10 Cards in this Set

  • Front
  • Back
Develop Project Charter
INPUTS:
1. Contract
2. SOW (includes business need, scope description, strategic plan)
3. EEF
4. OPA (templates, procedures)

OUTPUTS:
1. Project Charter
Scope Definition
INPUTS:
1. OPA
2. Project Charter
3. Preliminary Project Scope Statement
4. Project scope Management Plan
5. Approved change requests

OUTPUTS:
1. Project Scope Statement
2. Requested Changes
3. Project scope management plan (updates)
Scope Planning
INPUTS:
1. EEF
2. OPA
3. Project Charter
4. Preliminary Project Scope Statement
5. Project Management Plan

OUTPUTS:
1. Project Scope Management Plan
Develop Preliminary Project Scope Statement
INPUTS:
1. Project Charter
2. SOW
3. EEF
4. OPA

OUTPUTS:
1. Prelimnary Project Scope Statement
Create WBS
INPUTS
1. OPA
2. Project Scope Statement
3. Project Management Plan
4. Approved change requests

OUTPUTS
1. Project Scope Statement (updates)
2. WBS
3. WBS dicitionary
4. Scope Baseline
5. Project Scope Management Plan (updates)
6. Requested changes
Activity Definition
INPUTS:
1. EEF
2. OPA
3. Project Scope Statement
4. WBS
5. WBS Dictionary
6. Project management plan

OUTPUTS:
1. Activity list
2. Activity attributes
3. Milestone list
4. Requested changes
Activity Resource Estimating
INPUTS
1. EEF
2. OPA
3. Activity list
4. Activity attributes
5. Resource availability
6. Project management plan

OUTPUTS:
1. Activity resource requirements
2. Activity attributes (updates)
3. Resource breakdown structure
4. Resource calendars (updates)
5. Requested changes
Activity Duration Estimating
INPUTS:
1. EEF
2. OPA
3. Project scope statement
4. Activity list
5. Activity attributes
6. Resource calendars
7. Project management plan

OUTPUTS:
1. Activity duration estimation
2. Activity attributes (updates)
Activity Sequencing
INPUTS:
1. Project scope statement
2. Activity list
3. Activity attributes
4. Milestone list
5. Approved change requests

OUTPUTS:
1. Project schedule network diagrams.
2. Activity list (updates)
3. Activity attributes (updates)
4. Requested changes
Cost Estimating
INPUTS:
1. EEF
2. OPA
3. Project scope statement
4. WBS
5. WBS dictionary
6. Project management plan (schedule & staffing mgmt plan, risk register)

OUTPUTS:
1. Activity cost estimates
2. Activity cost estimate supporting detail (description, basis of estimate, constraint, ROM)
3. Requested changes
4. Cost management plan (updates)