• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/23

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

23 Cards in this Set

  • Front
  • Back

Earned Value Management Formulas

PV - Planned Value


EV - Earned Value


AC - Actual Costs


BAC - Budget at Completion

Variance formulas

CV - Cost of Variance


SV - Schedule Variance







Index Formulas



CPI - Cost Performance Index


SPI - Schedule Performance Index





Forecasting Forumals

EAC - Estimate at Completion


ETC - Estimate to Complete


VAC - Variance at completion


TCPI - To complete Performance Index

PV =

SV / (SPI-1)

(Planned Value)




Authorized budget assigned to scheduled work.

EV=

(Earned Value) = % COMPLETE * BAC or PV


(Budget at Complete) (Present Value)


AC =

(Actual Cost) = CV / (CPI-1)


(Cost Variance) (Cost Performance Index)
BAC =

(Budget at completion)

SUM of PV (Planned value) at project completion

The value of total planned work, the project cost baseline.

CV=

(Cost Variance) = EV-AC

(>0 good)

(Earned Value) (Actual Costs)
SV =

(Schedule Variance)

SV = EV-PV
(>0 good)

(Earned Value) (Planned Value)

VAC

(Variance at Completion)

VA = BAC - EAC
(Budget at Completion - Estimate at Completion)
CPI =

(Cost Performance Index)

CPI = EV/AC
(>1 good)

(Earned Value) (Actual Costs)
SPI =

(Schedule Performance Index)

SPI=EV/PV
(>1 good)

(Earned Value) (Planned Value)

EAC

Estimate at Compeltion


EAC = BAC / CPI

ETC
(Estimate to Complete)
EAC-AC
(Estimate at completion - Actual Cost)
TCPI
(BAC-EV) / (BAC-AC)
-or-
(BAC-EV) / (EAC-AC)

Remaining work / Remaining Budget
EMV =
(Expected Monetary Value)
Impact * Probability
FIND COMMUNICATION CHANNELS
N (N-1)
----------
2

(n = number of people)
COST TO BUY =
Initial cost + # of months * monthly maintenance costs
NORMAL DISTRIBUTION
(6 sigma formulas)
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.999%
1 SD = 1 Sigma
PV =

(Present Value)
FV
----------
(1 + r)n

(FV = Future Value; r=rate of interest)
(n = number of time periods
PERT =
(Program Evaluation and Review Technique)
(O+4M+P)/6

(Optimistic) (Most Likely) (Pessimistic)

Standard Deviation

STD=(P-O)/6