash Costs'
'The cost of reducing an Activity to its Crash Duration.'
'Crashing'
'Action to decrease the duration of an activity or project by increasing the expenditure of resources.'
'Critical Factors'
'Favorable or adverse conditions that may exist or be expected that may significantly impact the course of a project. See also Critical Success Factors.'
'Critical Path Analysis'
'Procedure for calculating the critical path and floats in a network.'
'Critical Path Method'
'(CPM) - A technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility. Early dates are figured by a forward pass using a specific start date and late dates are figured by using a bac
'Critical Path'
'The series of tasks that must finish on time for the entire project to finish on schedule. Each task on the critical path is a critical task. In a network diagram
'Critical Task'
'A task that must finish on time for the entire project to finish on time. If a critical task is delayed
'Cross-Stage Plan'
'A detailed plan showing activities that span more than one stage in the project life cycle.'
'Cybernetics'
'The study of man-machine relationships to optimize output performance. Generally given inadequate attention on projects. See also Method Study.'
'Dangle'
'An activity in a network which has neither predecessors nor successors.'
'Decomposing'
'The process of reducing a project scope into its various elements resulting in a work breakdown structure.'
'Dependency Arrow'
'A link arrow used in an activity on node network to represent the interrelationships of activities in a project.'
'Dependency Diagram'
'Another name for a network or precedence diagram that shows the dependencies (precedence) between tasks.'
'Discrete Milestone'
'A milestone that has a definite scheduled occurrence in time.'
'Dual Concern Model'
'A graphical display in which the five negotiating strategies are plotted with Concern about Own Outcomes (X-axis) against Concern for Other Side#s Outcomes (Y-axis).'
'Dummy Activity'
'An activity of zero duration used to show a logical relationship in the arrow diagramming method. Dummy activities are used when logical relationships cannot be completely described with regular activity arrows. Dummies are shown graphically as a dashed
'Duration Compression'
'Shortening the project schedule without reducing the project scope. Duration compression is not always possible and often requires an increase in project cost.'
'Dynamic Baseline Model
'(DBM) - A conceptual model framework for: Exploring the evolution of project management behaviors
'EAC'
'EAC - Estimate at Completion. A value expressed in either dollars and/or hours
'ECC'
'Estimated Cost to Complete (ECC) - The remaining costs to be incurred to satisfy the complete scope of a project at a specific data date. The difference between the cost to date and the forecast final cost.'
'ETC'
'Estimate to Complete (ETC) - The value expressed in either dollars or hours developed to represent the cost of the work required to complete a task. The ETC is calculated as BAC - BCWP.'
'EVMS'
'Earned Value Management System - (EVMS) A management system and related sub-systems implemented to establish a relationship between cost
'Earned Value Analysis'
'Analysis of project progress where the actual money budgeted and spent is compared to the value of the work achieved.'
'Earned Value'
'A measure of the value of work performed so far. Earned value uses original estimates and progress-to-date to show whether the actual costs incurred are on budget and whether the tasks are ahead or behind the baseline plan.'
'Effort-Driven Activity'
'An activity whose duration is governed by resource usage and availability. The resource requiring the greatest time to complete the specified amount of work on the activity will determine its duration.'
'Elaboration'
'The second phase of the Unified Process in which the concept developed in the conception phase is funded for problem domain analysis
'End Tranche Assessment'
'A review carried out at the outset of the benefits realization phase to verify the completion of all tranche projects and to plan for maximizing benefits from tranche projects and executing the next tranche.'
'Essentials of Project Management'
'The four essentials of project management are: Common Vocabulary
'Estimate Class A'
'An estimate based on complete contract documents and used as a control check on authorized expenditures prior to tendering.'
'Estimate Class B'
'An estimate based on completed preliminary design drawings. Upon acceptance
'Estimate Class C'
'An estimate based on completion of all work necessary to undertake preliminary design. This estimate must be based on knowledge of site conditions adequate to enable the identification of site related risks and the development of corresponding contingenc
'Estimate Class D'
'An Order of Magnitude estimate only. In all cases
'Event-on-Node'
'A network diagramming technique in which events are represented by boxes (or nodes) connected by arrows to show the sequence in which the events are to be completed. Used in the original Program Evaluation and Review Technique.'
