• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/138

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

138 Cards in this Set

  • Front
  • Back
The Cost Management Plan is created as part of the ________ ________ ________ _______ process in integration management.
Develop Project Management Plan
Estime Costs is done during ____ process group.
Planning
Determine budget is done during __________ process group.
Planning
Control Costs is done during _________ ___ _______ process group.
Monitoring and Controlling
The __________ __________ includes:

1. Specifications for how estimates should be stated (in what currency).

2. The level or accuracy needed for estimates.

3. Reporting formats to be used.

4. Rules for measuring cost performance.

5. Whether costs will include both direct and indirect costs

6. Control thresholds.
Cost Management
The creation of the Cost Management Plan requires thinking ahead about how costs will be ____________.
controlled
__________ __________ __________ is looking at the cost of the whole life of the product, not just the cost of the product.
Life Cycle Costing
__________ ___________ involves finding a less costly way to do the same work.
Value Analysis
Value analysis requires the sytematic use of tehniques to identify the required project functions, assign values to these functions, and provide functions a the lowest overall cost without __________ __ _________.
loss of performance.
The _______ _______ process is where the estimates for each activity are made.
Estimate Costs
Estimatinig should be based on a ______ to improve accuracy.
WBS
Estimating should be done by ___________________ whenever possible to improve accuracy.
the person doing the work
A ________ _______ should be kept and not changed except for approved project changes.
cost baseline
____________ ___________ from past projects is a key to improving estimates.
Historical information
The project ____ should be managed to the project cost baseline.
costs
Changes are approved in the _____ ____________ _____________process.
integrated change control
Estimates are more accurate if ____________ ________ work components are estimated.
smaller size
Changes should be requested when __________________.
when cost problems occur
Plans should be revised during completion of the work as necessary with _______ ______.
approved changes
_____________ must be reviewed when they are received to see if they are reasonable and to check for padding risks.
Estimates
Estimates must be kepp ________ through the life of the project by reestimating and reviewing them periodically.
realistic
Estimates can be decreased by reducing or eliminating ________.
risks
The _____ _____ has the professional responsibility to provide estimates that are accurate as feasible and to maintain the integrity of those estimates throughout the life of the project.
project manager
________ costs change with the amount of production or amount of work. Examples include the cost of material, supplies, and wages.
Variable
______ costs are overhead items or costs incurred for the benefit of more than one project. Examples include taxes, fringe benefits, and janitorial services.
Fixed
In order to estimate, you need to know the detail of what you are estimating, what is out of scope, and what constraints might have been placed on the project. These can be found by looking at at:
1. all the components of the scope baseline.

2. project scope statement

3. WBS

4. WBS Dictionary
You need a ____ before you can come up with a budget.
schedule
The timing of when you buy something affects it's _____.
cost.
You need to develope time-phased spending plan to control project ________ so that you know how much money will be spent for periodic periods of time.
expenditures
_________ systems can increase productivity and save money, but they are still a cost item to be estimated
Reward
The ____ _______ plan also lists resources (including the quantity and their skills) intended to be used for the project.
human resources
____ management will save time and money, but there are costs associated with the efforts to control ______.
- Risk
- risk.
Risks are more properly thought of as both an input to the Estimate Cost process and an _______.
output.
Planning is _____.
iterative.
_________ help make the work of creating templates, processes, procedures, and lessons learned for the project faster and easier.
Policies
In ____-_______ estimating; detailed estimating is done for each activity or work package, and the estimates are then rolled up into control accounts and finally into an overall project estimate. To do this well requires an accurate ______.
Bottom-Up
WBS
Advantages of Analogous Estimating are:
1. Quick

2. Activities need not be identified

3. Less costly to create

4. Gives the project mgr an idea of the level of management's expectations

5. Overall project costs will be capped
Disadvantages of Analogous Estimating include:
1. Less accurate

2. Estimates are prepared with a limited amount of detailed information and understanding of the project.

3. Requires considerable experiance to do well.

4. Infighting to gain the biggest piece of the budget without being able to justify the need

5. Extremely difficult for project with uncertainty

6. Does not take into account the differences between projects.
Advantages of Bottom-Up Estimating are:
1. More accurate

2. Gains buy-in from the team because the team creates estimates they can live with

3. Based on a detailed analysis of the project

4. Provides a basis for monitoring and controlling, performance measurement, and management.
Disadvantages of of Bottom-Up Estimating are:
1. Takes time and expense to do this form of estimating

