Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
122 Cards in this Set
- Front
- Back
As the construction administrator, what are the responsibilities of the Landscape Architect?
|
-check the quality of work and make sure it meets code and the specifications of the contract. -resolving any problems that arise in as quickly a manner as possible |
|
components of contract supervision include
|
selection of contractors
award of contract acceptance of work completed |
|
components of design development include:
|
schematic designs
feasibility studies preliminary estimates |
|
components of design implementation include:
|
|
|
components of programming and analysis include:
|
site selectionsite inventory and analysis
|
|
Does CLARB work with A.S.L.A. in developing the L.A.R.E?
|
No
|
|
if a contractor provides unsatisfactory work, how long may the owner withhold payments?
|
until the situation is rectified
|
|
if contacting the employer about unsafe working conditions fails, who should be notified?
|
O.S.H.A. who will then bring in an inspector to assess the situation
|
|
List the reasons a contract may be terminated
|
|
|
over the course of a project's design and installation, a landscape architect is responsible for:
|
-keeping a record of the designs
-analyze environmental conditions -plan the design -observe construction progress |
|
over the course of a project's design and installation, the contractor is responsible for:
|
obtaining all permits and installing the desing
|
|
over the course of a project's design and installation, the owner is responsible for:
|
-setting the budget
-providing goals and objectives |
|
public bids usually have what type of requirements?
|
-complete and thorough bids
-specific types of advertising -specific bid due dates -times and a requirement to select the lower bidder |
|
Reasons a landscape architect can lose their license include:
|
|
|
reasons for keeping a retainer
|
-unsatisfactory work
-failure of the contractor to do the work -damaged property -compliance with the mechanic's lien |
|
same as time and materials agreement except that there is a maximum limit on the amount of money that the design firm can get paid for its services
|
time and materials with a maximum not to exceed payment agreement.
|
|
the pay rate for the labor is negotiated beforehand when the payment method is time and materials.
|
true
|
|
There is a limit to the amount of time that can be spent on a project when the payment method is time and materials
|
false
|
|
time and materials with maximum not to exceed payment agreement encourages the design team to be efficient.
|
true
|
|
time and materials with maximum not to exceed payment agreement helps keep the costs down for the client
|
true
|
|
What are some of the benefits of a Joint Venture?
|
It allows two companies to share resources, combine expertise and capital
|
|
what are the benefits of a corporation
|
it provides security of one's personal assets in the event of a lawsuit against the firm and will still exist in the event of one of the partners leaving the company
|
|
What are the components to a bid?
|
-the invitation to bid-the instructions to bid
-a detailed bid form-assorted bonds |
|
what are the responsibilities of the landscape architect operating in the capacity of a construction administrator?
|
-observe work being completed on site
-recommending whether to accept or reject the work being done. |
|
What does the Certificate of Occupancy state?
|
That the building complies with all local codes and is in condition to be occupied.
|
|
What doesn't CLARB do?
|
Set the minimum requirement that each state must require in order to become licensed
|
|
What is a graphical representation of the project at hand that details the proposed construction?
|
the shop drawings
|
|
What is CLARB's role?
|
Assist state registration boards
Compile Professional records Develop the L.A.R.E Provides services, which tests the examinees and provides the results to each individual state boards |
|
what is discussed at a pre-construction meeting?
|
-permits
-material testing -duties of those involved -due dates |
|
what is included in a closeout package?
|
-guarantees
-inspection certificates -as-built drawings -maintenance agreements |
|
what is included in the base bid?
|
-overhead
-labor -equipment -site preparation -materials |
|
What is included in the instructions to bidders?
|
-the start date of the project-the time and place to submit bids and any product substitution information
|
|
What is needed in order to begin using a building after all the work has been completed?
|
A Certificate of Occupancy
|
|
what is the minimum amount that contractors are required to pay their employees on a federally funded project?
|
The prevailing wage, which includes salary and benefits in the price.
|
|
when does a pre-construction meeting take place?
|
after a bid package has been sent out and a contract has been signed
|
|
When is a writ of execution granted?
|
When the defendant refuses to pay the judgement and may result in a levy against the defendant's property.
|
|
when should Record Drawings be done?
|
also called as-built drawings, should be recorded contemporaneously with the execution of work being done on a job site.
