• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/138

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

138 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)

Early finish minus late finish

Total float

Critical path method

Forward and backward pass


Used to estimate minimum project duration and determine flexibility on network paths. Characterized by a zero float.


Considers leads, lags, logical relationships, constraints.


Does NOT consider resource limitations

CPI

Cost Performance Index = EV/AC (getting X.X per dollar) use 3 decimal places

SPI

Schedule Point Index = EV/PV (progressing at X% rate) use 3 decimal places

EAC

Estimate at Construction = BAC/CPI (total cost continuing at current work effort)

ETC

Estimate to Complete = EAC-AC ($X more cost to complete project)

VAC

Variance at Completion = BAC-EAC (over/under budget if resumed planned pace)

ROM

Rough order of magnitude -25% to +75%

Definitive estimate

-5% to +10%

Ethics 4 PM traits

Responsibility, fairness, respect, honesty

Development approach

(selected in PL develop proj mgmt plan)


Predictive (waterfall)


Incremental


Iterative


Adaptive (agile)


Hybrid

Ethical decision making

5As: ASSES facts; consider ALTERNATIVES; ANALYZE validity of decision; APPLY ethic principles to decision; ACTION (make a decision)

Project Information

Work performance data (raw); work performance information (analyzed); work performance reports (published)

Competing constraints

Scope


Schedule


Cost


Quality


Resources


Risk


Business documents

Needs assessment (goals, obj, opp/constraints)


Project business case (econ feasibility)


Project benefits mgmt plan (how maximizing and sustaining benefits)

Project selection methods

Constrained optimization (math calcs, algorithms)


Benefit Measurement Method (comparative, ie. ROI, NPV)

Economic model interpretation

ROI, IRR, NPV, present/future value, BCR


- biggest number, percentage or ratio


Opportunity cost - biggest number NOT selected


Payback period - shortest duration

Project success

Met business case


Organization moved from present to future state


Achieved organization objectives


Fulfilled contract terms


Achieved stakeholder satisfaction


Acceptable user adoption


Achieved quality of delivery and success criteria

PMO structures

Supportive (low control, provides policies and templates)


Controlling (moderate control, provides support and requires compliance)


Directive (high control, directly manages projects, provides PMs, responsible for outcomes)

Organizational structures

Organic, Functional, multi divisional


Matrix - strong, balanced, weak


Project oriented


PMO

Functional or multi-divisional org structure influence

Grouped by - job done (engineering) process, org function, region


PM authority - little, none


PM role - part-time


Manages budget - functional mgr


PM admin - part-time

Matrix org structure influence strong to weak

Group arranged - job function


PM authority - high, mod, low


PM role - full, PT, PT


Manages budget - PM, mixed, functional


PM admin - full, PT, PT

Project-oriented or PMO org. structure influences

Grouped by - project or mixed


PM authority - high


PM role - full-time


Manages budget - PM


PM admin - full-time

Initiation processes

Develop project charter (Integration)


Identify stakeholders (Stakeholder)


2

Planning Processes

(Initiate) Dev PM Plan



(Scope) Plan scope mgmt


Collect req


Define scope


Create WBS



(schedule) Plan sched mgmt


Define activities


Sequence activities


Estimate activity duration


Dev sched



(cost) Plan cost mgmt


Estimate costs


Determine budget



(Quality) Plan quality mgmt



(Resource) plan resource mgmt


Estimate activity resources



(Communications) plan com. mgmt



(Risk) plan risk mgmt


Identify risks


Perform qual risk analysis


Perform quan risk analysis


Plan risk response



(Procurement) plan proc mgmt



(Stakeholders) plan stake engagement

Executing Processes

(integration) Direct and manage project work


Manage proj knowledge



(Quality) manage quality



(Resource) acquire resources


Develop team


Manage team



(Communications) manage communications



(Risk) implement risk response



(Procurement) conduct procurements



(Stakeholder) manage stake engage

Monitoring and controlling processes

(integration) monitor & control proj work


Perform change control



(Scope) validate scope


Control scope



(Schedule) control schedule



(Cost) control cost



(Quality) control quality



(Resources) control resources



(Communication) monitor communications



(Risk) monitor risks



(Procurements) control procurements



(Stakeholder) monitor stake engage

Leadership styles

Laissez-faire (team makes own decisions)


