Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/9

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

9 Cards in this Set

  • Front
  • Back

Three terms commonly used to refer to a layout where similar equipment or functions are grouped together.

Workcenter, job-shop, or functional

A layout where the work to make an item is arranged in progressive steps and work is moved between the steps at fixed intervals of time.

Assembly Line

A measure to evaluate a work center layout.

Number of annual movements multiplied by the distance of each movement, and then multiple by the cost.

This is a way to shorten the cycle time for an assembly line that has a task time that is longer than the desired cycle time. Assume that it is not possible to speed up the task, split the task, use overtime, or redesign the task.

Use parallel workstation.

This involves scheduling several different models of a product to be produced over a given day or week on the same line in a cyclical fashion.

Mixed-model line balancing.

If you wanted to produce 20 percent of one product (A), 50 percent of another (B), and 30 percent of a third product (C) in cyclic fashion, what schedule would you suggest.

AABBBBBCCC (then repeat)

A term used to refer to the physical surroundings in which a service takes place and how these surrounding affect customers and employees.

Servicescape

A firm is using an assembly line and needs to produce 500 units using an eight-hour day. what is the required cycle time in seconds?

57.6 seconds = (8x60x60)/500

What is the efficiency of an assembly line that has 25 workers and a cycle time of 45 seconds? Each unit produced on the line has 16 minutes of work?

85% = (16x60)/(25x45)