• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/24

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

24 Cards in this Set

  • Front
  • Back

ROM

Rough Order of Magnitude


Done when little is knows about project specifics, gives a large range, done in Initiating process

CV

Cost Variance


EV - AC

ETC

Estimate to complete


EAC - AC


BAC - EV

TCPI

To-complete performance index


(BAC - EV) / (BAC - AC)

EAC

Estimate at completion


BAC / CPI


AC + (BAC - EV)


AC + (BAC - EV) / (CPI * SPI)

Beta Distribution

Uses weighted averages to compute activity durations

Crashing

Technique used to shorten the schedule duration for the least incremental cost by adding resources

Network diagram

Graphical representation of logical relationships among project schedule activities


Shows dependencies

Precedence Diagramming

Method of constructing network diagram using boxes, or nodes, to represent activities and connects them with arrows


Also called activity on node (AON) method

Heuristic

Generally accepted rule

Standard deviation

(Pessimistic - optimistic) / 6

Resource histogram

Bar chart showing amount of time that a resource is scheduled to work over a series of time periods

Matrix organization

Any organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of persons assigned to the project

Gantt chart

Bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates

Pareto Diagram

Contains both bars and lines


Left vertical axis is frequency of occurrence or cost


Right vertical axis is cumulative percentage of the total number of occurrences or total cost


Purpose is to highlight the most important among a set of factors

Monte Carlo Analysis

Computer mode is iterated many times, with input values chosen at random for each iteration driven by input data, including probability distributions and probabilistic branches.


Outputs are generated to represent the range of possible outcomes for a project

EVA

Earned value analysis

SV

Schedule variance


EV - PV

SPI

Schedule performance index


EV / PV

CPI

Cost performance index


EV / AC

VAC

Variance at completion


BAC - EAC

Resource leveling

Adjustments are made to the project schedule to optimize the allocation of resources


May affect critical path

Resource smoothing

Free and total float are used without affecting the critical path

CPM

Critical Path Method


Method used to estimate minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model