Transactional (goals, feedback, rewards)


Servant leader (other people first)


Transformational (inspirational motivation)


Charismatic (energetic, confident, strong convictions)


*Interactional (combo transactional, transformational, charismatic)

Project Charter

Formally authorize project


name PM (and authority)


signed by sponsor


Co-developed w sponsor and PM



High level description, key deliverables


Milestone summary


Key stakeholder list


Project risk


Measurable objectives w success criteria


Project approval and exit criteria


Pre-approved financial resources

Business case

Used to create the project charter


States expected outcomes to justify investment


Includes business needs & cost benefit analysis



Expert judgement

ALWAYS a T&T (never input or output)

Project Management Plan

(10 mgmt plans)


Scope


Requirements


Schedule


Cost


Quality


Resources


Communication


Risk


Procurement


Stakeholder


(baselines)


Performance measurements baseline=


- Scope


- Schedule


- Cost


(Additional elements)


Change plan


Configuration plan


Project life cycle


Development approach


Management reviews

Issue log is created...?

(E) direct and manage project work

Lessons learned register is created...?

in (E) manage project knowledge

Assumptions log is created...?

In (IN) develop project charter

Change log is created...?

In (MC) perform integrated change control

Scope baseline contents

Scope statement


Work breakdown structure (WBS)


WBS dictionary

Requirements documentation is created...?

In (PL) collect requirements output

Requirements traceability matrix is created...?

In (PL) collect requirements output

Project scope statement is created....?

In (PL) define scope output

Joint application development (JAD)

Used in collect project requirements - in software development

User stories are created...?

In (PL) collect requirements, for role, goal and motivation

Project scope statement contains...

(like in a contract)


Project scope description


Project deliverables


Acceptance criteria


Project exclusions

Work breakdown structure (WBS)

Organized by phase/deliverable/contract into control account > planning package > work package (NO tasks or activities)



Activity list is created...?

In (PL) define activities as an output

Activity attributes are created...?

In (PL) define activities as an output

Milestone list is created...?

In (PL) define activities as an output

Process diagramming methods (PDM) for schedule dependencies

FS (most common)


FF


SS


SF (rarely used)

Schedule dependencies

Mandatory or hard logic (legally/ contractually required)


Discretionary or preferred/soft logic (could be best practices)


------


External (to project)


Internal (to project)

Project schedule network diagram is created...?

In (PL) sequence activities as an output

Configuration management plan

Defines documents that require formal changes and how to record and report changes to them (output in PL develop PM plan)

WBS dictionary

Detailed chart/list of deliverable, activity and schedule info

Reserve analysis (for costs)

Contingency - for known unknowns (included in cost baseline)


Management - for unknown unknowns (NOT in schedule/cost baselines)

Duration estimates are created...?

In (PL) estimate activity duration as output, does not include lags

Basis of estimates is created...?

In (PL) estimate activity duration + estimate costs + estimate activity resources outputs.


Constraints/assumptions/methods supporting how the estimate was developed

Monte carlo analysis

'simulation' Quantitative risk data analysis for cost, schedule and risk processes (by computer program) to evaluate impact


Output: Histogram or probability distribution

Schedule data is created...?

In (PL) develop schedule as an output, for describing and controlling

Project calendar is created...?

In (PL) develop schedule as an output

Schedule baseline contains

Project schedule


Schedule data


Project calendar

Project schedule is created

In (PL) develop schedule as an output, could be milestone chart, or more detailed bar chart or dependency diagram

Schedule forecasts are created...?

In (MC) control schedule as an output

Cost estimates are created ...?

In (PL) estimate costs as an output

Quality metrics are created...?

In (PL) plan quality management output

Quality reports are created...?

In (EX) manage quality output

Quality control measurements are created...?

In (MC) control quality output

Quality vs Grade

Q- degree a set of characteristics fulfill requirements (is it defective or not?)


G- deliverables having same use but different characteristics (waygu steak vs sirloin)

Attribute vs variable sampling

A- conforms or not


V- rated on a degree of conformity

Quality and/or resource management methodology history

Deming (focus on quality over costs)


Plan-do-check-act (PDCA)


Total quality management (TQM)


Kaizen / continual improvement / lean manufacturing



Juran (identify customer needs)


Pareto principle/ 80-20 rule


Resistance to change



Crosby (prevention)


Zero defects


Fitness for use


Doing it right the first time (DRIFT)


Cost of quality (COQ)

Resource requirements are created...?

