No. of Communication Channels |
N=n(n-1)/2
|
|
SPI (Schedule Performance Index)
|
SPI=EV/PV
|
|
CPI (Cost Perormance Index)
|
CPI=EV/AC
|
|
SV (Schedule Variance)
|
SV=EV-PV
|
|
CV (Cost Variance)
|
CV=EV-AC
|
|
EAC (Estimate At Completion) 1
(when original estimate if flawed) |
EAC=AC+ETC
|
|
EAC (Estimate At Completion) 2
(same variance expected) |
EAC=BAC/CPI
|
|
EAC (Estimate At Completion) 3
|
EAC=AC+[(BAC-EV)/(CPI*SPI)] |
|
EAC (Estimate At Completion) 4
(Atypical Variance) |
EAC=AC+BAC-EV
|
|
TCPI (To Completion Performance Index)
|
TCPI=(BAC-EV)(BAC-AC) i.e.(Remaining Work/Remaining Funds)
|
|
ETC (Estimate To Completion)
|
ETC=EAC-AC
|
|
VAC (Variance At Completion)
|
VAC=BAC-EAC
|
|
PERT Estimation
|
(O+4M+P)/6
|
|
Triangular Estimation
|
(O+M+P)/3
|
|
Activity Standard Deviation
|
(P-O)/6
|
|
Activity Variance
|
[(P-O)/6]^2
|
|
PV (Present Value)
|
PV=FV/(1+R)^n |
|
EMV (Expected Monetary Value) |
P x I (P - Probability, I - Impact) |
|
ETC (Estimate To Completion)
(Typical Variance) |
(BAC-EV)/CPI |