Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
49 Cards in this Set
- Front
- Back
Process Lead Time (PLT)
|
The time from release of a product into a process until its completion
Example: The elapsed time from when a homeowner calls, to when the mortgage refinancing closes averages 33 days. |
|
Work-In-Process (WIP):
|
): Product that is within the boundaries of the process
Example: There were 3300 refinance applications in process at the end of the month. |
|
Exit Rate (Throughput)
|
The output of a process over a defined period of time. It’s a rate.
Example: Our process closed 100 mortgage refinance applications per day last month |
|
Little’s Law
|
PLT = WIP/Exit Rate
|
|
Process Cycle Efficiency (PCE)
|
PCE is a measure of the relative efficiency in a process – it represents the percentage of value add time (changing form, fit, function) of a product along the critical path.
It is calculated using: Process Cycle Efficiency = (Customer Value Add Time/PLT)*100 |
|
Benefits of a Work Control System
|
The primary goals of a work control system are to stabilize then reduce process lead time and lead time variability
|
|
Foundation for Lean Improvements
|
Lean seeks to reduce process lead time.
o To reduce Process Lead Time, you either have to increase Exit Rate or reduce Work In Process – both require process improvements to improve process parameters o To reduce Process Lead Time, first investigate the relationship between process parameters like setup time, scrap, downtime, etc. and Work in Process o Then, for a given amount of demand per part, we can calculate the optimum amount of Work In Process needed to minimize the Process Lead Time ☺ Then we can… o Find the part of the process that introduces the most time delay, in order to reduce Process Lead Time |
|
Work Control Systems
|
The primary goals of a work control system are to stabilize then reduce process lead time and lead time variability
Fundamental Principle – Start Rate = Exit Rate Fixed WIP Improves Flexibility |
|
How to Size a Work Control System:
Step 1. Determine current Process Lead Time (PLT) |
PLT = minute, hour day
WIP is the Stuff ER = Qty output by time PLT=WIP/ER or PLT x ER = WIP or ER = WIP/PLT |
|
Step 2. Determine current Process Cycle Efficiency (PCE):
|
PCE% = Customer Value Add Time/PLT x (100)
|
|
How to Size a Work Control System
Step 3. Identify appropriate target PCE |
Rules of Thumb:
If current PCE is << Low End Target, multiply current PCE by 10 (one order of magnitude improvement) for use as Target to be conservative. If current PCE is < Low End Target, use Low End as Target PCE If current PCE @ or > Low End Target, use High End as Target PCE |
|
How to Size a Work Control System
Step 4. Calculate theoretical best PLT |
PLTtb = CVA TIme/Target PCE
|
|
How to Size a Work Control System
Step 5 Calculate WIP cap |
The WIP Cap…determines the maximum WIP allowed within the process at any time. It is measured as:
WIP Cap = PLTtb x ER |
|
Different Formulas used in sizing a work control system
|
PLT = WIP/ER, also CVA/PCE
ER = WIP/PLT PCE = CVA/PLT WIP = PLT*ER PLTTB = CVA/Target PCE WIPCAP = PLTTB * ER |
|
Value of Speed & Work Control Systems
|
Primary Goal is to stabilize then reduce process lead time and lead time variability
Benefit is a more manageable process with controllable WIP levels |
|
Quick Improvement – 5S
|
Sort
Set in Order Shine Standardize Sustain |
|
5S - Sort
|
Sort means that you remove all items from the workplace that are not needed for current tasks.
|
|
5S - Sit in Order
|
arrange the items that are needed in the area and identify them or label them so that anyone can find them or put them away.
|
|
Change Reduction
|
Document the Set-up and seperate into serial and parallel events.
-Serial event – an activity that cannot (or should not) be performed while any other task is being completed -Parallel event - is an activity that could be performed while another task is being completed Convert Serial events to parallel. Streamline remaining serial events Eliminate adjustments |
|
Brainstorming
|
Brainstorming is a structured method of generating unconstrained ideas/solutions and gaining engagement/involvement in the improvement process.
