• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/107

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

107 Cards in this Set

  • Front
  • Back

Submittals are approved by

Owners or architect?

Subsurface conditions (sooo boring, test piles etc) are whose responsibility?

Owner

Failure to do a required act

Nonfeasance

The unit price form of construction cobra facts is desirable when

Variations are expected in quantities and materials estimated

The largest single item of overhead cost for an la office is

Salaries of administrative personnel


(Know direct costs vs overhead)

Insurance to cover vandalism during course of construction is furnished by:

Contractors coverage for liability

The actual cost of materials delivered to the site exceeds the cash allowance stayed in the contract:

The contractor may not request increase in the cost of installation

A complete set of contract documents normally includes

Cost estimate and contract only (does not include advertisement)

The la's responsibility in administration of the construction contract ends:

Upon final payment by the owner to the contractor

Limit of liability clause in la contract should be used with

Everyone, always! (Steady small, large new..)

Best method to recruit new personnel

Employees recommendation


Classifieds in paper


Professional journal


Employment agency

Payment bonds prevent

LIENS

For a public project, without a bond, subs and suppliers do what if they aren't paid?

File a STOP NOTICE

Miller act

Requires payment and performance bonds on state projects

MILESTONES

Completion of portions of the work by interim dates.




Require the contractor to schedule and perform the work in a manner that meets the milestones for specified portions of the work.




Changes in milestone dates or timeline = change order!

CONSTRUCTIVE CHANGE

owner changes conditions- contractor is entitled to adjustment in contract price and timeline.

WHEN DOES WARRANTY BEGIN

at substantial completion

LIQUIDATED DAMAGES

Failure to finish on time is considered a BREACH OF CONTRACT




Only can be at an amount that is reasonable in the light of the anticipated or actual loss caused by the breach.




COMPENSATORY not PUNITIVE (punish)




LD ends at substantial completion because "usable" by owner.

MECHANIC LIEN VS PAYMENT BOND

Mechanic Lien's cannot be placed against public property- therefore, the payment bond is the only protection these claimants have if they are not paid for the goods and services they provide to the contract. file a stop notice. Upon notice, the owner will make no further payments to the general contractor until the claimant has been paid.




Miller Act requires payment and performance bond on federal construction projects.

WHO DO BONDS PROTECT?

They protect the OWNER. They are not intended to protect the contractors that post them. They protect the OWNER of the construction project against contractor failure and protect certain laborers, materials suppliers and subcontractors against non-payment.

What is a FUD

It illustrates general project components while taking into consideration the components' sizes, shapes, and relationships to one another.

Focus Groups

A good way to discover the attitudes of a wide variety of potential users. They allow groups to discuss topics in depth and they provide opportunities for participants' views to be considered. Focus group conversations can be spontaneous and can elicit solutions to a variety of potential project concerns. The client can be included in the process.




Start with broad questions, which will generate opinions on various topics. The topics can later be pared down to more specific questions or ideas.

FOUR CORNER RULE

Form the face value of a written agreementDrawings, Spec's General Conditions etc.

FORCE ACCOUNT

another name for self-performance method.no contracts are written - all work done in house.

PROMISSORY ESTOPPEL

promissory estoppel prevents one party from withdrawing a promise made to a second party if the latter has reasonably relied on that promise.common = subcontractor withdrawing a bid after GC has won contract based on that bid.

ANOTHER WORD FOR EMINENT DOMAIN

CONDEMNATION

RIGHT OF WAY VS EASEMENT

right of way - property is owned (either purchased or condemned by eminent domain)




easement - a right to use, not owned.

DISCHARGING A LIEN

-Payment of the debt


-Foreclosure




First the suppliers are paid- then contractor and subcontractor

CONTINGENT LIABILITY

an injured third party is not affected by a contract between the two other parties.the owner may be held liable or have contingent liablity for damages sustained by a third party due to contractor's actions. A GC may have contingent liability due to subcontractor's actions.if a consultant is judged to be independent, a third party can seek recovery directly from them.





acceptable and non acceptable reasons to withdraw a low bid

unacceptable:


-error of judgement




acceptable:


-error of fact


- material error


-mistakesgrounds to nullify the bid since there were no meeting of minds.

design specifications ALSO CALLED:

