8 Cards in this Set

  • Front
  • Back
Project Management Goals
1.) Plan- goals want to achieve what is needed
2.) schedule how to step up planning sequence
3.) control- not going as planned need to recover
PERT and CPM
program evaluation and Review Techniques (allow for variability) and critical path method (no variability)
graphically displays project activities
est. how long the project will take
1.) identify activities
2.) determine sequence
3.) create network
4.) determine activity time
5.) find critical path
Slack
Allowable delay
S = LS - ES OR LF - EF
Critical Path
longest path in activity
shortest time project can be completed
any delay on critical activity delays entire project
activities have zero slack
ES
Begin at start work forward
ES= 0 for first activities
EF = ES + activity time
ES = Max EF of all predecessors for non started activities
LS
Begin at the end work forward
LF= Max EF for ending activities
LS = LF-Activity time
LF= Min LS of all successors
Individual Paths
each are normally distributed due to Central Limit Theory
each paths duration time is independent of others paths duration times
Crash
shorten activity durations by injecting additional resources
increases direct expenses realize savings in indirect project costs