43 Cards in this Set
- Front
- Back
teaches that people will perform if they expect a reward, example of a retention bonus |
Expectancy theory |
|
Running tasks in parallel is an example of ______ |
fast tracking` |
|
adding more resources to the project is an example of __________ |
crashing |
|
Scope change requests would be handled as described in the _______________ and ___________ |
Scope management plan and the Change management plan |
|
Note: PM can make decisions. Do not make the mistake of assuming that a change control board exists, though in some organizations' methodologies, a change control board is authorized to make such decisions. |
PM can make decisions. |
|
hybrid agreement which acts like a Cost Plus Incentive Fee contract until the Ceiling Price, or Price Cap, is invoked, at which point it begins to act as a Fixed Price contract. |
Fixed Price Incentive Fee contract |
|
what are two alternative names for budget |
S-curve and Cost baseline |
|
The To-Complete-Performance-Index conveys the (cost or schedule) efficiency? |
Cost spending efficiency required to achieve the financial goals of the project ?? |
|
deviations from baselines are often due to what? |
incomplete risk identification and risk management |
|
what do you do when a project deviates significantly from established baselines? |
review the projects risk management process |
|
Inputs to the Develop Charter Process? |
Project Statement of Work Business Case Agreeements Enterprise Env Factors Org Process Assets |
|
Tools used in the Develop Charter Process? |
Expert Judgment Facilitation Techniques |
|
Output to Develop Charter |
Project Charter |
|
The same tools are used in the process Develop Project Plan and Develop Project Charter. Those tools are: |
Expert Judgment and Facilitation techniques |
|
true or false typically preventative and corrective actions are taken to adjust performance within the existing project baselines and do no change them |
true |
|
these are examples of ____________
adjusting the project to prevent the same problem from occuring again changing a resource because the resource;s last activity nearly failed to meet acceptance criteria |
preventative action |
|
preventative actions, corrective actions and defect repairs all should be reviewed and approved or rejected as part of the ____________ process |
performance integrated change control |
|
change requests are outputs to which two integration mgmt processes? |
direct and manage project work and monitor and control project work |
|
Tools used in Perform Integrated Change Control |
Expert Judgement meetings change control tools |
|
what are the tools used in Direct and Manage project work? |
meetings, expert judgment, project management information system |
|
Project Management Information System is a tool used in which two processes? |
Direct and Manage Project work AND Monitor and Control Project work |
|
Inputs to monitor and control project work |
project mgmt plan schedule forecasts cost forecasts validated changes work performance information enterprise envir. factors org process assets |
|
define scope has 4 inputs what are they? |
scope mgmt plan, project charter, requirements documentation, org process assets |
|
alternatives generation and product analysis are 2 of the 4 tools used in what process? |
define scope? |
|
what is the most important output of define scope? |
project scope statement |
|
two outputs to create WBS |
scope baseline and project document updates |
|
Tool used in Control scope |
Variance analysis |
|
Plan X Mgmt inputs are usually |
Project mgmt plan, project charter, org process assets and enterprise envir factors |
|
decomposition, rolling wave planning and expert judgment are tools used in which process? |
Define activities |
|
leads and lags are tools used in which two processes? |
Sequence Activities and Develop schedule |
|
which process uses these tools? Precedence diagramming method and dependency determination |
sequence activites |
|
Which process has this output? Project schedule network diagram |
sequence activities |
|
resource breakdown structure is an output of what process? |
estimate activity reasources |
|
true or false Risk register is needed when estimating time and cost |
true |
|
published estimating data, bottoms up estimating, project mgmt software, alternative analysis and expert judgement are all tools of what process? |
estimate activity resources |
|
Expert judgment, analogous estimating, parametric estimating, 3 point estimating, group decision making, and reserve analysis are all tools used in which 2 processes? |
estimate costs and estimate activity durations |
|
Remember Changes could mean that you need to update the cost baseline or scope baseline or schedule baseline BUT NOT NECESSARILY ALL |
Changes could mean that you need to update the cost baseline or scope baseline or schedule baseline BUT NOT NECESSARILY ALL |
|
this tool is used in risk mgmt determines the probability of any activity actually being on the critical path Or translates uncertainties into impacts to the total project Or Evaluates the overall risk on the project |
monte carlo analysis |
|
Remember this for the exam-
"Who generally has authority over the situation described in this question?" "What resolution of this problem would be serve the customers interest?" |
Who generally has authority over the situation described in this question?" "What resolution of this problem would be serve the customers interest?" |
|
What conflict resolution type is this? It is a lose lose situation since both parties can't get everything |
Compromising and reconciling- Brings some degree of satisfaction to both parties |
|
This technique for conflict mgmt emphasizes agreement |
Smoothing / accommodating |
|
Tip - when the exam requires you to solve a problem ask yourself what is the real problem behind the situation presented. |
when the exam requires you to solve a problem ask yourself what is the real problem behind the situation presented. |
|
Tip Comm Channels - A project with 15 stakeholders—the project manager is already included in the stakeholder count.The total number of stakeholders would be 15. - A project manager has a team of 15—the project manager isn’t included in the stakeholder count,so needs to be included. The total number of stakeholders would be 16 (team of 15+PM = 16). |
A project with 15 stakeholders—the project manager is already included in the stakeholder count. The total number of stakeholders would be 15. |