'Exculpatory Language'
'Language in the contract documents which purports to release the liability of one party for certain actions which may occur during the performance of the work.'
'Expected Value'
'(EV) - A way for comparing the values/costs of different scenarios
'Expediting'
'Facilitating and accelerating progress by the removal of obstacles.'
'Expert Power'
'The ability (of a project manager) to gain support because project personnel perceive the project manager as possessing special knowledge or expertise (that functional personnel consider important.)'
'FTC'
'Forecast to Completion (FTC) - Forecast To Completion is the cost to completion based upon the actual performance to date and assumes that the rate of expenditure continues as at present i.e. FTC = ACWP x 100 / % complete'
'Fast Tracking'
'Compressing the project schedule by doing some or all of certain activities in parallel that would normally be done in sequence (such as design and construction).'
'Feasibility Study'
'The methods and techniques used to examine technical and cost data to determine the economic potential and the practicality of project applications. It involves the use of techniques such as the time value of money so that projects may be evaluated and c
'Finish to Finish Lag'
'The minimum amount of time that must pass between the finish of one activity and the finish of its successor(s). All lags are calculated when a project has its schedule computed. Finish-to Finish lags are often used with Start-to-Start lags.'
'Finish to Start Lag'
'The minimum amount of time that must pass between the finish of one activity and the start of its successor(s). The default finish-to-start lag is zero. All lags are calculated when a project has its schedule computed. In most cases
'Firm Fixed Price Contract'
'(FFP) - A contract where the buyer pays a set amount to the seller regardless of that seller#s cost to complete the work.'
'Floating Task'
'A task that can be performed earlier or later in the schedule without
'Forcing'
'The project manager uses his power to direct the solution. This is a type of win-lose agreement where one side gets its way and the other does not.'
'Formal Authority'
'The ability (of a project manager) to gain support because project personnel perceive the project manager as being officially empowered to issue orders.'
'Forward Pass'
'Calculating the earliest start dates moving from left to right along a network.'
'Free Float'
'The maximum amount by which an activity can be delayed beyond its early dates without delaying any successor activity beyond its early dates.'
'Free Riding'
'A situation where some project team members do less work than the others.'
'Free Slack'
'The amount of time a task can slip without delaying another task. For a task without successors
'GERT'
'Graphical Evaluation and Review Technique (GERT) - A network analysis technique that allows for conditional and probabilistic treatment of logical relationships (i.e.
'Gantt Chart'
'A chart using time lines and other symbols that illustrates multiple
'Goal Setting Theory'
'The view that when a manger sets clear
'Hammock Activity'
'An Activity that spans between two points in a network. It has no duration of its own but derives one from the time difference between the two points to which it is connected.'
'Hanger'
'An unintended break in a network path.'
'Hard Project'
'A project that has a well defined physical product as its outcome as distinct from a soft project
'Harmonization'
'The process and/or results of adjusting differences or inconsistency to bring significant aspects into agreement.'
'Histogram'
'A graph showing resource usage on the vertical axis against time on the horizontal axis.'
'Hold Point'
'A defined step during processing when work must stop so that authorized inspection can be conducted and the work approved and released for further progress.'
'INCOTERMS'
'A set of international terms defining conditions for delivery and shipping of equipment and materials.'
'Impact
risk'
'Implied Warranty'
'The legal theory that when an owner requires a contractor to execute a project in accordance with plans and specifications supplied by the owner
'Imposed Date'
'A predetermined calendar date set (usually externally) without regard to logical considerations of the network.'
'Imposed Finish'
'A finish date imposed on an activity by external constraints.'
'Independent Float'
'The degree of flexibility which an activity has which does not affect the float available on any preceding or succeeding activities.'
'Inexcusable Delays'
'Project delays that are attributable to negligence on the part of the contractor which lead in many cases to penalty payments.'