2. Tendency for the team to pad estimates unless taught about reserves

3. Requires that the project be defined and well understood before work begins

4. Requires time to break the project down into smaller pieces
Detailed cost estimating requires the knowledge of the actual cost of _____.
labor
It is required project management to accomodate the xost and time risk in a project estimate through use of _____.
reserves
In _______ _______, you identify which activities on your project have significant risks and determine how much t ime and money to set aside to deal with the risks if they happen.
risk analysis
_______ ________ reserves are used for the specifically identified risks, and a lump sum management reserve is used to accomodate uniditified risks.
Ris contingency
_______ __ ____ estimate is usually made during the intitiating process.
Rough order of Magnitured (ROM)
A typical range for a ROM estimate is +/- ___% from actual.
50
The Budget Estimate is usually made during the _______ phase and is in the range of - __% to _ + 25 from actual.
planning
-10% to +25%
The _______ estimate will come later during the project and project managers typically use the range of +/- __% of +/- _%
10%

5%
The Estimate Cost process should result in _______ ______ estimates and the basis for those estimates.
activity cost
The Estimate Cost process may result in:
1. changes or updates to the risk register

2. updates to other parts of the project management plan and project documents in order to decrease project costs.
The ____ __ of the project needs to be calculated in order to determine the amount of funds the organization needs to set aside or have available for the project.
total cost
A project ______ can not be completed without risk management activities and the inclusion of reserves.
estimate
_______ reserves are to address the cost impacts of the risks remaining during risk response planning.
Contingency
_____ reserves are any extra funds to be set aside to cover unforseen risks or changes to the project.
Management
The _____ budget is the cost baseline plus the management reserves.
cost
To create a budget, activity costs are rolled up to ____ ____ costs.
work package
Work package costs are then rolled up to ___ _____ costs and final into project costs. This process is called _______ _____.
control account.
cost aggregation.
The cost-baseline, therefore, is time-phased and may be shown as a _ ________,
S curve
After the cost baseline and cost budget are completed, many estimators will compare these numbers to parametric estimates, expert judgement, or ________ __________ in order to do a sanity check.
historical relationships
An unrealistic budget is the _____ _______ fault.
project manager's
Without oversight and _______, neither the proejct nor you will be as successful.
Control
________ helps you see if there are any variances.
Measurement
The _______ ______ plan should include what you will measure, when, and what amount of variation between planned and actual will require action.
cost management
To get the ______ __ you complete activity estimates, work package estimates, control account estimates, project estimates, contingency reserves, cost base, management reserves.
cost budget
An activity is considered 50% complete when it ________ and gets credit for the last 50% when complete.
betgins as part of 50/50 rule
In the ________ rule an activity is considered 20% complete when it begins and gets credit for last 80% when it is complete.
20/80
_______ ______ will lead to budget forecasts, change requests, and other items wthat will need to be communicated.
Earned Value
A sign of a poor ______ _______ is ________ ___ who has to work overtime at the end of the project because he or she did not control the project along the way
project manager
project manager
Results from earned value analysis indicate potential ______ of the project from scope, schedule, and cost base line.
variation
___ value: as of today, what is the estimated value of the work planned to be done?
Planned
_____ value: As of today, what is the estimated value of the work actually accomplished?
Earned
______ ________; As of today, what is the actual cost ihncurred for the work accomplished?
Actual Cost
______ ___ _______; How much did we Budget for the Total project effort?
Budget at Completion
_________ ____ ________; What do we currently expect the Total project to cost (forecast)?
Estimate at Completion
_____ __ __________; From this point on, how much More do we expect it to cost to finish the project?
Estimate to Complete
________ ____ ______; As of today, how much over or under budget do we expect to be at the end of the project?
Variance at Completion
What is the formula for Cost Variance (CV)?
Earned Value - Actual Cost = Cost Variance

Neg is over budget
Pos is under budget
What is the formula for Schedule Variance?
Earned Value - Planned Value = Schedule Variance.

