The Downfalls Of Project Scope Management

Great Essays
Register to read the introduction… Fulfilling this Knowledge Area ensures that the project manager has an understanding of all the work or tasks the project entails. It can be further refined by having other opinions of the task lists from a quantifiable description of the project. Knowing most of the tasks at an early stage usually highlights and triggers changes that would need to be made before resources are wasted on them. One of the downfalls of the project is the Top Down approach when considering workloads. The DPA’s IT Support Manager underestimated the tasks associated with developing the software systems. The two consultants were still reporting directly to him, even though he had no experience in this field and might not have been able to steer the project successfully. Taz and Jeremy should have been more instrumental together with the IT support manager in assessing the work loads. There was no project plan or scope formulated by the project director or the IT consultants because the project director assumed that Jeremy formulated it and Jeremy was of the opinion that he did not need to have an official plan, but a plan in his mind was sufficient. Having taken this approach, Jeremy’s plan was not exposed to the team for constructive criticism and the element of human error was encouraged. Early formal definition of a project scope is a very effective technique of ensuring that projects run …show more content…
Sequencing tasks based on individual task duration, ability of tasks to run concurrent with other tasks, predecessors of tasks, strategic scheduling and controlling of tasks are all elements that need to be considered when managing time in any project. A Proactive approach for time allocation – “working on plans that are beyond the timeframe of ‘that which needs to be done immediately’ with the emphasis on ‘problem prevention’ ( Harvey Maylor 4th Edition pg 270). This approach on time management is designed to save time in the initiating stages of any project. Without considering a task list or any form of initial planning the DPA and Regional Sales Centers deemed an arbitrary project duration of 3 to 4 months. Additionally the Project Director nominated by the head of the DPA only worked 2 days / week on the project and had a significant amount of persons reporting to him. This type of work schedule creates disconnects and loss of focus. Considering the criticality of the project, a fully committed Project Director may have been a wiser choice. Breakdown structures should have been initially employed to allow for better control of tasks and containment of risk. Implementing Organization Breakdown Structure techniques coupled with Work Breakdown Structure “Chunking” (Lecturer’s Notes), would have highlighted possible continuity issues such as Jeremy and Taz not being able to meet the “go live” date due to the underestimation of the quantity of work to be done on the

Related Documents

  • Improved Essays

    International project management is when a project takes place in more than one foreign country (What is International, n.d.). There are particular skills and knowledge that is needed to be able to conduct business in different nations such as; knowing and understanding the local regulations, customs, and laws and having the ability to facilitate transactions involving multiple currencies (What is International, n.d.). International projects may operate in similar methods as domestic projects; they may also offer some opportunities when crafting a statement of work; they may require a special set of leadership skills for project managers; and they may impact a variety of aspect related to project management. Statement of Work…

    • 1655 Words
    • 7 Pages
    Improved Essays
  • Decent Essays

    Staff members are not given much information if any at all with regards to targets, time limits, and goals when they are assigned projects. The result has been missed deadlines, foolish spending, and deteriorating the morale of the staff. The solution for management is that they simply have to put forth an extra effort in arranging projects and responsibilities rendering to their goals. CanGo has to contemplate the possibilities of training managers and employees in Project Management software like Microsoft Project, which provides a schedule to employees for upcoming jobs, and provides graphical progress to each project. Going forward CanGo’s employees need to be involved in the decision-making of the projects or, at least, have the ability…

    • 294 Words
    • 2 Pages
    Decent Essays
  • Decent Essays

    promotion. Conjointly, the structure did not set procedure on how an engineer becomes a project manager. The process was purely out of director of engineering discretion. The structure also does not specify what employees will be doing. Therefore, an employee can be called out of the project even if it is not completed and assigned a new task.…

    • 315 Words
    • 2 Pages
    Decent Essays
  • Improved Essays

    This also ensures that necessary steps should be taken during creation of project requirements that involves consultation with the stakeholders as well as gathering external inputs and conducting marketing research. Missing this critical point is a contributing factor on why the project failed and unusable for the end-users. Roles and…

    • 834 Words
    • 4 Pages
    Improved Essays
  • Great Essays

    Introduction With over 60 different substance abuse treatment facilities in Wichita Kansas alone it is important that Center for Change stays ahead of the ever growing and changing modalities of treatment. While meeting the needs of the ever changing types of treatment, being able to find staff that can work together and provide excellent treatment to the many cultures, severity of substance abuse as well as to all the differing socioeconomic classes is vital. While working within the company, taking ideas from employees and listening to what they believe the strengths and weaknesses of the facility along with ways they feel that the clients can be better served I have created a plan to begin meeting these needs and implementing new programs…

    • 1742 Words
    • 7 Pages
    Great Essays
  • Improved Essays

    Therefore, tasks must be completed on time for the success of the project. McCullough and Sims (2012) stated that if a task or part of the project does not meet the set deadline then the entire project will be delayed. For example, if the Information Technology (IT) Department is swamped with more urgent work or they are having trouble developing the order set for the Amiodarone Protocol then the project will be delayed. The project plan, pathway/workflow redesign, screen design, order set, Amiodarone Protocol, and clinical decision support are all crucial activities that must follow an arrangement of tasks for the success of the project (see Appendix B). McCullough and Sims suggest that these arrangement of tasks follows a path that links critical tasks together and are crucial to the duration of the project.…