'Initiation'
'The process of preparing for
'Input Restraints'
'Imposed external restraints
'Intangible Capital'
'The market value of the knowledge
'IBR'
'Integrated Baseline Review (IBR) - A joint PM/Customer review to understand and assess the adequacy
'Interactive Project Planning'
'Project planning carried out in active cooperation between project participants. Forms a contrast to project planning centralized in the project manager.'
'Investment Life-Cycle'
'The lifetime of a project deliverable from inception to ultimate termination. Often there is uncertainty about the length of time over which a project will be operating and assumptions will have to be made.'
'Key Success Indicators'
'(KSI) - Those project management indicators that: are determined at the beginning of the project and listed in order of priority
'Kickback'
'Any money
'Ladder'
'Device for representing a set of overlapping activities in a network diagram.'
'Lag Time'
'The amount of time delay between the completion of one task and the start of its successor task.'
'Lag'
'The amount of time after one task is started or finished before the next task can be started or finished.'
'Legacy Thinking'
'Wedded to outmoded concepts and practices.'
'Level Float'
'The difference between the level finish and the late finish date.'
'Loop'
'A path in a network closed on itself passing through any node more than once on any given path. The network cannot be analyzed
'MIS Quality Requirements'
'The process of organizing a project#s objectives
'Management Reserve'
'(MR) - An amount of the owner#s total allocated budget withheld under the owner#s management control
'Management Styles - Authoritarian'
'Lets individuals know what is expected of them
'Management Styles - Combative'
'project manager that is marked by an eagerness to fight or be disagreeable over any given situation.'
'Management Styles - Conciliatory'
'A project manager that is friendly and agreeable; one that attempts to assemble and unite all project parties involved to provide a compatible working team.'
'Management Styles - Disruptive'
'A project manager that tends to break apart the unity of a group
'Management Styles - Ethical'
'A project manager that is honest
'Management Styles - Facilitating'
'The project manager is available to answer questions and give guidance when needed; he does not interfere with day to day tasks
'Management Styles - Intimidating'
'A project manager that frequently reprimands employees for the sake of an image as a tough guy
'Management Styles - Judicial'
'A project manager that exercises the use of sound judgment or is characterized by applying sound judgment to most areas of the project.'
'Management Styles - Promotional'
'Encourages subordinates to realize their full potential
'Management Styles - Secretive'
'A project manager that is not open or outgoing in speech activity
'Management by Exception'
'The issue of management reports to responsible managers only when action is called for. This helps the manager to avoid wading through voluminous reports where progress is going according to plan. However
'Management by Methods'
'(MBM) - Level 2 of a five level Dynamic Baseline Model in which those proficient in MBR build on their knowledge base
'Management by Objectives'
'(MBO) - A management theory that calls for managing people based on documented work statements mutually agreed to by manager and subordinate. Progress on these work statements is periodically reviewed
'Management by Politics'
'(MBP) - A potential Level 5 of a five level Dynamic Baseline Model structure. This is an extrapolation of the model which would lead to a management approach where the essential values of the corporation are a dynamic baseline. This would entail dealing
'Management by Project'
'A term that is gaining popularity
'Management by Rules'
'(MBR) - Level 1 of a five level Dynamic Baseline Model structure at which behavior
'Management by Threshold'
'A system approach in which deviation limits or thresholds for key parameters are set relative to the baseline plan. When thresholds are exceeded the system alerts management to review and take corrective action. Such a system is intended to avoid the nec
'Management by Values'
'(MBV) - Level 4 of a five level Dynamic Baseline Model structure in which an employee has the capacity to manipulate and evolve the objective throughout the project life cycle as appropriate to the overarching corporate values. MBV practitioners are expe
'Management by Walking Around'
'(MBWA) - Part of the Hewlett Packard legacy and popularized by management theorist Tom Peters. MBWA works on the assumption that a manager must circulate to fully understand the team#s performance and problems. The best managers
'Matrix Organization'
'A combination of the advantages of the pure functional (traditional) structure and the product organizational structure. The project manager has total responsibility and accountability for project success
'Maturity Model'
'A published framework as a basis for determining the degree of maturity of an organization
'Milestone'
'A point in time representing a key or important intermediate event in the life of a project. A milestone should be capable of validation by meeting all of the items prescribed in a defining checklist as agreed with the stakeholders.'