Neg is behind sched
Pos is ahead of sched
What is the formula for Cost Performance Index (CPI)?
Earned Value/Actual Cost = Cost Performance Index
What is the formula for Schedule Performance Index?
Earned Value/Planned Value = Schedule Performance Index.
_______ ______ Index tells us that we are only progress at ___% of ther rate originally planned.
Schedule Performance
What does Cost Performance Index tell us?
We are getting $____ worth of work out of every $1 spent. Funds are or are not being used efficiently.
________ _________ _____ tells us that as of now, how much do we expect the total project to cost $___.
Estimate at Completion
Actual Cost + Bottom-up estimate/Estimate to Complete is the formula to calulate what?
Actual plus a new estimate for the remining work. It is used when the original estimate was fundamentally flawed.
_________/Cumulative CPI formula is used if no variances from the BAC hace occured or you will continue at the same rate of spending.
Budget at Completion
What formula calculates actual to date plus remaining budget. It is used when current variances are thought to be atypical of the future.
Actual Cost +(Budget at Completion-Earned Value).
The formual for To Complete Performance Index (TCPI) is...
BAC-EV/BAC-AC
What does To Complete Performance Index (TCPI) tell us?
It answers the question of "In order to stay within budget, what rate must we meet for the remaining work?"
EAC-AC/Restimate is the formual for...
Estimate to Complete
ETC tells us...
How much more the project will cost - reestimate the remaining work from the bottom up.
The formula for Variance at Completion (VAC) is...
BAC-EAC
Variance at Completion tells us how much over or under __________ we will be at the end of the project.
budget
Any time _____ is used in a formula it comes first.
Earned Value
If the formula is a ________ it is EV minus something.
variance
If the answer is an ______, it is EV devided by something.
index
If the formula relates to Cost, us ___.
Actual Cost
If the formula relates to schedule, use ___.
Planned Value
For ___ interpretation, negative is bad and positive is good.
variances
For _______ interpretation, greater than one is good; less than one is bad.
indices
_______ ______ is an effective tool for measuring performance and determining the need to request changes.
Earned Value
One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and:
Divide by Cost Performance Index (CPI). The formual for EAC is BAC/CPI.
Estimate at completion (EAC) is a period of evaluation of:
The anticipated total cost at project completion.
If Earned Value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV)?
EV-AC = CV so the answer is -50
The customer responsible for overseeing your project asks you to provide a written cost estimate that is 30% higher than your estimate of the project's cost. He explains that the budgeting process requires managers to estimate pessimistically to ensure enough money is allocated for projects. What is the BEST way to handle this?
Ask for information on risks that would cause your estimate to be too low? Presenting anything besides yoru original estimate is inaccurate and calls into question your competence and integrity as a project manager. The customer should list potential changes and risks to your estimate. If the costs and risks are justified, you can increase the budget.
Analogous estimating:
Uses top-down estimating techniques - Analogous estimating is used most frequently during the planning process, not the executing process. You don't need historical costs.
All of the following are outputs of the Estimate Costs process EXCEPT:

A. An understanding of the cost risk in the work that has been estimated

B. The prevention of inappropriate changes from being included in the cst baseline.

C. An indication of the range of possible costs for the project.

D. Documentation of any assumptions made during the Estimate Cost process.
The prevention of inappropriate changes from being included in the cost baseline.
The main focus of life-cycle costing is to:
Consdier operations and maintenance costs in making project decisions.
Cost performance measurement is BEST done through...

A. Asking for a percent complete from each team member and reporting that in the monthly progress report.

B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance.

C. Using the 50/50 rule and making sure the life cycle cost is less than project cost.

D. Focusing on the amount of expended last month and what will be expended the following month.
Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance because this answer looks at the past and uses this information to estimate future costs.
A cost performance index (CPI) of 0.89 means:
The project is only getting 89cents out of every $1 for project work.
A schedule performance index of 0.76 means:
You are only progressing at 76% of the planned rate.
Which of the following is NOT needed in order to come up with a project estimate>

A. A WBS

B. A network diagram

C. Risks

D. A change control system
D. A change control system as it is not required to obtain estimates.
Which of the following is an example of parametric estimating?

A.Dollars per module

B. Learning bend

C. Bottom-up

D. CPMA
A. Dollars per module, parametric estimates use a mathematical model to predict project cost or time.
A rough order of magnitude estimate is made during which project management process group?
Initiating
A cost baseline is an output of which cost management process?
Determine budget process
During which project management process group are budget forecasts created?
Monitoring and Controlling as they are outputs of cost control.
Which type of cost is team training?

A. Direct

B. NPV

C. Indirect

D. Fixed
A. Direct because you are training the team on skills required for the project. The cost is directly related to the project.
Project setup costs are an example of:

A. variable costs

B. Fixed costs

C. Overhead costs

D. Opportunity costs
B. Fixed costs as set up costs do no change as production on the project changes.
Value analysis is performed to get.

A. More value from the cost analysis

B. Management to buy into the project.

C. The team to buy into the project.

D. A less costly way of doing the same work.
D. A less costly way of doing the work.
Who has the cost risk in fixed price contract?

A. the team

B. the buyer

C. the seller

D. Management
The seller
Which of the following represents the estimated value ofthe work actually accomplished:

A. Earned Value (EV)

B. Planned Value (PV)

C. Actual Cost (AC)

D. Cost Variance (CV)
A. Earned Value (EV) as this is the definition of EV.
Which of the following are ALL items inlcudded in the cost management plan?

A. The level of accuracy needed for estimates, rules for measuring cost performance, specifications for how duration estimates should be stated.

B. Specifications for how estiamtes should be stated, rule for measuring cost performance, the level of accuracy needed for estimates.

