Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
15 Cards in this Set
- Front
- Back
- 3rd side (hint)
No. of Communication Channels |
n (n-1)/2 n = number of members in the team |
n should include the project manager |
|
Schedule Performance Index (SPI) |
SPI = EV/PV EV = Earned Value |
< 1 behind schedule |
|
Cost Performance Index (CPI) |
CPI = EV/AC EV = Earned Value |
< 1 Over budget |
|
Schedule Variance (SV) |
SV = EV – PV EV = Earned Value |
< 0 Behind schedule |
|
Cost Variance (CV) |
CV = EV – AC EV = Earned Value |
< 0 Over budget |
|
Estimate at Completion (EAC) if original is flawed |
EAC = AC + New ETC AC = Actual Cost |
if the original estimate is based on wrong data/assumptions or circumstances have changed |
|
Estimate at Completion (EAC) if BAC remains the same |
EAC = AC + BAC – EV AC = Actual Cost |
the variance is caused by a one-time event and is not likely to happen again |
|
Estimate at Completion (EAC) if CPI remains the same |
EAC = BAC/CPI BAC = Budget at completion |
if the CPI would remain the same till end of project, i.e. the original estimation is not accurate |
|
Estimate at Completion (EAC) if substandard performance continues |
EAC = AC + (BAC -EV)/(CPI*SPI) AC = Actual Cost |
use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used |
|
To-Complete Performance Index (TCPI) |
TCPI = (BAC – EV)/ BAC = Budget at completion TCPI = Remaining Work BAC = Budget at completion |
< 1 Under budget |
|
Estimate to Completion |
ETC = EAC -AC EAC = Estimate at Completion |
|
|
Variance at Completion |
VAC = BAC – EAC BAC = Budget at completion |
< 0 Under budget |
|
PERT Estimation |
(O + 4M + P)/6 O= Optimistic estimate |
|
|
Standard Deviation |
(P – O)/6 O= Optimistic estimate |
this is a rough estimate for the standard deviation |
|
Float/Slack |
LS – ES LS = Late start LF – EF LF = Late finish |
= 0 On critical path |