'Mixed Organization'
'This organizational structure includes functional groups
'Negative Float'
'The amount of time by which the early date of an activity exceeds its late date.'
'Network Diagram'
'A schematic display of the sequential and logical relationship of the activities which comprise the project. Two popular drawing conventions or notations for scheduling are arrow and precedence diagramming.'
'Network Logic'
'The collection of activity dependencies that make up a project network diagram.'
'Node'
'The start and end of activities in an activity on arrow network or the activity box in a precedence network.'
'Normal Probability Distribution'
'The continuous distribution most commonly used in statistics to make inferences about a population from sample data.'
'Object-Oriented Analysis'
'Analysis based on considering the system as a collection of objects (entities
'Order of Magnitude Estimate'
'(Accuracy -25
'Organizational Breakdown Structure'
'(OBS) - A hierarchical structure designed to pinpoint the area of an organization responsible for each part of a project.'
'Organizational Factors'
'The availability of expertise of personnel
'Overrun'
'An increase in the time or cost compared to the plan. A reduced scope without a corresponding reduction in the time or cost would be considered an overrun.'
'PMBoK'
'Project Management Body of Knowledge - (PMBoK) An inclusive term that describes the sum of knowledge within the profession of project management. As with other professions such as law and medicine
'Parametric Cost Estimating'
'Appraising the costs of a project based on knowledge gathered from similar
'Parametric Estimating'
'An estimating technique that uses a statistical relationship between historical data and other variables (e.g.
'Pareto Diagram'
'A histogram
'Project Life Cycle'
' The four sequential major time periods through which any project passes
'Project Log'
'A project diary. A chronological record of significant occurrences throughout the project.'
'Project Manager'
'(PM) - The person who heads up the project team and is assigned the authority and responsibility for conducting the project and meeting project objectives through project management.'
'Project Matrix'
'An organization matrix that is project based in which the functional structures are duplicated in each project.'
'Project Monitoring '
'Comparison of current project status with what was planned to be done to identify and report any deviations.'
'Project Office'
'A designated location where the administrative work of the project is conducted and the project management skills (resources) such as cost accounting
'Project Oriented'
'Typically organizations who have a predisposition to use projects as their corporate business approach
'Project Portfolio'
'The projects included in a particular program.'
'Project Progress Report'
'Formal statement that compares the project progress
'Project Records Management'
'The system and procedures established by the Company for the consistent and effective storage and retrieval of all project information for the efficient use by the project manager and his/her project Team.'
'Project Reporting'
'A planning activity involved with the development and issuance of (internal) TIME management analysis reports and (external) progress reports.'
'Project Risk Management'
'The process of identification
'Project Risk'
'The cumulative effect of the chances of uncertain occurrences which will adversely affect project objectives. It is the degree of exposure to negative events and their probable consequences. Project risk is characterized by three factors: risk event
'Project Schedule'
'Planned dates for starting and completing activities and milestones.'
'Project Scope Management'
'A subset of project management that includes initiation
'Project Scope'
'A concise and accurate description of the end products or deliverables to be expected from the project and that meet specified requirements as agreed between the Project
'Project Stakeholder'
'A person
'Project Standard'
'A norm
'Project Status Report'
'A report on the status of accomplishments and any variances to spending and schedule plans.'
'Project constraint'
'A factor that will limit the project management team#s options. For example
'Punishment of the Innocent'
'A humorous reference to what is perceived to happen when projects go wrong and scapegoats are found.'
'Purchasing Strategy'
'To the extent that there may be alternative approaches
'Qualitative Risk Analysis'
'A generic term for subjective methods of assessing risks.'
'Quality Assurance Plan'
'A plan that guarantees a quality approach and conformance to all customer requirements for all activities in a project.'
'Quality Assurance'
'All those planned and systematic actions necessary to provide adequate confidence that a product or service will satisfy given requirements for quality.'
'Quality Audit'
'A systematic and independent examination to determine whether quality activities and related results comply with planned arrangements and whether these arrangements are implemented effectively and are suitable to achieve objectives.'
