19 Cards in this Set

  • Front
  • Back

No. of Communication Channels

N=n(n-1)/2
SPI (Schedule Performance Index)
SPI=EV/PV
CPI (Cost Perormance Index)
CPI=EV/AC
SV (Schedule Variance)
SV=EV-PV
CV (Cost Variance)
CV=EV-AC

EAC (Estimate At Completion) 1



(when original estimate if flawed)

EAC=AC+ETC

EAC (Estimate At Completion) 2



(same variance expected)

EAC=BAC/CPI
EAC (Estimate At Completion) 3

EAC=AC+[(BAC-EV)/(CPI*SPI)]

EAC (Estimate At Completion) 4



(Atypical Variance)

EAC=AC+BAC-EV
TCPI (To Completion Performance Index)
TCPI=(BAC-EV)(BAC-AC) i.e.(Remaining Work/Remaining Funds)
ETC (Estimate To Completion)
ETC=EAC-AC
VAC (Variance At Completion)
VAC=BAC-EAC
PERT Estimation
(O+4M+P)/6
Triangular Estimation
(O+M+P)/3
Activity Standard Deviation
(P-O)/6
Activity Variance
[(P-O)/6]^2
PV (Present Value)

PV=FV/(1+R)^n

EMV (Expected Monetary Value)

P x I


(P - Probability, I - Impact)

ETC (Estimate To Completion)



(Typical Variance)

(BAC-EV)/CPI