Question:
Estimate Costs Process Group |
Answer:
• Planning |
Project Cost management
|
|
Question:
Estimate Costs Knowledge Area |
Answer:
• Project Cost management |
Project Cost management
|
|
Question:
Estimate Costs Inputs |
Answer:
• Scope baseline • Project schedule • HR plan • Risk register • EEF • OPA |
Project Cost management
|
|
Question:
Estimate Costs Tools & Techniques |
Answer:
• Expert judgement • Analogous estimating • Parametric estimating • Bottom up estimating • 3 point estimates • Reserve analysis • Cost of quality • PM estimating software • Vendor bid analysis |
Project Cost management
|
|
Question:
Estimate Costs Outputs |
Answer:
• Activity cost estimates • Basis of Estimate (BOE) • Project document updates |
Project Cost management
|
|
Question:
Determine Budget Process Group |
Answer:
• Planning |
Project Cost management
|
|
Question:
Determine Budget Knowledge Area |
Answer:
• Project cost management |
Project Cost management
|
|
Question:
Determine Budget Inputs |
Answer:
• Activity cost estimates • BOE • Scope baseline • Project schedule • Resource calendars • Contracts • OPA |
Project Cost management
|
|
Question:
Determine Budget Tools & Techniques |
Answer:
• Cost aggregation • Reserve analysis • Expert judgement • Historical relationships • Funding limit reconciliation |
Project Cost management
|
|
Question:
Determine Budget Outputs |
Answer:
• Cost performance baseline • Project funding requirements • Project document updates |
Project Cost management
|
|
Question:
Control Costs Process Group |
Answer:
• Monitoring & controlling |
Project Cost Management
|
|
Question:
Control Costs Knowledge Area |
Answer:
• Project Cost Management |
Project Cost Management
|
|
Question:
Control Costs Inputs |
Answer:
• PMP, Project Management Plan • Project funding requirements • Work performance information • OPA, Organizational Process Assets |
Project Cost Management
|
|
Question:
Control Costs Tools & Techniques |
Answer:
• Earn Value Management (EVM) • Forecasting • To-complete performance index (TCPI • Performance reviews • Variance analysis • PM software |
Project Cost Management
|
|
Question:
Control Costs Outputs |
Answer:
• Work performance measurements • Budget forecasts • OPA updates • Change requests • PMP updates • Project document updates |
Project Cost Management
|
|
Question:
How many processes in "Project Cost management" ? |
3
Estimate Cost Determine Budget Control Costs |
Project Cost management
|