'Quality Criteria'
'The characteristics of a product that determines whether it meets certain requirements.'
'Quality Plan'
'A document setting out the specific quality practices
'Quantitative Control'
'Any quantitative or statistically-based technique appropriate to analyze a software acquisition process
'RAM'
'Responsibility Assignment Matrix (RAM) - The RAM correlates the work required by a Contract Work Breakdown Structure (CWBS) element to the functional organization responsible for accomplishing the assigned tasks. The responsibility assignment matrix is
'RF'
'Remaining Float - The difference between the early finish and the late finish date.'
'RFP'
'Request for Proposal - A formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form the basis of a contract.'
'ROI'
'Return on Investment (ROI) - The financial return for a given outlay
'Re-baseline'
'Development of a revised implementation plan with new milestone schedules. Re-baselining is required in response to changed contract requirements
'Readiness Assessment'
'A meeting or series of meetings by selected members of the customer C/SCSC review team at a contractor
'Recovery Schedule'
'A special schedule showing special efforts to recover time lost compared to the master schedule.'
'Recurring Costs'
'Expenditures against specific tasks that would occur on a repetitive basis. Examples are sustaining engineering
'Reengineering'
'The process of redesigning a product
'Referent Power'
'The ability (of a project manager) to gain support because project personnel feel personally attracted to the manager or the project.'
'Regression Analysis'
'Where past data is insufficient for direct forecasting of future levels of activity it may still be possible to make assumptions based on relationships with other activities that can be forecast. This applies particularly to apportioned-effort tasks and
'Regulations'
'Rules or orders issued by an executive authority or regulatory agency of a government and having the force of law.'
'Remaining Available Resource'
'The difference between the resource availability pool and the level schedule resource requirements. Computed from the resource allocation process.'
'Replacement Theory'
'A statistical methodology for arriving at the optimum life of replaceable elements in a project. It considers replacement cost
'Requirement'
'A description of a condition or capability to which a system must conform; either derived directly from user needs
'Requirements Traceability Matrix'
'A document that maps the parent-child relationships of requirements.'
'Requirements Traceability'
'The management of the parent/child relationships of all system requirements.'
'Reserve'
'A provision in the project plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g.
'Residual Risks'
'Those risks which are not avoided
'Resource Constraint'
'Limitation due to the availability of a resource.'
'Resource Optimization'
'A generic term for resource leveling and resource smoothing.'
'Resourcing Plan'
'Part of the definition statement stating how the program will be resource loaded and what supporting services
'Response Planning'
'The process of formulating suitable risk management strategies for the project
'Risk & Readiness Assessment'
'An evaluation
'Risk Analysis'
'An examination of risk areas or events to assess the probable consequences for each event
'Risk Assessment'
'The process of identifying potential risks
'Risk Assumption'
'Risk assumption is an acknowledgment of the existence of a particular risk situation and a conscious decision to accept the associated level of risk
'Risk Avoidance'
'The process of planning activities so as to avoid identified risks by using an alternative method.'
'Risk Management Plan'
'A document defining how Project Risk Analysis and Management is to be implemented in the context of a particular project.'
'Risk Management'
'An organized assessment and control of project risks.'
'Risk Matrix'
'A matrix with risks located in rows
'Risk Mitigation Strategy'
'An overall plan for mitigating the risks in the investment activity.'
'Risk Mitigation'
'The act of revising the project#s scope
'Risk Quantification'
'Process of applying values to the various aspects of a risk.'
'Risk Response Plan'
'A plan (prepared towards the end of the risk review) for controlling the risks once implementation begins.'
'Risk Response'
'The planned or actual action in response to a risk event.'
'Risk Sharing'
'Diminution of a risk by sharing it with others
'Risk Transfer'
'A contractual arrangement between two parties for delivery and acceptance of a product where the liability for the costs of a risk is be transferred from one party to the other.'
'Risk'
'The probability of an undesirable outcome.'
