Case Study Of The Alliance Prototype Project

Superior Essays
Project Strategy and Planning
When planning for the Alliance Prototype Project, we took a very structured approach. Group members were assigned formal roles, which were then used to delegate portions of the planning document. Each section of the planning document was completed individually, but was revised at a follow up meeting where the group discussed their rationale behind each of their decisions. When formulating the scope statement, our Quality Manager focused on key deliverables and defined constraints, synthesizing the available information into one cohesive statement. Our Risk Manager brainstormed a list of all possible risks when executing the simulation, assigned probability and cost impacts to each, and then decided whether to accept
…show more content…
If the scope of the project was too limited, the outcome may not meet customer and sponsor expectations. Specifically in the case of the Alliance Project, if our website prototype had more than 12 defects, the project would be considered a failure, as this was a critical success factor. The other two corners of the iron triangle would be affected, as this would force the project over time and over budget, since we would have to revise the product such that it met the customer 's acceptance criteria. Consequently, we identified scope to be the most important constraint. At the same time, we took into account time and budget, as the customer expected that the project would be completed within 11 weeks at a maximum cost of $50,000. Accounting for these constraints and assumptions was necessary so that when uncertain information arises throughout the project, we were able to return to our constraints and assumptions, which reminded us of what we were to achieve, how we were to achieve it, and how much achieving it is supposed to …show more content…
However, we were unable to complete the simulation within the given time frame of 11 weeks, and budget of $50 000. For the first ten weeks of the project, we were projected to finish at the 12 week mark. We made sure to appropriately allocate employees in order to complete the required tasks in a timely manner. We paid specific attention to the Gantt charts and network diagram in order to set the priorities of all staff members relative to the order that tasks needed to be completed in, thus minimizing the idle time of our resources. Quality and quality assurance training was provided to employees early on in the simulation in order to reduce the defect level of our product. This proved to be beneficial for our quality level, as our projected defect level following the training progressively dropped from 20, to our final quality level of 11

Related Documents

  • Improved Essays

    Healthcare Gov Essay

    • 618 Words
    • 3 Pages

    These challenges include, inappropriate design, inadequate resources and time, lack of clearly outlined goals and plans and inadequate cooperation among team members. Individuals tasked with handing the above-mentioned challenges did not communicate and cooperate with each other in an appropriate manner. The situation would have been different if the project had a strong and competent management team. For instance, lack of White House support made the situation worse as those in charge had no one to look up to for guidance. Therefore, the complexity of this project required commitment from both the Whitehouse and those mandated implementing it.…

    • 618 Words
    • 3 Pages
    Improved Essays
  • Great Essays

    American Shogun Case Study When a high-profile project is implemented, there needs to be a lot of planning, research, and flexibility. When a high-profile project also includes a very aggressive deadline, there is little room left for error.…

    • 1141 Words
    • 5 Pages
    Great Essays
  • Improved Essays

    Notice that the reason for including the cash flows in Exhibit 6 is explained in detail in the “The Super Project”. In particular, should General Foods include the following or not? Discuss briefly. a) Test market expenses; b) Charges for the use of Jell-O agglomerator capacity; c) Charges for erosion of Jell-O sales; d) Overhead expenses; Tip:…

    • 610 Words
    • 3 Pages
    Improved Essays
  • Great Essays

    Brightspace Case Study

    • 1667 Words
    • 7 Pages

    1. I believe we were asked to find the paper using the citation provided rather than having a copy of the paper posted on the D2L website in order to familiarize ourselves with how to interpret citations, since it is critical to understand what information (for example: title, author, publishing date) is provided within the citation, and also to get a sense of how the Ryerson online library site operates, along with the various resources offered on the library site. 2. The legal reason as to why the paper was not posted on Brightspace, but instead we were asked to go through the Ryerson library site in order to access the paper, may be due to the fact that the authors’ permission must be obtained prior to posting the scientific paper to Brightspace.…

    • 1667 Words
    • 7 Pages
    Great Essays
  • Great Essays

    Fusion Center Case Study

    • 1292 Words
    • 6 Pages

    Fusion Centers Due to the attacks of 9/11, law enforcement felt they needed to start an intelligence sharing place to help reduce attacks such as this one in the future. This idea also led to the creation of fusion centers, an area to exchange information and intelligence. The fusion center is also capable of analyzing information from a variety of sources and deciding how to proceed. These centers can be found in police stations to help ease the process of sharing information, but the idea is still new. Executives hope the use of fusion centers will continue to prove effective and influence more jurisdictions to participate.…

