Project |
a set of related and interdependent activities directed towards creating a product or service |
|
Project Management |
planning, scheduling, and monitoring of tasks to meet project goals within the stipulated time frame and allocated resources |
|
Work Breakdown Schedule (WBS) |
breakdown of a project into smaller, more detailed activities and tasks |
|
PERT & CPM |
techniques used to identify the critical activities and start/finish dates of each activity in a project |
|
Optimistic Time |
(OT) the shortest time estimated, if everything goes right, to complete the project
|
|
Most Likely Time |
(MT) the most likely time the project will be completed |
|
Pessimistic Time |
(PT) the longest time it will take to complete a project, if everything goes wrong |
|
Expected Completion Time (equation) |
(ECT) (4 * MT) + OT + PT 6 |
|
Variance (equation) |
PT - OT ^2 6 |
|
the critical path |
the path that takes the most time to complete (highest ECT) |
|
Probability of completing a project in a certain amount of time (equation) |
z = T - Tcp sq.root of variance z= standard deviation T= target completion date Tcp= ECT of critical path variance= ((PT - OT) / 6)^2 |