MATERIAL AND WORKMAN SPECS


METHODS AND MATERIALS SPEC


PRESCRIPTIVE SPECS

PROPRIETARY SPECS

AREN'T USED FOR PUBLIC PROJECTS BECAUSE THEY ONLY GIVE ONE OPTION (CLOSED)


no allowance for alternatives


which drives up price and eliminates any competition.




open specs allow for more competitive lower prices

SUBMITTALS

designer should indicate when required.Could include cut-sheets, calcs, certificates, manufacturere's instructions, methods, etc.submittals are not generally required by proprietary, closed specs

project schedule

Contractor required to submit to owner showing critical path schedule, sequence of work, how work will meet number of working days or completion date specified in contract.once accepted by owner, both are bound to meet obligations to keep schedule.

letter agreement contract

written by consultant.generally produced from a master form.Preliminary contractual document which, with or without specifying the agreed to price or amount, authorizes a contractor to begin immediately with the job or project. A letter contractobligates the customer (principal) to either prepare the final (definitive) contract within the specified timeframe, or to reimburse the contractor for costs incurred under the letter.

Certification of Payments/ Schedule of Values

issuance of payment certificates by architect.Schedule of ValuesThe basis for calculating the owner's progress payments to the contractor is the schedule of values. This is an allocation of the total contract price among each of the segments of the work. It is prepared by the contractor and submitted for the architect's review and approval before the first payment.

LA CA Duties

Spending one day per week on site, attending a meeting and observing theprogress of construction• Responding to questions from the contractors and material suppliers• Reviewing shop drawings and submittals• Reviewing and certifying monthly applications for payment• Authoring clarifications and minor changes to the documents• Assisting consultants with construction administration duties• Record keeping• Project closeout responsibilities

SITE INSPECTION

There are only 2 inspections: at substantial completion and final completion.In the first of these two inspections, the architect is looking at the “completed” work to determine if it appears to be “substantially” complete.

GANT CHART

gantt chart = horizontal bar chart



INDIRECT COSTS

indirect costsIndirect costs are costs that are not directly accountable to a cost object (such as a particular project, facility, function or product). Indirect costs may be either fixed or variable. Indirect costs include administration, personnel and security costs. These are those cost which are not directly related to production.Costs usually allocated indirectlyUtilitiesRentAudit and legalAdministrative staffEquipment rentalFuelMaintenanceGeneratorSecurityTelephoneBill expense

DIRECT COSTS

Direct costs are directly attributable to the cost object. In construction, the costs of materials, labor, equipment, etc, and all directly involved efforts or expenses for the cost object are direct costs.




Costs usually charged directly:


- Project staff


-Consultants


-Project supplies


- Publications


-Travel


-Labour


-Material


-Directors Salary




Costs either charged directly or allocated indirectly


- Telephone charges


- Computer use


-Project clerical personnel


-Postage and printing


-Miscellaneous office supplies


- Overhead

DIRECT PAYROLL VS DIRECT LABOR COSTS

direct payroll costs:Payroll is the share of labor costs that goes directly to employees in their paychecks, or is withheld from their paychecks to cover their personal taxes.




direct labor costs: also include the employer's matching contribution to social security and medicare funds. It also includes unemployment insurance and industrial insurance taxes. These are direct labor costs because they accrue directly on the sums that you pay your employees in exchange for their labor.

A LANDSCAPE ARCHITECT WOULD NOT NORMALLY APPROVE A CONTRACTOR'S REQUEST FOR EXTENSION OF TIME FOR HTE COMPLETION OF THE CONTRACT BASED ON DELAYS CAUSED BY

excessive amounts of uncorrected work

contracts may be terminated

-at the convenience of the owner


-due to contractor default

the estimate of probably construction cost furnished by the landscape architect to the owner is

subject to market and competitive conditions during bidding

b101- owner/landscape architect agreement the architect is responsible for proving

too surveys and soil investigation

the basis of an accounting system in a landscape architect's office which systematically lists the items reflecting the activities of the organization is

a chart of accounts

the largest single items of overhead cost for a la office is

salaries for administrative personnel

planning tool graphically illustrating interrelationships while scheduling starting and finishing times

critical path method (CPM)

which cost analysis methods are currently widely employed?