'Rolling Wave'
'A term used in scheduling to imply detailed planning or scheduling over a short horizon. Each period
'Rough Order of Magnitude Estimate'
'(ROM) - Estimated cost based on approximate cost models or expert analysis. It is usually based on top level requirements or specifications
'Runaway Project'
'A term coined by the consultancy KPMG to identify mainly IT projects which resist termination. Typified by a constantly changing specification and absorption of much extra resource and cost in a desperate effort to get the project finished.'
'S Curve'
'A display of cumulative costs
'SC'
'Scheduled Cost (SC) - The total cost of work when completed as calculated according to the current schedule.'
'SF'
'Scheduled Finish (SF) - The date calculated by the resource scheduling program as the earliest date on which an activity can finish
'SOW'
'Statement of Work - A narrative description of the work to be performed.'
'SPI'
'Scheduled Performance Indicator (SPI) - The ratio of BCWP to BCWS i.e. SPI = BCWP / BCWS. A positive value (i.e. greater than 1) indicates that work is ahead of schedule. A negative value (i.e. less than 1) indicates that work is behind schedule.'
'SV'
'Schedule Variance (SV) - Either Any difference between the scheduled completion of an activity and the actual completion of that activity
'SWOT Analysis'
'A process whereby a group of people determine: Strengths - What Strengths do we have? (How can we take advantage of them?)
'Sample Size'
'The number of units of product in the sample selected for inspection.'
'Sampling Frequency'
'(f) - The sampling frequency
'Sampling'
'The technique of selecting a representative part of a population for the purpose of determining parameters or characteristics of the whole population. A small part selected as a sample for inspection or analysis.'
'Scanning'
'Investigating or examining thoroughly by checking point-by-point and often repeatedly.'
'Scenario Planning'
'The planning of responses
'Schedule Refinement'
'The rework
'Schedule Risk'
'The potential problems the team might encounter in meeting the deadlines for the final deliverable.'
'Scope Changes'
'Any change in the project#s deliverables from that which was originally intended
'Scope Constraints'
'Applicable restrictions which will affect the scope.'
'Scope Creep'
'On-going requirements increase without corresponding adjustment of approved cost and schedule allowances. As some projects progress
'Scope Criteria'
'Standards or rules composed of parameters to be considered in defining the project.'
'Scope Definition'
'Breaking down a deliverable in to smaller manageable parts to ensure better control.'
'Scope Management'
'The function of controlling a project in terms of its goals and objectives through the processes of conceptual development
'Scope Risk'
'The potential problems the team might encounter in creation of a final deliverable. Also known as technical risk.'
'Scope Verification'
'Ensuring all identified project deliverables have been completed satisfactorily.'
'Scope'
'The definition that describes the project#s product deliverables. See also Managing Scope.'
'Screening'
'Techniques used for reviewing
'Secondary Float'
'(SF) - The difference between the CPM calculated early finish and the imposed finish date.'
'Self-Inspection'
'A service by a company or organization that is responsible for inspection of its own work.'
'Show Stopper'
'An event or condition serious enough to halt or severely impede a project unless confronted and eliminated.'
'Slip Chart'
'A pictorial representation of the predicted completion dates of milestones (also referred to as Trend Chart.'
'Slippage'
'The amount of time a task has been delayed from its original baseline plan. The slippage is the difference between the scheduled start or finish date for a task and the baseline start or finish date. Slippage can occur when a baseline plan is set and th
'Smoothing'
'Differences between two groups are played down and the strong points of agreement are given the most attention.'
'Soft Project'
'A project which is intended to bring about some form of change
'Sole Sourcing'
'The acquisition of supplies or services after soliciting and negotiating with only one source.'
'Splitting'
'In resource scheduling
'Sponsor'
'The executive who manages
'Stabilization'
'The period of time between continuous operation and normal operation. This period encompasses those activities necessary to establish reliable operation at design conditions of capacity
'Stand Alone'
'A system which performs its function requiring little or no assistance from interfacing systems.'