Brainstorming produces many ideas/solutions in a short time. Brainstorming facilitates the creative thinking process. |
|
Affinity
|
A tool for organizing facts, opinions and issues into natural groups as an aid to diagnosing a complex problem
Helpful when a breakthrough is needed Helps organize ideas, concepts and/or facts Allows the development of central themes |
|
Cause & Effect (C&E)
|
Represents the relationship between an effect (problem) and its potential causes. Categorizes causes.
Helps ensure that a balanced list of ideas have been generated during brainstorming. Helps us overcome the “theme” or “group think” effect. When you have identified major causes, ask “Why?” five times to develop more detailed causes |
|
Nominal Group Technique (NGT)
|
NGT supplements brainstorming. It is a structured approach to generate additional ideas, survey the opinions of a small group, and prioritize brainstormed ideas
Structured to focus on problems, not people; to open lines of communication; tolerate conflicting ideas Builds consensus and commitment to the final result. Especially good for highly controversial issues. |
|
Force Field Analysis
|
A tool to help a team understand the forces that keep things the way they are so it can make change possible
Forces creative thinking focused on the issues of change List all of the driving forces (direct movement toward a goal) and all the restraining forces (block movement toward a goal). Establish a plan to eliminate or diminish some or all of the restraining forces |
|
C&E Matrix
|
The C&E matrix is a team tool used to focus in on the process steps and/or inputs that potentially have the greatest effects on CCRs.
Customer requirements are ranked by order of importance and then inputs and outputs are rated by their interaction impact. Numbers show strength of relationship between step/input and CCR. blank = no correlation 1 = remote correlation 3 = moderate correlation 9 = strong correlation Note: When matrix is complete 50-60% of cells should be blank. Totals show importance of each step/input. Use these numbers to focus on most important steps/inputs |
|
Hypotheses Testing
|
A sample is taken to make inferences about a population when it is not practical or possible to measure/query every item/person in the population.
In order to make those inferences, the sample must be representative of the population. Confidence Intervals for a sample statistic define the range of values in which we can expect to find the population parameter at a given Confidence Level. (e.g. When we specify a 95% Confidence Level, we are 95% confident that the population mean, also known as a parameter, falls within the confidence interval about a sample mean.) |
|
Null Hypothesis (Ho) & Alternative (Ha)
|
(H0) is a statement we assume is “true” unless we have enough evidence to prove otherwise
If we cannot prove otherwise, then we fail to reject the null hypothesis If we can prove otherwise, then we reject the null hypothesis and accept the alternative hypothesis (Ha) How will we know if Ho is likely to be true? If the p-value is less than or equal to a pre-selected level of significance (a - level), then we reject Ho and accept Ha. If the p-value is greater than the a - level, then we fail to reject Ho and cannot support Ha. “If P is low then H0 must go!” The p-value is the probability we are wrong if we reject the Ho(null hypothesis |
|
Contingency Table
|
The two categorical variables are usually a Y and an X, but not always. Can be two Y’s, two X’s, etc. However, they must be discrete.
Contingency Analysis is used to test the association between a discrete “X” and a discrete “Y |
|
Analysis of Variance (ANOVA):
|
is a statistical method for comparing the means of three or more levels of a discrete factor (X). In our case the factor is the site, i.e., PR05, Sesto, etc
|
|
Process Flow Improvement:
|
Process Flow Improvement follows a definite path that includes decision criteria to identify both the appropriate process improvement tool to apply, and when.
If the current process capacity is unable to meet customer demand, then the constraint operation must be identified and eliminated as a capacity constraint. If the process is simply unbalanced (different workloads for different steps), then it needs to be balanced. |
|
Time Trap
|
The process step that inserts the most delay in to the process.
