14 Cards in this Set

  • Front
  • Back

Two primary methods of project scheduling?

Program Evaluation and Review


Critical Path Method

What type of network ID usually associated with the PERT scheduling method?

Activity on Arrow

What type of network is usually associated with CPM scheduling?

Activity on Node

Can there be more than one critical path? Do you want there to be?

Yes.


No.

What is the duration of a milestone?

0

Can a critical path run over a dummy task?

Yes

Why is a dummy task included in a network diagram?

To show predecessors impact.

Can a critical path change?

Yes

How much float does the critical path have?

0

Can there be negative slack?


Would you leave project with negative slack?

Yes


No

How is total slack different from free slack?

Free slack - the slack an activity has before it delays the next activity.



Total slack - the slack an activity has before it delays the end of the project.

What are the three time estimated for probabilistic activity times?

Optimistic


Most likely


Pessimistic

Does recognizing and analyzing uncertainty cause uncertainty?

No

Does recognizing and analyzing uncertainty cause uncertainty to disappear?

No