• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/28

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

28 Cards in this Set

  • Front
  • Back
What are the Project Time Management Processes (6 of them, 4 A's and 2 S's)
Activity definition: Identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.
Activity sequencing: Identifying and documenting the relationships between project activities.
Activity resource estimating: Estimating how many resources a project team should use to perform project activities.
Activity duration estimating: Estimating the number of work periods that are needed to complete individual activities.
Schedule development: Analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule.
Schedule control: Controlling and managing changes to the project schedule.
What is an activity or task
An activity or task is an element of work normally found on the WBS that has an expected duration, a cost, and resource requirements.
What are 3 things you need to know about activity sequencing
Involves reviewing activities and determining dependencies.
A dependency or relationship relates to the sequencing of project activities or tasks.
You must determine dependencies in order to use critical path analysis.
What are the Three Types of Dependencies
Remember MDE

Mandatory dependencies: Inherent in the nature of the work being performed on a project; sometimes referred to as hard logic.
Discretionary dependencies: Defined by the project team; sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.
External dependencies: Involve relationships between project and non-project activities.
What are the 2 main formats for network diagrams
Two main formats are the arrow and precedence diagramming methods.
What kind network diagram is this
Activity-on-Arrow (AOA)
What is a network diagram
A network diagram is a schematic display of the logical relationships among, or sequencing of, project activities.
What are 4 things you need to know about Precedence Diagramming Method (PDM)
Activities are represented by boxes.
Arrows show relationships between activities.
More popular than ADM method and used by project management software.
Better at showing different types of dependencies.
What is Critical Chaining
a method of planning and managing projects that puts the main emphasis on the resources required to execute project tasks
What does PERT do?
PERT is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.
What does PERT use?
PERT uses probabilistic time estimates:
Duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations, or a three-point estimate.
What is the weighted average for PERT weighted average
PERT weighted average =

(optimistic time + 4X most likely time + pessimistic time) / 6
What will a critical chain tend to do
A Critical Chain project network will tend to keep the resources levelly loaded, but will require them to be flexible in their start times and to quickly switch between tasks and task chains to keep the whole project on schedule.
What is Critical Chaining scheduling
a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.
What does the Theory of Constraints seek to do?
The TOC process seeks to identify the constraint and restructure the rest of the organization around it
What does Critical chain scheduling use?
It Uses the Theory of Constraints (TOC), a management philosophy developed by Eliyahu M. Goldratt and introduced in his book The Goal.
What is a buffer
A buffer is additional time to complete a task.
What is Murphy’s Law
Murphy’s Law states that if something can go wrong, it will.
What is Parkinson’s Law
Parkinson’s Law states that work expands to fill the time allowed.
What is fast tracking
Fast tracking activities by doing them in parallel or overlapping them.

Used to Shorten a Project Schedule
What is Free slack or free float
Free slack or free float is the amount of time an activity can be delayed without delaying the early start of any immediately following activities.
Formula: FF = ES(2) - EF(1)
What is Total slack or total float
Total slack or total float is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
Formula: TF = LS - ES
What does a forward pass through the network diagram determine
A forward pass through the network diagram determines the early start and finish dates.
What does a A backward pass determine
A backward pass determines the late start and finish dates.
What does crashing do?
Crashing activities by obtaining the greatest amount of schedule compression for the least incremental cost.

Used to Shorten a Project Schedule
What do Gantt Chart do
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.
What does Phil not charge for?
Awesomeness

There is no charge for Awesomeness
What are the symbols included in Gantt charts?
Black diamonds: Milestones
Thick black bars: Summary tasks
Lighter horizontal bars: Durations of tasks
Arrows: Dependencies between tasks