• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/15

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

15 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)

No. of Communication Channels

n (n-1)/2


n = number of members in the team

n should include the project manager

e.g. if the no. of team members increase from 4 to 5, the increase in communication channels:
5(5-1)/2 – 4(4-1)/2 = 4

Schedule Performance Index (SPI)

SPI = EV/PV


EV = Earned Value
PV = Planned Value

< 1 behind schedule
= 1 on schedule
> 1 ahead of schedule

Cost Performance Index (CPI)

CPI = EV/AC


EV = Earned Value
AC = Actual Cost

< 1 Over budget
= 1 On budget
> 1 Under budget

sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment

Schedule Variance (SV)

SV = EV – PV


EV = Earned Value
PV = Planned Value

< 0 Behind schedule
= 0 On schedule
> 0 Ahead of schedule

Cost Variance (CV)

CV = EV – AC


EV = Earned Value
AC = Actual Cost

< 0 Over budget
= 0 On budget
> 0 Within budget

Estimate at Completion (EAC) if original is flawed

EAC = AC + New ETC


AC = Actual Cost
New ETC = New Estimate to Completion

if the original estimate is based on wrong data/assumptions or circumstances have changed

Estimate at Completion (EAC) if BAC remains the same

EAC = AC + BAC – EV


AC = Actual Cost
BAC = Budget at completion
EV = Earned Value

the variance is caused by a one-time event and is not likely to happen again

Estimate at Completion (EAC) if CPI remains the same

EAC = BAC/CPI


BAC = Budget at completion
CPI = Cost performance index

if the CPI would remain the same till end of project, i.e. the original estimation is not accurate

Estimate at Completion (EAC) if substandard performance continues

EAC = AC + (BAC -EV)/(CPI*SPI)


AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index

use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used

To-Complete Performance Index (TCPI)

TCPI = (BAC – EV)/
(BAC – AC)


BAC = Budget at completion
EV = Earned value
AC = Actual Cost


TCPI = Remaining Work
/Remaining Funds


BAC = Budget at completion
EV = Earned value
CPI = Cost performance index

< 1 Under budget
= 1 On budget
> 1 Over budget

Estimate to Completion

ETC = EAC -AC


EAC = Estimate at Completion
AC = Actual Cost

Variance at Completion

VAC = BAC – EAC


BAC = Budget at completion
EAC = Estimate at Completion

< 0 Under budget
= 0 On budget
> 0 Over budget

PERT Estimation

(O + 4M + P)/6


O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate

Standard Deviation

(P – O)/6


O= Optimistic estimate
P= Pessimistic estimate

this is a rough estimate for the standard deviation

Float/Slack

LS – ES


LS = Late start
ES = Early start


LF – EF


LF = Late finish
EF = Early finish

= 0 On critical path
< 0 Behind schedule