In (PL) estimate activity resources output

Resource breakdown structure is created...?

In (PL) plan resource management then in estimate activity resources output

Physical resource assignments are created...?

In (EX) acquire resources output

Project team assignments are created...?

In (EX) acquire resources output

Resource calendars are created...?

In (EX) acquire resources output

Team charter is created...?

In (PL) plan resource management output

Type of Responsibility Assignment Matrix (RAM)

RACI - responsible, accountable, consult, inform

Project communications are created...?

In (EX) manage communications output

Test and evaluation documents are created...?

In (EX) manage quality output

Push communication

Sent directly without ensuring it reached or was understood


Ie. Memos, reports, emails, blog, press releases

Pull communication

For large info and/or audiences, recipients access of their own volition


Ie. PMIS, elearning, databases

Risk register is created...?

In (PL) identify risks output

Risk report is created...?

In (PL) identify risks output

Change management plan

How change requests will be authorized & incorporated (output in PL develop PM plan)

Performance measurement baseline (PMB)

Integrated scope/schedule/cost plan to measure performance (output in PL develop PM plan)

Management reviews

Milestones for PM & stakeholders to review progress (output in PL develop PM plan)

Variability vs ambiguity risks (non-event)

V- uncertainty about specific key event/activity ie. Productivity below target - DECISION USE monte carlo


A- uncertainty about future ie. Changes in regulations DECISION USE expert judgement or benchmarking w best practices

Prompt lists

T&T used in identify risks, lowest level of risk breakdown structure (RBS)


Brainstorming categories:


PESTLE


TECOP


VUCA

Qualitative vs quantitative risk analysis

Qual- subjective, rank/prioritize individual risks


Quant- numerical, analyze effect on overall project objectives ($ and/or probability)

Risk responses threat/opportunity/project

T & O: Escalate, accept


T: avoid, transfer, mitigate


O: share, enhance, exploit


Proj: same as T&O (sans escalate)

Fixed-Price (FP) contracts

Use w detailed scope and no changes expected, seller bares risk


FFP - firm fee


FPIF- incentive, % of profit (over/under)


FP-EPA - Economic price adjustment


Purchase order - commodity

Cost-reimbursable (cost +) contracts

Use when no detailed scope or expecting changes. Buyer accepts more risk.


CPFF - fixed fee


CPIF - incentive, % of profit (over/under)


CPAF - award, set amount

Time & materials contract

Use when beginning quickly without a detailed scope, usually with a 'not-to-exceed'. Buyer accepts more risk

Dispute resolution

Negotiation, mediation, arbitration, court

Stakeholder register is created...?

In (IN) identify stakeholders output

Stakeholder matrix (SEAM) categories

leading, supportive, neutral, resistant, unaware

Communication vs Stakeholder plans

C - how


S - what, when, why

Cost baseline

Includes contingency reserve


Excludes management reserve

Design for x

Used in manage quality analysis - design optimization

Quality management vs control

M= analysis, problem solving & reporting


C= inspection, testing and measurements, verify deliverables

Develop team - tuckman model

Forming


Storming


Norming


Performing


Adjourning

Progress vs status report

P= work accomplished since last report


S= all topics

validate vs control scope vs quality control

VS= acceptance of deliverable


CS= monitoring scope status and changes


QC= verify correctness of deliverable

Retrospectives vs backlog vs time boxing vs user stories

R= reviews recording lessons learned


B= work plan, ordered list of work in story form


T= iteration/release lengths (periods of work)


US= features/deliverables/requirements

Zero inventory

JIT (just in time) - quality assurance, efficient ordering system

Requirements management plan is created...?

In (PL) plan scope mgmt output.


Also called business analysis plan, how project requirements will be analyzed, documented and managed.

Cost of quality categories

Cost of conformance


- prevention (training, process, time)


- appraisal (testing, destructive test, inspection)



Cost of nonconformance


- internal failure (rework or scrap)


- external failure (found by customer: liability, warranty, lost business)

Cost estimates includes...?