AREA AND VOLUME


UNIT USE


QUANTITY AND COST

ESSENTIAL ELEMENTS OF A WRITTEN CONTRACT

the identification of parties involved


statement of lawful consideration


statement of the purpose and time of performance

sum which the contractor may be required to include in his bid and contract sum for specific purposes relating to items to be included in the project are called:

COST ESTIMATES

FIELD INSPECTION is an inspection conducted to check on:

-contractor compliance with contract specifications

-construction deficiencies and poor workmanship


-safety and labor code violations


insurance to cover vandalism during the course of construction is furnished by:

the contractor's coverage for liability

costs for compaction testing should be paid by the

owner

if the actual cost of the materials delivered to the site exceeds the cash allowance stated in the contract documents the


owner can refuse to pay the difference




-The contract sum is not adjusted


-landscape architect is not liable for difference


-contractor may not request an increase in the cost of installation ?

the landscape architect should obtain prior written permission of the owner in order to:

-sublet any portion of work (assign?delegate?)

FIXED fee method of charging for professional services is most useful in

master planning?

revised working drawings

record drawings

Licensure vs Certification

Licensure: state regulation of a profession (not a function of ASLA) ONLY GAURAUNTEES MINIMAL COMPETENCY




Certification: Overseen by CLARB- going above and beyond minimal competency. Demonstrates higher understanding and skill.

PRACTICE LAW

PROTECTS HEALTH SAFETY AND WELFARE- NOT LA PROFESSION.

LICENSURE

protects public health, safety and welfare - does NOT protect profession, but does increase professional status, decreases insurance rates and improves job status and ability to obtain quality work.

Order of Licensure/

License (LEGAL)- minimal competency


----> Accreditation (EDUCATION) ----> Certification (CLARB) - above average professional

rfp vs rfq

request for qualifications- submit examples of previous work, experience, qualifications in order to recieve an RFP from a shortlist of professional firms.




request for proposals- REQUEST OF IDEAS ABOUT A PROJECT

Overhead vs Direct Costs

Overhead: expenses without direct association to a specific project (indirect costs) COST OF DOING BUSINESS


ex: phone calls, prints, materials




Direct Costs: costs directly associated to a project


(phone calls, flights, time, prints, materials, etc.)



Fees that are best for each amount of time

When you know scope of work and clearly defined:


-% of construction (total construction budget)


-Lump Sum




When you don't know scope of work- hard to define and darwings aren't complete


-Cost Plus


-Hourly (Time Per Diem) - with Min/Max Upset



Types of Work and their standard fee structure:


-Feasibility study


-Master Planning


-Implementation (CD's)

1. Fixed Fee/Per Diem (Easy to predict)


2. Lump Sum (Fixed Fee)


3. % of construction

Elements of a contract

1. ASSENT (mutual agreement) - offer and acceptance. If any changes are made or modification to original offer it becomes a counter pffer - both parties must both accept the offer with signatures.




2. CONSIDERATION- the benefit/value/motive/$ that draws two parties together




3. LEGAL CAPACITY- must be 18, cannot be intoxicated, mentally ill or handicapped, cannot be under legal guardianship by another




4. LEGAL OBJECTIVE- cannot contract an illegal activity





Order of Legal Precedent

1. constitution


2. statute


3. regulation


4. Law of the case



Penalties vs. Liquidated Damages

PENALTY- pay a sum of money in the event that the contract has been breached.


(associated with BONUS-) - you can't have one without the other


-The amount payable is excessive when


compared to loss



LIQUIDATED DAMAGES-similar but the intent is only recover the amount of the damages you sustain.


-Genuine estimate of the loss to be


suffered by the party in the event of a


breach




The real difference between the two is whether you are trying to profit from the breach.




-contract terms should not be used for a party to profit from the breach of contract by the other party.


-

Legitimate/non-legitimate reasons for late work:

-Added work


-If another party delays the work of another (crucial questions arise that must be answered prior to work beginning- and L.A is out of town and can't be reached, etc)




-Consultants or subcontractors didn't finish work on time


-Bad Weather



BREACHES OF DUTY

NONFEASANCE- "no-t done"


(Didn't fulfill responsibility)




MISFEASANCE- legal act was fulfilled but not done correctly. "MIS-TAKE"




MALFEASANCE- "ma-lice" - breaks the law

Do not tell a contractor how to do his work- instead tell them how it should look or function (perform) and let them figure out construction. This shifts LIABILITY from you to contractor should structure fail or injure someone. Be especially careful if you are acting as the AGENT of owner- since this would shift the liability to THEM.