C. Rules for measuring team performance, the level of accuracy needed for estimates, specifications for how estimates should be stated.

D. Specifications for how estimates should be stated, the lovel of risk needed for estimates, rules for measuring cost performance.
B. Specifications for how estiamtes should be stated, rule for measuring cost performance, the level of accuracy needed for estimates.
Your project has a medium amount of risk and is not very well defined. The sponsor hands you a project charter and asks you to confirm that the project can be completed within the project cost budget. What isthe BEST method to handle this?
Build the estimate in the form of a range of possible results.
The cost contingency reserves should be:

A. Hidden to prevent management from disallowoing the reserve.

B. Added to each activity to provide the customer with a shorter critical path.

C. Maintained by management to cover cost overruns.

D. Added to the base costs of the project to account for risks.
D. Added to the base costs of the project to account for risks
The seller tells you that your activities have resulted in an increase in their costs. You should:

A. Recommend a change to the project charter

B. Have a meeting with management to find out what to do.

C. Ask the seller for supporting information.

D. Deny any wrong doing.
C. Ask the seller for supporting information.
This is a social and professional responsibility question. This question involves a claim.
Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?

A. Eliminate risks in estimates and reestimates

B. Meet with the sponsor to find out what work can be done sooner.

C. Cut quality

D. Decrease scope
A. Eliminate risks in estimates and reestimates - it is the answer with the least negative response
A new store development project requires the purchase of various equipment, machinery, and furniture. The department responsible for the development recently centralized its external purchasing process and standardized its new order systems. In which document can these new procedures be found.

A. Project Scope Statement

B. WBS

C. Staffing and Management Plan

D. Organizational Policies
D. Organizational Policies - Procedures for the rental and purchase of supplies and equipment are found in the organizational policies part of organizational process assets.
Early in the life cycle of your project, you are having a discussion with the sponsor about what estimating techniques should be used. you want a form of expert judgement, but the sponsor argues for analogous estimating. It would be BEST to:

A. Agree to analogous estimating, as it is a form of expert judgement

B. Suggest life cycle costing as a compromise

C. Determine why the sponsor wants such an accurate estimate.

D. Try to convince the sponsor to allow expert judgement because it is typically more accurate.
A. Agree to analogous estimating, as it is a form of expert judgement
You have just completed the initiating process of a small project and are moving into planning processes when a project stakeholder asks you for the project's budget and cost baseline. What should you tell her?
The project budget and baseline will not be finalized and accepted until the planning processes are completed.
The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this.

A. Cost Mgt

B. Estimate Costs

C. Determine Budget

D. Contorl Costs
C. Determine Budget
Monitoring costs expended to date in order to detect variances from the plan occurs during:

A. The creation of the cost change management plan

B. Recommending corrective actions

C. Updating the cost baseline

D. Product performance reviews.
D. Product performance reviews.
A manufacturing project has a schedule performance index of 0.89 and a cost performance inex of 0.9. Generally what is the BEST explanation for why this occured:

A. The scope was changed

B. A supplier went out of business and a new one needed to be found.

C. Additional equipment needed to be purchased.

D. A critical path activity took longer and needed more laborr hours to complete.
D. A critical path activity took longer and needed more laborr hours to complete. It took longer and increased cost with less spent per $.
Although the stakeholders thought there was enough money in the budget, halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project cost budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was completed. Which of the following describes what was missing?

A. Estimated costs should be used to measure CPI.

B. SPI should be used, not CPI

C. Bottom-up estimating should have been used.

D. Past history was not taken into account.
C. Bottom-up estimating should have been used.
Earned value analysis is an example of:

A. Performance Reporting

B. Planning Control

C. Ishikawa diagrams

D. Integrating the project component into a whole.
A. Performance Reporting
You are about to take over a project from another project manager and find out the following information about the project. Activity Z has an early start date of 15 and a late start date of 20. Activity Z is a difficult activity. The cost performance index (CPI) is 1.1. The schedule performance index is (SPI) is 0.8. There are 11 stakeholders on the project. Based on this information, which of the following wold you be the MOST concerned about?

A. Schedule

B. Float

C. Cost

D. The number of available resources.
A. Schedule because SPI is less than 1
The difference between the cost baseline and the cost budget can be BEST described as:

A. The management reserve

B. The contingency reserve

C. The project cost estimate

D. The cost amount
A. The management reserve
You provide a project cost estimate for the project to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15% off the project estimate. What should you do?
Inform the sponsor of activities to be cut to meet the difference.
Cost risk means:
There is a risk that project costs could go higher than planned.
A project manager needs to analyze the proejct costs to find ways to decrease costs. It would be BEST if the project manager looks at...
Direct costs and variable costs as theses costs are directly contributed to the project or vary with the amount of work accomplished.