    • 1292 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    Janus Vs Project Femini

    • 607 Words
    • 3 Pages

    3. Project Janus and Project Gemini are both profitable projects to the organization but due to the financial constraint placed on budget, it is impossible for both projects to the funded at the same time. Nova Western should select Project Gemini because according to the first evaluation team which used the Scoring Model, the weighted score was favourable to the Project Gemini. Although, the NPV analysis used by the second evaluation team showed that Project Janus will bring a higher net present value for the initial investment made which will also take two years longer than Project Gemini. Most organizations like Nova Western will find it difficult to tie up their company’s money in a project that will take too long because the longer the time a project takes, the higher the budget.…

    • 607 Words
    • 3 Pages
    Improved Essays
  • Superior Essays

    Fusion Centers Case Study

    • 1683 Words
    • 7 Pages

    ways that enable multiple agencies to 'connect the dots ' and identify potential security threats (Monahan & Palmer, 2009). The role and contribution of fusion centers in counterterrorism and national security become even greater, given that they are central to developing effective information-driven relationships with private entities. The latter can provide useful information to help prevent possible attacks. Dozens of fusion centers currently operate in the U.S., with hundreds of thousands of people working in them. The federal government maintains the public belief in the information sharing effectiveness of such centers.…

    • 1683 Words
    • 7 Pages
    Superior Essays
  • Improved Essays

    m. . 7. Interchanges Plan All gatherings in reference to the development ought to have succinct gathering minutes that are taken utilizing an institutionalized configuration with appropriation rules. A complete correspondences arrangement would be actualized. 8.…

    • 754 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Currently the world witnesses a very dynamic, aircraft manufacturing industry, which invests billions and billions in its projects, due to tough market competitors. In order to achieve their goal and objectives, any project requires an efficient management. However, due to a diversity of issues, goals are not always achieved nor targets are met. During the 21st century, the aircraft manufacturing industry was leaded in the world by two major’s commercial jet manufacturers, namely Boeing and Airbus.…

    • 2435 Words
    • 10 Pages
    Improved Essays
  • Superior Essays

    The developed plans will help in time management, cost, quality, change and risk issues. The plan include the ability to manage staff and external supplies to ensure that the project meet the deadline and within the budget. A list of all items that need to be purchased to complete the project must be supplied this include labour, equipment, materials, administration and other costs. Identify all major risks that might occur when running the project and strategize on how you will prevent them from happening (Gray and Larson,…

    • 2384 Words
    • 10 Pages
    Superior Essays
  • Superior Essays

    The most efficient plan for carrying out the activities is calculated and determines the timeline prior to starting work. Resources can be allocated accordingly so that each activity has proper assets when needed. Understanding of interdependent tasks can lead to possible reductions in project duration. Sub-critical tasks that are not on the longest timeline can be performed in parallel, also reducing the overall timeline of the project. Reducing Uncertainty All projects will encounter delays, unexpected issues, and surprises.…

    • 3964 Words
    • 16 Pages
    Superior Essays
  • Improved Essays

    This process defines the framework of the project What is possible / realistic? Investigate potential solutions and the ramifications of choosing different routes to achieve the same or slightly modified outcomes. If outcomes differ from the original plan, is this a more effective solution to the change process. Stakeholders and opinion formers need to be kept informed of relevant details relating to the project. A communications plan with a schedule of events, meetings or newsletters.…

    • 737 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    SCOTT SUTTERFIELD, DECEMBER 2006) of the DOD’s LAMP-H project. This inflation of requirements causes the needed resources to complete the project to grow, putting it at risk of termination, or failing in the event it’s completed. Improper Planning During the planning phase of a project, the project manager can make several mistakes that allow scope creep to become more likely to happen. If a project manager uses ambiguous or vague language in the projects statement of work describing the scope statement, scope, or change request management, outlined in the PMBOK (Project Management Institute Inc., 2000), it can lead to confusion between the project team and the stakeholders (Turk, 2010).…

    • 732 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    2). In this case, A2Z Construction’s stakeholders consisting of organisation’s top management, employees, project team and leader, clients, suppliers need to commit to the project from the planning stage to the post-project monitoring stage. 2) The success principle The success principle entails understanding the project milestones and deliverables agreeing upon them before the project commences and activities designated (Wideman 2003, p. 2).…

    • 1014 Words
    • 5 Pages
    Improved Essays
  • Great Essays

    Early formal definition of a project scope is a very effective technique of ensuring that projects run…

    • 2444 Words
    • 10 Pages
    Great Essays

Related Topics