|
|
Which takes precedent, written contracts or verbal contracts?
|
written contracts
|
|
who is responsible for hiring subcontractors?
|
The contractor
|
|
who is responsible for safety on the construction site?
|
the contractor
|
|
Who issues A Certificate of Occupancy?
|
The local building department
|
|
who provides shop drawings?
|
the contractor or manufacturer that provided the details of an item to be installed
|
|
who should be contacted first if working conditions are hazardous, and is responsible for providing a safe working environment?
|
the employer
|
|
who's responsibility is it to make the final decision on whether the work is acceptable or not, when the L.A. is construction administrator, L.A. or owner?
|
the owner
|
|
when a cost plus contract is approppriate
|
- used when the actual costs of a project are difficult to estimate with accuracy
- plans may not be complete - project cannot be accurately portrayed - project could be needed to be complete within a fairly short time period and the plans and specs cannot be completed before construction starts - almost exclusively in the private sector |
|
When to use separate contract method
|
- availability of competent construction mgr
- where required specialty work is restricted to a few types of construction - not widely used |
|
When unit price contracts are appropriate
|
- when project is fairly well definedbut actual quantities may be difficult or impossible to estimate with accuracy after construction has started
|
|
This governs in the case of a conflict between plans and specs
|
specs
|
|
three types of hold harmless agreements
|
1 - limited form indemnification
2 - intermediate form indemnification 3 - broad form indemnification |
|
tract of land, usually consisting of a series of connected parcels of property, that is used for the operation of a highway or public utility
|
right of way
|
|
typical instructions relative to the writing of bid(8)
|
- bids must be submitted on forms provided
- erasures must be initialed by the signer - all items in the bid schedule must be priced - alternatives are not considered unless called for - discrepancies between the unit price and the extended amount are discussed - can the bid be mailed? - can bid modifications be made? - submission policy must be followed |
|
typical project completion phase(9)
|
1 - major construction work items are completed
2 - punch list prepared 3 - substantial completion- owner may occupy- warranty for project begins- time of completion marked- time is marked for filing liens- last periodic payment is requested 4 - punch list items addressed 5 - final inspection conducted 6 - final completion defined 7 - project accepted 8 - release of retainage requested9 - final payment |
|
typical subcontractor agreement provisions (3)
|
- subcontractors will be paid:
1 - after completion of the work 2 - after acceptance by architect/engineer 3 - after full payment of the work by the owner |
|
Risks of professional construction management contract
|
- CM is responsible to the owner to complete project on time and budget
- similar to GC method - firm enters contract prior to design completion |
|
Self-performance method
|
- force account work
- owner self-perform construction work/do work in house - no written contract - just the owner and workers - owner as manager - appropriate for projects small in scope, simple, ongoing and maintenance projects - criticized when public owners decide to do projects by self-performance |
|
Separate contract method
|
- multiple prime contracts method
- owner contracts directly to specialty contractors for various jobs - appropriate if owner has in house capabilities to manage construction project - owner keeps profit that would have gone to general contractor |
|
signatures on change orders
|
- owner
- architect - contractor |
|
Specifications in the broader term of the contract....10
|
1 - invitation to bid
2 - instruction to bidders 3 - general conditions 4 - supplementary conditions 5 - bid proposal form 6 - bid bond form 7 - contract bond form 8 - list of prevailing wages 9 - noncollusion affidavit 10 - technical specifications |
|
private sector advertisements for bids
|
- owner can choose a contractor by any means
- public advertising is frequently used to obtain the advantages of open and free competition - owner can elect to negotiate with a particular contractor - owner can create a select bidders list who are then asked to bid on the project |
|
process of change order
|
- Owner issues modification
- GC reviews proposed change - GC finalizes estimate for changes - Owner evaluates price proposed - owner issue form change order to the GC agreed price/cost -plus basis OR owner decides not to issue change order |
|
professional construction management
|
- owner hires firm with construction expertise
- on large complex projects - permits flexibility for changing |
|
Project Manual consists of... (4)
|
1 - bidding documents
2 - general conditions 3 - supplementary conditions 4 -technical specifications |
|
positives of cost plus contract
|
contractor almost always assured of not losing money
|
|
payment in lump sum
|
contractor asked to break down the project into a variety of work items and to allocate the appropriate payment to be made for each item
|
|
payment in unit price contract
|
- usually contractor will request payments on the basis of measurements of in-place quantities
|
|
On private works projects the design ownership is assigned to either the owner or designer in the....
