• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/25

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

25 Cards in this Set

  • Front
  • Back

AC - Actual Cost =

CV/(CPI - 1)
CV/(CPI - 1)

CV=Cost Variance
CPI=Cost Performance Index
PV - Planned Value =
SV/(SP1 - 1)
SV/(SP1 - 1)

SV=Scheduled Variance
SPI=Scheduled Performance Index
BAC - Budget At Completion =
∑(PV) at project completion
∑(PV) at project completion

∑=Summation
PV=Planned Value
EV - Earned Value =
% complete X BAC
% complete X BAC

BAC=Budget At Completion

CV - Cost Variance =

EV - AC (>0)
EV - AC (>0)

EV=Earned Value
AC=Actual Cost
SV - Schedule Variance =
EV - PV  (>0)
EV - PV (>0)

EV=Earned Value
PV=Planned Value
CPI - Cost Performance Index =
EV/AC (>1)
EV/AC (>1)

EV=Earned Value
AC=Actual Cost
SPI - Schedule Performance Index =
EV/PV (>1)
EV/PV (>1)

EV=Earned Value
PV=Planned Value

EAC - Estimate At Completion =

= AC/% Complete
= BAC/CPI
= AC/% Complete
= BAC/CPI

AC=Actual Cost
BAC=Budget at Completion
CPI = Cost Performance Index
ETC - Estimate To Completion =
EAC-AC

EAC=Estimate At Completion
AC=Actual Cost
VAC - Variance At Completion =
BAC-EAC
BAC-EAC

BAC=Budget At Completion
EAC=Estimate At Completion
TCPI - To Complete Performance Index =
= Remaining Work/Remaining Budget

= (BAC-EV)/(BAC-AC)
OR = (BAC-EV)/(EAC-AC)
= Remaining Work/Remaining Budget

= (BAC-EV)/(BAC-AC)
OR = (BAC-EV)/(EAC-AC)

BAC=Budget At Completion
EV=Earned Value
EAC=Estimate At Completion
AC=Actual Cost
Qualitative Risk Score =
Probability x (iscope + itime + icost + iquality)
Probability x (iscope + itime + icost + iquality)
Communication Channels =
N(N-1)/2

N = # of people in project
N(N-1)/2

N = # of people in project

EMV (Expected Monetary Value) =

Impact x Probability
Impact x Probability
Normal Distribution
1 σ = 68.26%
2 σ = 95.46%
3 σ = 99.73%
4 σ = 99.999%

Sigma = Standard Deviation = SD = σ
1 σ = 68.26%
2 σ = 95.46%
3 σ = 99.73%
4 σ = 99.999%

Sigma = Standard Deviation = SD = σ
Normal Distribution - 1 σ =
Normal Distribution - 1 σ =
68.26%
68.26%
Normal Distribution - 2 σ
Normal Distribution - 2 σ
95.46%
95.46%
Normal Distribution - 3 σ
Normal Distribution - 3 σ
99.74%
99.74%
Normal Distribution - 6 σ
Normal Distribution - 6 σ
99.999%
99.999%
Present Value (PV)
PV = FV/(1 + r)^n

FV = Future Value
r = Rate of Interest
n = Number of Years
PV = FV/(1 + r)^n

PV = Present Value
FV = Future Value
r = Rate of Interest
n = Number of Years
PERT (Program Evaluation and Review Technique) =
(O + 4M + P)/6

O=Optimistic
P=Pessimistic
M=Most Likely
(O + 4M + P)/6

O=Optimistic
P=Pessimistic
M=Most Likely
SD of Activity (σ) =
(P-O)/6

P=Pessimistic
O-Optimistic
(P-O)/6

P=Pessimistic
O-Optimistic
Variance of Activity =
(SD)^2
(SD)^2

SD=Standard Deviation
Float =
LS-ES = LF-EF

LS=Late Start
LF=Late Finish
ES=Early Start
EF=Early Finish
LS-ES = LF-EF

LS=Late Start
LF=Late Finish
ES=Early Start
EF=Early Finish