Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/32

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

32 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)
How many processes in the "Project Integration Management" process?
6
Develop Project Charter
Develop Project Plan
Direct and Manage Project Execution
Monitor & Control Project Work
Perform Integrated Change Control
Close Project or Phase
Project Integration Management
What are the "Project Integration Management" processes?
Develop Project Charter
Develop Project Plan
Direct and Manage Project Execution
Monitor & Control Project Work
Perform Integrated Change Control
Close Project or Phase
Project Integration Management
Question:
Develop Project Charter
Process Group
Answer:

• Initiating
Project Integration Management
Question:
Develop Project Charter
Knowledge Area
Answer:

• Project integration management
Project Integration Management
Question:
Develop Project Charter
Inputs
Answer:

• Project statement of work
• Business case
• Contract
• Enterprise environmental factors
• Organizational Process Assets (OPA)
Project Integration Management
Question:
Develop Project Charter
Tools & Techniques
Answer:

• Expert judgement
Project Integration Management
Question:
Develop Project Charter
Outputs
Answer:

• Project charter
Project Integration Management
Question:
Develop Project Management Plan
Process Group
Answer:

• Planning
Project Integration Management
Question:
4.2 Develop Project Management Plan
Knowledge Area
Answer:

• Project Integration Management
Project Integration Management
Question:
Develop Project Management Plan
Inputs
Answer:

• Project charter
• Outputs from planning process
• Enterprise environmental factors (EEF)
• OPA
Project Integration Management
Question:
Develop Project Management Plan
Tools & Techniques
Answer:

• Expert judgement
Project Integration Management
Question:
Develop Project Management Plan
Outputs
Answer:

• Project management plan (PMP)
Project Integration Management
Question:
Direct and Manage Project Execution
Process Group
Answer:

• Executing
Project Integration Management
Question:
Direct and Manage Project Execution
Knowledge Area
Answer:

• Project Integration Management
Project Integration Management
Question:
Direct and Manage Project Execution
Inputs
Answer:

• PMP, Project Management Plan
• Approved change requests
• EEF
• OPA
Project Integration Management
Question:
Direct and Manage Project Execution
Tools & Techniques
Answer:

• Expert judgement
• PM information system
Project Integration Management
Question:
Direct and Manage Project Execution
Outputs
Answer:

• Deliverables
• Work performance information
• Change requests
• PMP updates
• Project document updates
Project Integration Management
Question:
Monitor & Control Project Work
Process Group
Answer:

• Monitoring & controlling
Project Integration Management
Question:
Monitor & Control Project Work
Knowledge Area
Answer:

• Project Integration Management
Project Integration Management
Question:
Monitor & Control Project Work
Inputs
Answer:

• PMP, Project Management Plan
• Performance reports
• EEF, Entreprise Environmental Factors
• OPA, Organizational Process Assets
Project Integration Management
Question:
Monitor & Control Project Work
Tools & Techniques
Answer:

• Expert judgment
Project Integration Management
Question:
Monitor & Control Project Work
Outputs
Answer:

• Change requests
• PMP updates
• Project document updates
Project Integration Management
Question:
Perform Integrated Change Control
Process Group
Answer:

• Monitoring & controlling
Project Integration Management
Question:
Perform Integrated Change Control
Knowledge Area
Answer:

• Project Integration Management
Project Integration Management
Question:
Perform Integrated Change Control
Inputs
Answer:

• PMP, Project Management Plan
• Work performance information
• Change requests
• EEF, Enterprise Environmental Factors
• OPA, Organizational Process Assets
Project Integration Management
Question:
Perform Integrated Change Control
Tools & Techniques
Answer:

• Expert judgement
• Change control meetings
Project Integration Management
Question:
Perform Integrated Change Control
Outputs
Answer:

• Change request status updates
• PMP updates
• Project document updates
Project Integration Management
Question:
Close Project or Phase
Process Group
Answer:

• Closing
Project Integration Management
Question:
Close Project or Phase
Knowledge Area
Answer:

• Project Integration Management
Project Integration Management
Question:
Close Project or Phase
Inputs
Answer:

• PMP, Project Management Plan
• Accepted deliverables
• OPA, Organizational Process Assets
Project Integration Management
Question:
Close Project or Phase
Tools & Techniques
Answer:

• Expert judgment
Project Integration Management
Question:
Close Project or Phase
Outputs
Answer:

• Final product, service, or result transition
• OPA updates
Project Integration Management