Quantitative assessment of probable costs


Contingency


Management reserve



Labor


Materials


Equipment


Services


Facilities


Info tech


Cost of financing


Inflation allowance


Exchange rates


Cost contingency reserve


Indirect costs

Progressive elaboration

Ongoing refinement of the PM plan, iterative activities

Product requirements are created...?


& analyzed how...?

In (PL) define scope output, used to define products and services through:


Product breakdown


Requirements analysis


Systems analysis


Value analysis


Value engineering

Communication T&Ts

Expert judgement,


communication technology/models/methods/skills,


PMIS,


interpersonal and team skills,


data representation,


project reporting,


meetings

Conflict resolution techniques

1. Withdrawal/avoid - retreat or postpone


2. Smooth/accommodate - emphasize agreement and conceding ones position


3. Compromise/reconcile - solutions to temporarily or partially resolve (lose-lose)


4. Force/direct - pushing ones viewpoint usually through power (win-lose)


5. Collaboration/problem solve - incorporating different perspectives, cooperative (win-win)

Salience model

Classes of stakeholders based on:


Power


Urgency


Legitimacy (or proximity)

Nominal group technique

Used for brainstorming requirements, uses voting to rank (from 1-5) most useful ideas for further prioritization/brainstorming

Pre-assignment

For resources identified in a proposal or with specific expertise. Can be assigned in develop project charter or before initial resources management plan.

develop vs manage team

D: training, recognitions/rewards, locate and organize set up, team assessment



M: tracking performance, providing feedback, resolving issues, managing changes

Time-boxing is used for...?

In adaptive life cycle, time periods for releases or iterations focused on a goal, minimizes scope creep

Avoid vs mitigate risks

A: eliminate through changing something to avoid


M: reduce probability by adopting processes, more tests, creating prototypes

Communication vs Stakeholder vs project integration mgmt

C: ensuring collection, creation, distribution, retrieval and management of ALL project information - project reporting


S: communicating and working with stakeholders, engaging at project stages, clarifying/resolving issues


PI: leading and performing all work, documents performance data, aimed at producing deliverables, issue log

Funding limit reconciliation

Variance between funding & planned expenditures - rescheduling of work to level rate by date constraints for work

Resource management plan categories

Role - function, title


Authority - right to apply resources, make decisions, accept deliverables


Responsibility - assigned duties, to perform


Competence - skill and capacity

Active vs passive acceptance

A: establish a contingency reserve


P: no action, only periodic review

To acquire resources, negotiate with....?

Functional managers


Other PM teams


External organizations/suppliers

Change actions/types

Corrective - realigns performance


Preventative - ensures future performance


Defect repair - modify nonconformance


Updates - changes project documents

Unplanned training

Observation, conversation, PM appraisals

Decision tree inputs and outputs

Decision node: in- cost, out- decision made


Chance node: in- scenario probability/reward (if occurs), out- EMV


Net Path Value: payoff minus cost

Use to prevent bias in qualitative assesment

Facilitator

Consideration in make-or-buy analysis

Current resource allocation


Resource skills & abilities


Need for specialized/independent expertise


Expansion possibilities


Risks


Team performance assessment vs performance reviews

Team: overall team effectiveness during 'develop team'


Perform review: measures project performance against performance measurement baseline (combined scope, schedule, cost)

Collective bargaining agreement vs mandate plan

CBA: between employer & union re: hours, wages


MP: organizational re: takes, activities

Delphi technique

Anonymous questionnaires used to find consensus or agreement

Close phase/project trigger

Once authorized, product/service/result is delivered or handed over to operations/client/group

Scope mgmt plan contains?

PROCESSES for preparing/establishing


- scope statement


- WBS


- scope baseline


- formal acceptance of deliverables

Specification vs control limits (control chart)

S: represent customer or contractual requirements; outside of control limits


C: statistically calculated

OBS vs RACI/RAM

O: organized by department or team with work packages and project activities listed



R: specific resources assigned to each work packages or activities, can include responsibilities

Simulation is used for...?

Data analysis, effects of project risks - Monte Carlo

Decision matrix is used for....?

Decision making, used for stakeholders and assessing risk responses

Technical performance analysis is used...?

T&T in Monitor Risks

Sensitivity analysis is used for...?

Measuring potential risk impact


Output: tornado diagram

Influence diagram

Time ordering risk in quantitative


Then analyzed in monte carlo