'Standard Cost'
'The normal expected cost of an operation
'Standard Deviation'
'A measure of the dispersion of possible outcomes. Mathematically
'Standard Project Cost Accounting'
'The standards associated with a project cost accounting system. Unlike the Generally Accepted Accounting Principles (GAAP) of corporate accounting
'Standard'
'A specific statement of the rules and constraints governing the naming
'Standards'
'Established or accepted rules
'Statistical Quality Control'
'Various statistical methods and relationships are available for determining performance quality and the adjustment necessary to achieve specified results. Used particularly in the sampling of high volume materials such as steel and concrete strengths
'Statistics'
'The mathematical methods used to determine the best range of probable values for a project and to assess the degree of accuracy or allowance for unpredictable future events such as accidents
'Status Report'
'A written report given to both the project team and to a responsible person on a regular basis stating the position of an activity
'Steering Committee'
'Formal group representing the owner or client.'
'Storming'
'The second stage of team building where conflicts arise as members of the group try to exert leadership and exert influence over methods of operation.'
'Strategic Risk'
'Any risk event which has serious or catastrophic consequences even though the probability of occurrence may be quite low.'
'Sunk Costs'
'Costs which could not be avoided even if the project were to be terminated.'
'TAB'
'Total Allocated Budget (TAB) - The sum of all budgets allocated to a contract. Total Allocated Budget consists of the performance measurement baseline plus all management or contingency reserves. The TAB will reconcile directly to the Contract Budget Ba
'TAE'
'Total Anticipated Expenditures (TAE) - The sum of work-to-date plus obligations plus planned future expenditures
'TQM'
'Total Quality Management (TQM) - A strategic
'Team Building'
'The process of influencing a group of diverse individuals
'Termination for Convenience'
'A unilateral right of the buyer to terminate any or all of a contractual effort for any reason at any time.'
'Termination for Default'
'Buyer action to cancel a procurement that is not meeting contract requirements. Default relates to failure of the contractor to perform contract work within the specified time or any other provisions of the contract.'
'Test Plan'
'A description of the tests needed to complete a project properly.'
'Thresholds'
'Monetary
'Tiger Team'
'A team established to focus on visibility
'Time Box'
'The calendar limits within which an activity is required or expected to occur.'
'Top Down Cost Estimating'
'The preparation of a cost estimate by using judgment and experience to arrive at an overall total amount
'Tracking'
'Collecting actual time
'Tranche'
'A block of work within the program
'Transit Time'
'Dependency link that requires time and no other resources. It may be a negative time.'
'Transition Plan'
'Part of the program definition statement that describes how the transition from the current business operation to the new environment of the blueprint will be managed.'
'Trend Line'
'A line on a schedule or chart showing the pattern of progress that is being set over time
'Trial Balloon'
'A tentative plan offered to test the reaction of a particular audience.'
'Triple Constraint'
'The term used to describe the three key project objectives that must be simultaneously accomplished
'Turnaround Report'
'A report created especially for the various responsible managers to enter their progress status against a list of activities that are scheduled to be in progress during a particular time window.'
'Undistributed Budget'
'(UB) - Budget applicable to contract effort which has not yet been identified to specific cost accounts or work packages.'
'Usage Variance'
'The difference between the budgeted quantity of materials and the actual quantity used.'
'VAC'
'Variance at Completion - (VAC) The budget at completion less the estimate at completion. A negative result indicates that the project is over budget.'
'Value Analysis'
'An activity devoted to optimizing cost performance. It is the systematic use of techniques which identify the required functions of an item
'Variance Threshold'
'The amount of a variance which will require a formal problem analysis report
'Venn Diagram'
'A diagram in which closed circles represent separately identifiable sets and their logical commonality or distinction by the inclusion
'Virtual Collocation'
'An arrangement whereby project team members meet as often as necessary through teleconferencing. This arrangement has been made necessary for companies who operate globally
'WBS Dictionary'
'A document that describes each element in the WBS including a Statement of Work (SOW)
'WBS'
'Work Breakdown Structure (WBS) - A task oriented detailed breakdown
'Wet and Dry Test Runs'
'A procedure for testing plant and equipment prior to full commissioning. Dry test runs imply tests without product throughput
'What-If Analysis'
'The process of evaluating alternative strategies.'
'Work Acceptance'
'Work is considered accepted when it is conducted