Example: Our sample preparation group prepares 120 samples per day, all other process steps can process 145 samples per day |
|
Constraint
|
A process step that is unable to produce at the exit rate required to meet customer demand (internal or external
|
|
Process Flow Improvement Hierarchy
|
Process is not meeting customer demand
Use process constraint identification Process is meeting customer demand, but the tasks/work loads are not balanced Use process balancing Tasks are balanced, but there is too much movement of information/material Use CVA / BVA / NVA analysis Process has limited movement, but has too much NVA time Use CVA / BVA / NVA analysis |
|
Lean improvement in ‘DMAICV’
|
Document and measure the process (D,M)
Analyze the process for improvement (A) Apply process flow improvement techniques (I) Standardize Operations (C) |
|
Solution Generation
|
We’ll use this process to generate Great solutions:
Step 1 – Generate Solution Ideas Step 2 – Reduce the List of Potential Solutions and Develop Solution Concepts Step 3 – Evaluate and Prioritize Solution Concepts against established Criteria (use your CCRs and CBRs); and Step 4 – Tie Together: Synthesize Better Solution Concepts and Iterate |
|
Analytical Hierarchy Process (AHP)
|
AHP has many uses, but is most effective in determining the relative importance of evaluation criteria
It converts subjective assessments of relative importance into a set of overall scores or weights The fundamental input to the AHP is the team’s answers to a series of questions of the general form, “How important is criterion A relative to criterion B?” |
|
PUGH- Weight the Evaluation Criteria based on importance
|
Using a numeric scale (often 1 to 5, but it doesn’t matter), rank the criteria in terms of relative importance
Good opportunity to utilize pair wise comparisons and the Analytical Hierarchy Process to determine weights for the evaluation criteria Be sure to discuss the criteria and the weighting with the sponsor – if you agree in the criteria and weighting, you should agree on the result. |
|
PUGH- Prepare Evaluation matrix
|
Compare each of the alternatives against the BASELINE
|
|
Random Word
|
This technique helps teams approach problems from different perspectives rather than through patterned ways of thinking
|
|
20 Questions
|
Useful to “tear apart” an existing process or service and challenge all current assumptions prior to developing the next generation
|
|
Process Balancing
|
Process Balancing” is a procedure whereby a set of process steps are “equalized” in terms of time required to accomplish them
|
|
Process Flow Improvement Decision Hierarchy
|
Process is not meeting customer demand
Use process constraint identification 2. Process is meeting customer demand, but the tasks/work loads are not balanced Use process balancing 3. Tasks are balanced, but there is too much movement of information/material Use CVA / BVA / NVA analysis 4. Process has limited movement, but has too much NVA time Use CVA / BVA / NVA analysis |
|
Process Flow Hierarchy key Item
|
Remember, CVA / BVA / NVA analysis
is a part of EVERY Lean process improvement |
|
GREaT solutions
|
Step 1 – Generate Solution Ideas
Step 2 – Reduce the List of Potential Solutions and Develop Solution Concepts Step 3 – Evaluate and Prioritize Solution Concepts against established Criteria (use your CCRs and CBRs); and Step 4 – Tie Together: Synthesize Better Solution Concepts and Iterate |
|
Mistake Proofing
|
• A method which makes it very difficult or impossible to produce defective work
|
|
FMEA (Failure Modes and Effects Analysis)
|
Examine the implications of a solution or redesigned process
Plan for unintended consequences related to your solution before you implement or promote it. |
|
Steps of a Pilot
|
Conduct a Design Review
Set the Pilot Plan and Timeline Prepare All Stakeholders Run the Pilot Summarize the Pilot Conclusions |
|
Project Risk management
|
Project Risk Management is a comprehensive
means to proactively Identify, Assess, and Mitigate the risks related to your project |
|
Project Risk Elements
|
Project Risk Management consists of four primary elements:
Initial Risk Analysis: Risks related to successful project completion (schedule and results) Business Risk Management: Potential risks resulting from the planned solution and implementation plan on the business and its customers Organizational Acceptance Risk Management: Risks related to lack of cultural buy-in for the proposed solution and implementation Sustainment Risk Management: Risks related to sustaining the project gains over the long-term |