Develop Project Charter |
Project birth certificate. Document that officially starts the project. Must have to have an official project. |
Birth Certificate |
|
Develop Project Management Plan |
A comprehensive document that guides the project’s execution and control & is much more than a schedule chart. |
Schedule / guide |
|
Direct & Manage Project Work |
This is the process where executing the work gets done. This process takes up about 80% of your time. |
“Roads get built, software apps get written, buildings are constructed...” |
|
Manage Project Knowledge |
This process benefits the project by leveraging lessons learned from precious projects, and it also benefits the performing organization so that it can hold onto the lessons learned on this project. |
Lessons learned |
|
Monitor & Control Project Work |
It looks at how the overall project is progressing and takes corrective action as needed through change requests. |
Checks and balances |
|
Perform Integrated Change Control |
The process where you assess ea change, weather if already occurred or it has been requested, to assess the impact on the project. |
One of the most important of all the processes. Manages change to the project. |
|
Close Project or Phase |
All about shutting the project or phase down properly. |
Finish Line |