    • 631 Words
    • 3 Pages
    Improved Essays
  • Decent Essays

    What factors are likely to impact on your project scope? The factors are likely to impact on your project scope are time,tecnology and resoursis. 4) Develop a scope management plan To develop a scop management plan i need to collect the requirments,defining the scope then producing a WBS and verify and control the scope 5) What is project initiation d of my project against my planocumention?How can you use this within your project?…

    • 179 Words
    • 1 Pages
    Decent Essays
  • Superior Essays

    Project Strategy and Planning When planning for the Alliance Prototype Project, we took a very structured approach. Group members were assigned formal roles, which were then used to delegate portions of the planning document. Each section of the planning document was completed individually, but was revised at a follow up meeting where the group discussed their rationale behind each of their decisions. When formulating the scope statement, our Quality Manager focused on key deliverables and defined constraints, synthesizing the available information into one cohesive statement. Our Risk Manager brainstormed a list of all possible risks when executing the simulation, assigned probability and cost impacts to each, and then decided whether to accept…

    • 1288 Words
    • 5 Pages
    Superior Essays
  • Great Essays

    Within the project planning process, the project scope is created. The scope functions as the overall summary of the undertaking with details about all of the necessary requirements and specifications, including the project plans and documents (Vaidyanathan, 2013). Appendix E outlines the project scope statement for the AAE Project. The next document that has been generated is the requirement traceability matrix. The requirements traceability matrix is a framework to ensure that all requirements are tracked and managed throughout the project lifecycle (PMI, 2013).…

    • 1670 Words
    • 7 Pages
    Great Essays
  • Improved Essays

    A project must be considered by senior management in order to justify the setup of a proper organization unit for proper management and to make organization different from other normal structure. The business objectives for this project are development of project, management and increasing the capacity of project with right decision. This case study will identify different challenges and show its effects to this business and some solution to manage challenges. The solution will help in managing time, cost and risk of project. Finally summary of project will provide final decision of project.…

    • 1054 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    A work breakdown structure (WBS) is an important project provide able that categorizes the group's work into controllable segments. The project management body of Knowledge outlines the work breakdown structure as a bring-able concerned with graded disintegration of the work to be performed by the project group. The work breakdown structure of Primark graphically expresses the scope into wieldy amounts that a project team can comprehend as both equal of the work breakdown structure make available additional characterization and feature. In illustrates a section work breakdown structure with three stages…

    • 91 Words
    • 1 Pages
    Improved Essays
  • Improved Essays

    SCOTT SUTTERFIELD, DECEMBER 2006) of the DOD’s LAMP-H project. This inflation of requirements causes the needed resources to complete the project to grow, putting it at risk of termination, or failing in the event it’s completed. Improper Planning During the planning phase of a project, the project manager can make several mistakes that allow scope creep to become more likely to happen. If a project manager uses ambiguous or vague language in the projects statement of work describing the scope statement, scope, or change request management, outlined in the PMBOK (Project Management Institute Inc., 2000), it can lead to confusion between the project team and the stakeholders (Turk, 2010).…

    • 732 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    While conducting research of project management and one of the process groups – monitoring and controlling – there are 11 processes within that group that span all 12 knowledge areas (PMBOK, 2013). The PMBOK illustrates a great foundation for project managers to build a concrete framework for successful monitoring and controlling. That foundation includes inputs, tools and techniques, and outputs needed for success. A Project Manager may face challenges along the life cycle of a project but being able to effectively monitor and control activities with tools, mechanisms and knowledge can reduce those challenges and turn them into opportunities. This paper will outline the definition of monitoring and controlling, lessons learned and challenges a project manager may face with monitoring and controlling a project.…

    • 885 Words
    • 4 Pages
    Improved Essays
  • Superior Essays

    The most efficient plan for carrying out the activities is calculated and determines the timeline prior to starting work. Resources can be allocated accordingly so that each activity has proper assets when needed. Understanding of interdependent tasks can lead to possible reductions in project duration. Sub-critical tasks that are not on the longest timeline can be performed in parallel, also reducing the overall timeline of the project. Reducing Uncertainty All projects will encounter delays, unexpected issues, and surprises.…

    • 3964 Words
    • 16 Pages
    Superior Essays
  • Improved Essays

    Nayatel Case Study

    • 1443 Words
    • 6 Pages

    PMO DEPARTMENT IN NAYATEL COMPANY: After the analysis of PMO,the management has decided to establish the PMO department in Nayatel. The PMO plays a supportive role in the organization by providing training's to the project team members on various projects, tracking the progress of the project and communicating the success of the project to the board of directors and key stakeholder 1.ISSUES FACED BEFORE PMO: After the foundation of a Project Management Office, numerous issues and issues identified with projects have been resolve under the help of the PMO-Nayatel. The PMO has controlled the project consummation stages, making it a more light-footed, fruitful and viable process.…

    • 1443 Words
    • 6 Pages
    Improved Essays

Related Topics