|
contract you idiot
|
|
On public works projects the design ownership is assigned to the,...
|
owner
|
|
only time a contractor can terminate a contract due to delays
|
- when the owner delays in issuing a certificate or a delay in making payments
|
|
notice to contractor may be called either
|
notice of award
- start date is usually specified here notice to proceed |
|
lump sum projects are particularly vulnerable for the following reasons...
|
- prices can increase
- labor difficulties can arise - subsurface conditions may be different than expected - government policy may change, affecting the ability to borrow |
|
lien discharged in two ways
|
foreclosure or elimination
|
|
it is common for changes clauses to include the following items....(4)
|
- owner has the right to make changes within the general scope of the contract
- contractor is obligated to perform the work necessitated by the change - the change must be in written form and must be signed - an adjustment to the contract price and/or contract duration will be assessed by some means, or can be predetermined |
|
in the case of a conflict between the plans and specs the conflict will be resolved by the....
|
architect
|
|
General Conditions do the following...
|
establish the rights, authority and obligations of the contracting parties: the owner, the owner's representative, and the contractor
|
|
General contract method
|
- between owner and general contractor
- owner represented by firm (contract documents) |
|
how to avoid liens
|
- owners can post a notice of nonresponsiblity
- no lien contract - owner can require the contractor to furnish an affidavit that all the bills related to a project have been paid - owner can demand to see receipts - owner can require GC to pay the subs before he gets paid - owner can keep retainage |
|
disadvantages of bid process
|
- accurate costs cannot be known until the design is completed
- bids that exceed owners budget cannot be readily accomodated - various parties tend to be adversarial under this process - errors or ommisions in the design may lead to costly change orders |
|
disadvantages of cost plus contracts
|
- owner has little idea of what actual cost of project will be
- owner must maintain additional staff to monitor the progress of contractor |
|
Disadvantages of General Contract
|
- often extends project duration
- leads to tight bid and small profit margins - incentive for general contractors to cut corners on performance - inflexibility - high probability of claims for owner |
|
disadvantages of lump sum
|
- construction of project is delayed while plans are completed
- errors in plans will be costly because they result in extras |
|
disadvantages of unit price
|
- owner is not certain of the actual cost of the project until the project is completed
- plans must be reasonably complete in order for the bidders to develop unit prices for all the bid items |
|
Describes the preparation, workmanship, installation, erection, and application procedures to be employed along with quality requirements and performance criteria that must be satisfied
|
Execution Specs
|
|
describes the product or products and the development and manufacturing process to be used in producing them
|
Product Specs
|
|
criticism of liens
|
- they are complex and take a long time to process
- inconsistent between states - no guarantee of payment and are often useless- severe means of collection if the debt is small |
|
construction contract documents include....(6)
|
1. construction agreement
2. drawings 3. general conditions 4. supplementary conditions 5. technical spec's 6. addenda |
|
conditions must be met for a tort to occur
|
- one party owes a duty to another party
- the party does not conform to the standard (breach in performance of the duty) - the second party is harmed by the act or failure to act - there is a clear casual relationship between the act and the harm that results |
|
Can be authorized by personnel in the field without direct owner approval
|
field change
|
|
arrangment of the three parties in a surety bond
|
surety
- the bond company obligated to perform or pay when principle doesn't performprinciple - general contractor whose performance is promised or guaranteedobligee - owner who is promised the performance |
|
Another names for Design specifications
|
method and materials specs
prescriptive specs material and workshop specifications |
|
Agent is appointed to act for the principle and is authorized to...
