6 Cards in this Set
- Front
- Back
Lead |
Activities are moved closer together or overlap (negative time) |
|
Crashing |
Adding resources to reduce the project duration; adds costs to the project |
|
Lag |
Waiting time between activities (positive time) |
|
Fast tracking |
Allows project phases to overlap to reduce the project duration; adds risk to the project |
|
Free float |
Amount of time an activity can be delayed without delaying the next activity's start date |
|
Total float |
Amount of time an activity can be delayed without delaying the project's end date |