REAL PROPERTY VS PERSONAL PROPERTY

REAL PROPERTY is fixed and immovable




PERSONAL PROPERTY is mobile and perishable (car, money, etc.)

MAINTENANCE BOND

Gaurantees that completed work will be free of defects for a set period of time.

mechanics liens must be filed

within 45 days of substantial completion of project

INSURANCE TO KNOW:

- Limited Liability (errors and omissions)


-Builders Risk (Construction --> fire, weather, flood etc.)


-Contractors General Liability (CGL)


-Workman's Compensation

SPECIFICATIONS AREAS:

1. General: Description, Submittals, Product Delivery, Storage, Job Conditions, Alternatives




2. Products: Materials, Mixes, Fabrication and manufacturer




3. Execution:


Inspection


Preparatoion


Installation/application/performance


field quality control


adjust and clean


schedules

Which of the following documents is NOT part of the project manual bid package?

-Addenda


-Drawings


-Scope of services


-Specifications


-Advertisement to Bid

Strict Liability

Liability without Fault

Which one of the following elements is typical included in the advertisement for bid?

Basis on which the bids will be judged




Not:


-Maximum Bid Estimate range


-Survey of the property


-Starting day of the construction project



Which of the following is NOT a reason for rejecting a bid?

-The bid is received and stamped two minutes after the advertised due time and day


-Bonding requirements are not met


-The bid form included in the bidding documents is altered


-a clerical mistake

The arbitration process is/isn't open to the public

Is NOT.

Scope of Services Include:

-Description of work


-Fee and products


-breakdown of work items into phases with corresponding fees for each phase.


-meetings and deadlines

The purpose of setting projects charts is to

-maintain schedules


-monitor production activity


-make prudent decisions related to the scheduling of personnel


-

The chart most commonly used for the typical projects in landscape architectural office is

BAR CHART

Which of the following is not a part part of the contract between the contractor and owner?

Plans and specification


Scope of Services


Change Orders


Addendas

As a representative of the client you are obligated to conduct periodic inspections of a construction project. You observe a sidewalk is being placed in the wrong location- the construction supervisor is not on the site. It is your responsibility to

advise the owner of the problem and inform the supervisor when he returns.




do NOT require stop work (not LA responsibility)

You have just signed a contract with a homeowner for the design of her courtyard. one part of the contract involves "consideration". consideration maens

you will work with the client in accordance with the terms of the contract

Certificate of payment should be signed by the LA

True

Field Observation Reports

Provide a record of the construction activity

Certification of substantial completion leads to

the release of bonds

The certificate of substantial completion is completed by

The landscape architect and the contractor

with the approval of the substantial completion form, the contractor is

released from various bonds

In order to join ASLA, you must

Be involved in the public, private or academic practice of landscape architecture (don't have to have graduated from a school bc you can be in ASLA while still in school)



Which statement best describes Scope of Service

It is used to solicit proposals from consultants

The scope of services sets the stage for

Calculating the project budget


Determining production hour needs




(not reducing general overhead and administration costs)

Scope of Services

Provides a detailed description of each task

RFP

is initiated by the client

Work Plan

The basic document for a strong project management system

Sequencing

RFP


Qualifications


Scope of Services


Contract


Detailed Budget


Contract

Joint Venture

is formed to create from a legal standpoint, a single firm to do the work

the purpose of setting project charts is to

maintain schedules


monitor production activity


make prudent decisions related to the scheduling of personnel.



THE SCOPE OF SERVICS SETS THE STAGE FOR CONSULTING FIRMS TO

determine personnel needs

landscape architects may practice under

Title and practice acts

Project manual includes

1. General Provisions (front end)- legal aspects


2. Technical Provisions ("specs")- technical aspects

TYPES OF SPECIFICATIONS

descriptive


(Most liability to LA)


-Work to be done


-methods to use


-products to use




performance spec


(most liability to contractor)


-process is up to the contractor




reference


-refers to standard




proprietary (closed)


-specific manufacturer number etc.


-not allowed on public project since it limits bidders


-can be done if there is an "allowance" which sets sum of money aside to remove those portions of work from the bid set