• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/10

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

10 Cards in this Set

  • Front
  • Back

Which of the following are risk responses? (Select TWO)

A. Delaying
B. Analysis
C. Acceptance
D. Avoidance
E. Work around

C. Acceptance
D. Avoidance

When handling multiple changes on a project, which of the following would be the BEST format in which to inform the team?

A. Follow the communication plan
B. Email documentation
C. Fax documentation
D. Hold a meeting with the project team

A. Follow the communication plan

While developing a project schedule, which of the following are purposes of a milestone? (Select TWO)

A. Milestones are not required since the major events are already placed in the project work plan without durations
B. Milestones are considered a placeholder in time for a major event
C. Milestones have no duration
D. Milestones are indicators that any of the project major events have already taken place
E. Milestones require a duration indication as to provide the key stakeholders of information as a key performance indicator (KPI)

B. Milestones are considered a placeholder in time for a major event
C. Milestones have no duration

Which of the following is a formula for estimating?

A. (BAC-EV)/CPI
B. Actual Cost + Estimated Time to Completion
C. EV/PV
D. (Optimistic + (4 x Most Likely) + Pessimistic) / 6

D. (Optimistic + (4 x Most Likely) + Pessimistic) / 6



Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies?

A. Arrow Diagramming Method (ADM)
B. Work Breakdown Structure (WBS)
C. Precedence Diagramming Method (PDM)
D. Critical Path Method (CPM)

A. Arrow Diagramming Method (ADM)

Which of the following is the key characteristic of the WBS?

A. It represents the entire scope of work for the project
B. assists the project manager with the qualified vendor selection process
C. It should be developed by others outside the project team as to eliminate bias
D. Eighty percent of the work packages will be developed by twenty percent of the project team

A. It represents the entire scope of work for the project

Which of the following tools is used for determining activity schedules based on optimistic, most likely and pessimistic estimates?

A. Key event/activity list
B. PERT
C. CPM
D. Gantt

B. PERT

In which of the following team development stages would the project manager MOST likely determine the structure of the project team?

A. Storming
B. Norming
C. Forming
D. Performing

C. Forming

Which of the following would be important to remember when scheduling a teleconference for a project team?

A. Providing food for the meeting to keep members satisfied
B. Identify morning or afternoon personalities of team members
C. Securing a meeting room that has sufficient seating
D. Considering time zone that meets business hours for whole team

D. Considering time zone that meets business hours for whole team


Which of the following is the condition in which the team just cannot finish the last piece of work and cannot complete the project?

A. The 80/20 rule
B. The progressive elaboration
C. The 95 percent phenomenon
D. The law of diminishing returns

C. The 95 percent phenomenon