Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
25 Cards in this Set
- Front
- Back
AC - Actual Cost = |
CV/(CPI - 1)
CV=Cost Variance CPI=Cost Performance Index |
|
PV - Planned Value =
|
SV/(SP1 - 1)
SV=Scheduled Variance SPI=Scheduled Performance Index |
|
BAC - Budget At Completion =
|
∑(PV) at project completion
∑=Summation PV=Planned Value |
|
EV - Earned Value =
|
% complete X BAC
BAC=Budget At Completion |
|
CV - Cost Variance = |
EV - AC (>0)
EV=Earned Value AC=Actual Cost |
|
SV - Schedule Variance =
|
EV - PV (>0)
EV=Earned Value PV=Planned Value |
|
CPI - Cost Performance Index =
|
EV/AC (>1)
EV=Earned Value AC=Actual Cost |
|
SPI - Schedule Performance Index =
|
EV/PV (>1)
EV=Earned Value PV=Planned Value |
|
EAC - Estimate At Completion = |
= AC/% Complete
= BAC/CPI AC=Actual Cost BAC=Budget at Completion CPI = Cost Performance Index |
|
ETC - Estimate To Completion =
|
EAC-AC
EAC=Estimate At Completion AC=Actual Cost |
|
VAC - Variance At Completion =
|
BAC-EAC
BAC=Budget At Completion EAC=Estimate At Completion |
|
TCPI - To Complete Performance Index =
|
= Remaining Work/Remaining Budget
= (BAC-EV)/(BAC-AC) OR = (BAC-EV)/(EAC-AC) BAC=Budget At Completion EV=Earned Value EAC=Estimate At Completion AC=Actual Cost |
|
Qualitative Risk Score =
|
Probability x (iscope + itime + icost + iquality)
|
|
Communication Channels =
|
N(N-1)/2
N = # of people in project |
|
EMV (Expected Monetary Value) = |
Impact x Probability
|
|
Normal Distribution
|
1 σ = 68.26%
2 σ = 95.46% 3 σ = 99.73% 4 σ = 99.999% Sigma = Standard Deviation = SD = σ |
|
Normal Distribution - 1 σ =
|
68.26%
|
|
Normal Distribution - 2 σ
|
95.46%
|
|
Normal Distribution - 3 σ
|
99.74%
|
|
Normal Distribution - 6 σ
|
99.999%
|
|
Present Value (PV)
|
PV = FV/(1 + r)^n
PV = Present Value FV = Future Value r = Rate of Interest n = Number of Years |
|
PERT (Program Evaluation and Review Technique) =
|
(O + 4M + P)/6
O=Optimistic P=Pessimistic M=Most Likely |
|
SD of Activity (σ) =
|
(P-O)/6
P=Pessimistic O-Optimistic |
|
Variance of Activity =
|
(SD)^2
SD=Standard Deviation |
|
Float =
|
LS-ES = LF-EF
LS=Late Start LF=Late Finish ES=Early Start EF=Early Finish |