• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/25

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

25 Cards in this Set

  • Front
  • Back
Name 4 key qualities of a Project Manager.
1) Experience
2) Expertise in construction management techniques, and IT software to support (planning, scheduling)
3) Switch between micro (onsite work) and macro (overall project)
4) Good people skills and delegate tasks
Function of PM
1) Control costs to ensure profit for GC
2) Maintain scheduling and completion date
3) Make sure all subs perform
4) Make sure CDs are followed, the right product is delivered
5 main PM components:
1) Project cost control
2) Project planning
3) Project scheduling
4) Production planning
5) Project Financial management
A tool used to manage large number of job activities and complicated sequential relationships is __________ _____________ __________.
critical path method
Name five steps to construction planning.
1) Determine general approach to project
2) Breakdown project into ‘activities’
3) Ascertain sequential order of activities
4) Present planning info as ‘network’
5) Receive endorsement (consensus) of plan by planning team
What are the two general approaches to planning?
1) Beginning-to-end
2) Top-down
What are 3 advantages of top-down planning?
1) Serves many network users simultaneously
2) Organizes work as it will be completed
3) Logical dependencies defined and accounted for
A single work step that has recognizable beginning and end & requires time is called a job ____________.
activity
Determining the order which activities are to be completed in the field is called job ___________.
logic
A drawing that shows the various networks and their activities in sequential order is called ___________ _____________.
precedence diagram
One of the reasons why it is good for construction project managers to have excellent people skills is that they are primarily managing people outside their own company.
TRUE OR FALSE
TRUE
The management technique employed by construction PMs is called "management-by-____________" and involves monitoring deviations from the plan and schedule.
exception
The most appropriate project planning technique for large, complex construction projects is called ______________.
Beginning-to-end planning
Top-down planning
Top-down planning
Regarding the ordering of job activities in a 'network', erecting formwork and placing rebar prior to pouring concrete is an example of a physical _______________.
restraint
What action does the PM take if the schedule is not going to meet the promised completion date?
Using the schedule and CPM, shorten the project length at least cost.
How can surplus or float time be used in the schedule planning?
Use float to to minimize resource conflicts and smooth demand
What are two blocks of time added to the schedule to account for common delays?
1) Time contingency
2) Weather delays
How is the critical path found?

How much of a project is typically "critical?"
The path of activities with zero float.

Generally, about 20%
The bar chart that shows the project planning and scheduling is called a __________ chart.
Gantt
The process of examining a project and its components to find a better way of accomplishing tasks is ____________.
re-engineering
Which of the following is the most commonly used unit of time in a 'network' consisting of sequentially ordered job activities?
Calendar days Man-hours
Working days Shifts
Hours Minutes
Working days
The most common project delay is due to _____________.
weather
A job activity is deemed to be on the critical path if its total float time is equal to _____.
zero
A special point in time within a network, which signifies the start or completion of a major portion of the project, is called a _____________________.
milestone
The subcontractor selection process should be based on quality prequalification BEFORE price is considered.
TRUE OR FALSE
TRUE