Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
23 Cards in this Set
- Front
- Back
Earned Value Management Formulas |
PV - Planned Value EV - Earned Value AC - Actual Costs BAC - Budget at Completion |
|
Variance formulas |
CV - Cost of Variance SV - Schedule Variance |
|
Index Formulas |
CPI - Cost Performance Index SPI - Schedule Performance Index |
|
Forecasting Forumals |
EAC - Estimate at Completion ETC - Estimate to Complete VAC - Variance at completion TCPI - To complete Performance Index |
|
PV =
|
SV / (SPI-1)
(Planned Value) Authorized budget assigned to scheduled work. |
|
EV=
|
(Earned Value) = % COMPLETE * BAC or PV (Budget at Complete) (Present Value) |
|
AC =
|
(Actual Cost) = CV / (CPI-1) (Cost Variance) (Cost Performance Index) |
|
BAC =
|
(Budget at completion) The value of total planned work, the project cost baseline. |
|
CV=
|
(Cost Variance) = EV-AC (>0 good)(Earned Value) (Actual Costs) |
|
SV =
|
(Schedule Variance)
SV = EV-PV |
|
VAC
|
(Variance at Completion) (Budget at Completion - Estimate at Completion) |
|
CPI =
|
(Cost Performance Index) (>1 good) (Earned Value) (Actual Costs) |
|
SPI =
|
(Schedule Performance Index) (>1 good) (Earned Value) (Planned Value) |
|
EAC |
Estimate at Compeltion EAC = BAC / CPI |
|
ETC
(Estimate to Complete) |
EAC-AC
(Estimate at completion - Actual Cost) |
|
TCPI
|
(BAC-EV) / (BAC-AC)
-or- (BAC-EV) / (EAC-AC) Remaining work / Remaining Budget |
|
EMV =
(Expected Monetary Value) |
Impact * Probability
|
|
FIND COMMUNICATION CHANNELS
|
N (N-1)
---------- 2 (n = number of people) |
|
COST TO BUY =
|
Initial cost + # of months * monthly maintenance costs
|
|
NORMAL DISTRIBUTION
(6 sigma formulas) |
1 sigma = 68.26%
2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.999% 1 SD = 1 Sigma |
|
PV =
(Present Value) |
FV
---------- (1 + r)n (FV = Future Value; r=rate of interest) (n = number of time periods |
|
PERT =
(Program Evaluation and Review Technique) |
(O+4M+P)/6
(Optimistic) (Most Likely) (Pessimistic) |
|
Standard Deviation |
STD=(P-O)/6 |