Critical Path method is...
|
A list of activities to be done in a sequential order
|
|
Planner:
|
uses methods, procedures, equipment, and labor to create production
|
|
What are the 3 types of schedules and what do they consist of:
|
Level 1:(Basic) goes to Executives
Level 2:(Office) goes to office hands Level 3: (Field) goes to workers Activities, Sequential Relationships, and Restraints |
|
What Itiems may a planner use:
|
Residence Diagram, Resource Loading, and Critical Path
|
|
What is Float?
|
?
|
|
Labor Productivity is..
|
Measure of output and labor
|
|
Negative Productive Impact would include?
|
Poor Weather, Material Concerns, Labor Overturn, Unsafe/ Accidents, Overtime, Congested work area
|
|
For Laborers what is the chain of command?
|
Foreman, Lead, Journey man, Apprentice, Helper
|
|
Labor Agreements
|
Agreement between union worker and contractor with..
-Wages -Working Conditions |
|
Shop Stewards is a..
|
Union Representative that makes sure..
-The Collective Bargaining Act are being monitored and enforced -Laws and Regs are being fallowed -Promote Union values and consciousness |
|
Chris From RTC?
|
Rtc in 94 did 4 mill annually
2001 he bought RTC for 5000 2008 did 20 mill in work Mostly Bid work Surity Bonding 2.5 mill credit line Union Contractor |
|
What is the Davis Bacon Act
|
Prevailing Wages when work is being done under certain contracts
|
|
Collective Bargaining Agreement is
|
A high level agreement between the Union and Contractor with
-Wages -Overtime -Shiftwork |
|
Safety EQUALS
|
Value
|
|
Lost time is
|
the time lost due to an unsafe act at the work place that ends up costing the contractor.
|
|
Who is charged for workman's comp.
|
Contractor pays for this, but the owner pays for it as it is based in the bid. Less workman's comp less cost to the owner. Based on EMR
|
|
PPE stands for and is..
|
Personal Protective Equipment: Examples would include eye protection, safety vest, hard hat, and if needed fall protection.
|
|
What are the 3 V's of Safety Management Plan?
|
Vocal, Visible, and Vigorous
|
|
Explain EMR, and what it pertains too?
|
Experience Modification Rating, the lower the better. This number bases the rate of a companies insurance, and it probability of having something go wrong.
|
|
What is MSDS and what consists of those pages?
|
Material Safety Data Sheets; These sheets give information on the product, Hazards, What to do if in contact, flash point, and who to contact
|
|
Safety Management Plan consists of..
|
-Commitment to execs (3 V's)
-Safety Analysis -Safety Procedure -Training |
|
What is OSHA?
|
Occupational Safety and Health Administration; is an agency of Federal Government that regulates job-site safety, they can inspect a job-site at anytime and fine for any unsafe acts of duty.
|
|
Name the ways OSHA will come out?
|
-Referrals
-Complaint -Death/Catastrophe -Program |
|
What does a meeting consist of with OSHA?
|
-Nature
-Purpose -Scope |
|
To issue fines or court dates OSHA must have what?
|
A Hazard
Show it is against standard The Employees are exposed The Company knows of issue and General Duty clause doesn't apply |
|
Delayed Claims have what effect on a Project?
|
They extend the time until the final date
|
|
Project Cost Management consists of..
|
Measurement of Work Quantities
Weekly Labor Cost Report Deviation Equipment Cost (W.R &I) |
|
Deviation is...
|
Is the lag time between present time and where the scheduled time should be
|
|
Learning Curve of a Job explain productivity.
|
Productivity is slow at the beginning, high mid way through and then slow again swards the end.
|