Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
37 Cards in this Set
- Front
- Back
projects can be defined as...
|
a series of related tasks directed toward a major output.
|
|
The management of projects involves three phases:
|
1 planning 2 scheduling 3 controlling
|
|
planning
|
this phase includes goal setting, defining the project, and team organization
|
|
scheduling
|
this phase relates people, money, and supplies to specific activites and relates activites to each other
|
|
controlling
|
here the firm monitors resources, costs, quality, and budgets. It also revises or changes plans and shifts resources to meet time and cost demands.
|
|
project organization
|
an organization formed to ensure that programs (projects) receive the proper management and attention
|
|
work breakdown structure (WBS)
|
defines a project by dividing it into more and more detailed componenents
|
|
gantt charts
|
planning charts used to schedule resources and allocate time.
|
|
Project scheduling serves several purposes:
|
1 it shows the relationship of each activity to others and to the whole project 2 it identifies the precendence relationships among activities 3 it encourages the setting of realistic time and cost estimates for each activity 4 it helps make better use of people, money, and material resources by identifying critical bottlenecks in the project
|
|
computerized programs produce a broad variety of PERT/CPM reports, including...
|
1 detailed cost breakdowns for each task 2 total program labor curves 3 cost distribution tables 4 functional cost and hour summaries 5 raw material and expenditure forecasts 6 variance reports 7 time analysis reports 8 work status reports
|
|
program evaluation and review technique (PERT)
|
a project management technique that employs three time estimates for each activity
|
|
Critical path method (CPM)
|
a project management technique that uses only one estimate per activity
|
|
PERT & CPM both follow six basic steps.
|
The activities on the critical path will delay the entire project if they are not completed on time.
|
|
Activity-on-node (AON)
|
a network diagram in which nodes designate activities
|
|
Activity-on-arrow (AOA)
|
a network diagram in which arrows designate activities
|
|
In an AOa network, the nodes represent...
|
the starting and finishing times of an activity and are also called events
|
|
Dummy activity
|
An activity having no time that is inserted into a network to maintain the logic of the network. Can be added to the end of an AON diagram for a project that has multiple ending activities
|
|
Critical path analysis
|
A process that helps determine a project schedule
|
|
To find the critical path, we calculate two distinct starting and ending times for each activity:
|
earliest time (ES), earliest finish (EF), latest start (LS), and latest finish (LF)
|
|
Earliest start
|
is the earliest time at which an activity can start, assuming that all predecessors have been completed
|
|
earliest finish (EF)
|
is the earliest time at which an activity can be finished
|
|
latest start (LS)
|
is the latest time at which an activity can start, without delaying the completion time of the entire project
|
|
latest finish (LF)
|
latest time by which an activity has to finish so as to not delay the completion time of the entire project
|
|
forward pass
|
a process that identifies all the early start and early finish times
|
|
ES= Maximum EF of all immediate predecessors
|
EF= ES + Activity time
|
|
Backward pass
|
a process that identifies all the late start and late finish times
|
|
LF= Minimum LS of all immediate following activities
|
LS=LF - Activity time
|
|
Slack time
|
free time for an activity
|
|
Slack= LS - ES or
|
Slack = LF - EF
|
|
the activities with zero slack are called
|
critical activities and are said to be on the critical path
|
|
the critical path...
|
is a continuous path through the project network that starts at the first activity in the project, terminates at the last activity in the project, and includes only critical activities
|
|
optimistic time (a)
|
the "best" activity completion time that could be obtained in a PERT network
|
|
pessimistic time (b)
|
"worst" activity time that could be expected in a PERT network
|
|
Most likely time (m)
|
the most probable time to complete an activity in a PERT network
|
|
When using PERT, we often assume that activity time estimates follow the beta distribution.
|
Expected activity time t = (a + 4m +b)/6
variance of activity completion time = [(b-a)/6]^2 o^2 = project variance = Sum(variances of activities on critical path) Z = (Due date - expected date of completion)/project variance Due date = expected completion time + (Z x project variance) |
|
crashing
|
shortening activity time in a network to reduce time on the critical path so total completion time is reduced.
Crash cost per period = (crash cost - normal cost)/ (normal time - crash time) |
|
as with every technique for problem solving, PERT & CPM have a number of advantages as well as several limitations.
|
Microsoft Project, the most popular example of specialized project management software, is extremely useful in drawing project networks, identifying the project schedule, and managing project costs and other resources
|