|
do only what the principle wants
|
|
agent is responsible for actions if
|
they are not authorized by the principle
|
|
additional work must be from a change that...(3)
|
- should not have been anticipated
- was not open to observation - could not readily be discovered until work under the contract was undertaken |
|
advantages of bid process
|
- owner benefits from competitive market place
- owner has appearance of being impartial - process full embraces the fundamentals of free market - may be only viable method for some government agencies |
|
Advantages of design-build
|
- owners keep savings in public sector and share savings in private sector
- eliminate potential for being embroiled in disputes between design and construction firm |
|
Advantages of General Contract
|
- reduce cost for owner when contractor has unique skill set
- only method that gives owner a firm idea of final cost prior to construction phase- clearly defined roles for each party - owner minimizes contractual liability for cost overruns and late project delivery |
|
advantages of joint ventures
|
- increase bond capacity
- gain familiarity with the local labor market be enlisting the services of a local firm - increase capabilities - pool equipment resources - increase available capital |
|
advantages of lump sum
|
- plans are completed
- price is what it will be - good for limited budgets |
|
agency agreements consist of
|
1. agent
2. principle |
|
Agency agreements vs contracts
|
similar in that they contain the same basic elements
|
|
Acts agents cannot perform
|
- anything personal in nature
- anything illegal - immoral acts - acts opposed to public policy |
|
10 common things on a bid form
|
- price (lump or unit)- time of completion
- bid surety - agreement to provide contract surety - acknowledgement of having reviewed addenda - list of subcontractors - experience record - declaration regarding fraud and collusion - statement regarding site examination - signature |
|
12 rules to bidding
|
1 - follow instructions as in last card
2 - contractor MAY be required to submit an experience record 3 - instructions clearly list all documents part of the bid document 4 - construction time period spelled out 5 - instruction indicate who is responsible for geotech 6 - requirements of bid guarantee outlined 7 - insurance to be provided by contractor is stipulated 8 - bonding requirements given 9 - conditions for handling bid irregularites are stated 10 - where and when to deliver bids 11 - closed or public opening of the bids indicated 12 - a prebid conference MAY be described |
|
12 things typically in notice to bidders
|
- nature or type of project
- location of project - type of contract for construction- bonding requirements - dates in which to perform work- terms of payment - estimated construction costs - time, manner, and place to submit bids - location to obtain bid documents - deposit required on bid documents - owners right to reject any and all bids - requirements regarding wage rates |
|
3 types of construction CONTRACTS
|
1 - unit price
2 - cost plus 3 - lump sum |
|
3 types of delay categories
|
- delays caused by the contractor or contractor's agents
- delays caused by the owner or the owner's agents - delays caused by the force majeure or acts of god |
|
4 construction categories
|
1 - housing (private)
2 - building (non-residential, public and private) 3 - Engineering (civil works projects, public) 4 - industrial (private) |
|
5 types of contracting procedures
|
1 - General Contract Method
2 - Separate Contracts Method 3 - Self-performance Method 4 - Design-build method 5 - Professional construction management |
|
6 examples of torts
|
failure to exercise care in the exercise of one's duty to another |
|
9 ways an agency is terminated
|
|
|
What are the six requirements for a contract to be valid?
|
Some contracts must be in proper form or must be in writing though courts will support an oral contract |
|
Who is responsible for the accreditation of landscape architecture programs?
|
ASLA
|
|
Construction Manager at Risk
|
|
|
Construction Manager-Agent
|
|
|
contractor + designer agree to provide a finished building at a given time all the owner has to do is _______________ many HUD projects are this
|
TURNKEY CONTRACT
|
|
If a landscape architect approves a request for payment that includes services that have not been performed yet...
|
they are covered by errors and omissions insurance and therefore is held responsible
|
|
Who writes a "letter agreement contract?"
|
The consultant
|
|
Specs vs Drawings
|
In the event of conflicting information, specs prevail because they contain more detail and specificity.
|
|
What are the basic servies of a scope of work?
|
Project programming, schematic through final design, construction documents, and construction administration
|
|
What are some additional services in a scope of work?
|
post-construction evaluation, display model building, marketing material design, landscape maintenance programming
|
|
What is another name for a Mechanics Lien?
|
Labor and Materials Lien
|
|
INDEPENDENT BOARD VS JOINT BOARD
|
licensure board can be controlled by solely landscape architects vs other licensed professionals (arch, engineer, etc)
|
|
A document issued by the LA directing the contractor to erect some portion of the building in a manner different than described in the original plans + specs is this_____ if it does not have an effect on price and/or time, it is a _________
|
CHANGE ORDER
FIELD ORDER |