• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/85

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

85 Cards in this Set

  • Front
  • Back

Which decision mode is very fast and majority rules?

voting

A ________ _____________ team is composed of individuals with different objectives but come together to complete a project.

cross functional

What are the 2 obstacles of a team?

1) must solve complex problems together


2) project teams are temporary

Team values and meeting behaviours are two categories of ground ______.

rules

True or False



Adjourning is the development stage where leaders review the project.

True

Bob is being isolating and hard to approach. Which source of conflict is being experienced?

aloof

The common problems of a team are as follows:



- determining goals


- making trade offs between cost, schedule and scope


- designing a product


- setting _____________

milestones

Who created the 5 stages of development?

Bruce Tuckman

Team _________ creates a sense of commitment which are developed by goals.

identity

True or False



Problem analysis improves quality but reduces consistency.

False



improves both

Mental noise, speaking level and knowledge level are all obstacles in regards to __________ skills.

listening

In what stage of development do leaders foster trust?

storming

What are the 4 decision modes?

voting


consensus


delegate


autocratic

________ is a source of conflict where a member yells and loses their temper.

hostile

True or False



Mourning is the development stage where obstacles are removed.

False



no mourning stage, only mourning studying T.T

What are the 3 types of conflict?

relationship


task


process

Controlling _______ and having constant _______________ are 2 of 5 success factors in project management.

controlling scope


having constant communication

Becky pitches an idea her partner Linda had for the upcoming annual report, however Becky takes all the credit and speaks to Linda with a sarcastic, demeaning tone when confronted. What 2 sources of conflict is Becky preforming?

unappreciative


abrasive

What does CPM stand for?

Critical Path Method

In what stage of development is structure provided?

forming

Project management was first recognized as a real profession in the 20th century __________ but can be dated back to the actions of __________.

military


farming

Project Managers require what 3 skills?

business management skills


techinical skills


project management skills

90% of your time is spend is the __________ phase of a project life cycle.

execute

True or False



Representatives of external constants are government agencies that are against the project.

False



aren’t in support or against the project

In what phase of a project life cycle do you review failures?

close out

Purpose statement and scope statement are both in the SOW. What does SOW stand for?

Statement of Work

A ___________ document should include the statement of support.

project charter

We use the EACI sequence to code the responsibility matrix:



E___________ responsibility


A__________ authority


must be C_________


I__________ after the decision is made

Execution responsibility


Approval authority


must be Consulted


Informed after the decision is made

What is scope creep?

added tasks that can push back the schedule

When identifying risks, a risk profile is made of _______ experiences.

past

Which document is used to prevent breakdowns in communication?

communication plan

True or False



Risks can be retired.

True

What is the equation for Crash Cost?

(Reduced Cost – Initial Cost) / (Initial Duration – Reduced Duration) = Crash Cost

What are known unknowns?

funds for project’s identified risks

Unknown unknowns are funds set aside by upper management for _________ to predict risks.

impossible

True or False



Adding people to the project will always reduce the time needed and be more productive.

False



can cause conflicts

A ____________ appears as a diamond on the gantt chart.

milestone

What are the 4 sources of cost estimates?

labour


equipment


materials


fixed priced bids

___________ _____________ estimating is building the cost and schedule estimates by starting from work packages.

bottom line

True or Fasle



A negative float is impossible to meet.

True

Paper, ink and plates are all included in the _____________ estimates.

material

What does ROM stand for?

Rough Order of Magitude

If a costumer doesn't want to budge on quality, we can suggest cheaper rate for more ______.

time

Who should do the estimating and why?

The estimator because they are linked to the procurement department (suppliers).

Which estimating technique requires the most amount of effort but is the most accurate?

Bottom Up estimating

A bid is an offer from a _________ .

vendor

True or False



It is most productive to have continuous use of the fewest resources possible.

False

Don’t negotiate the estimate, negotiate ____________ .

equilibrium

Which level of estimating accuracy is good for deciding to take or leave a project?

Ballpark estimates

True or False



The 3 common restraints are time, money and quality.

False



time, money, resources

Which estimating technique is methodical and based on historical data?

Parametric estimating

Phased estimating requires ________ and ____________ commitments one project phase at a time

cost and schedule

Using internal and external experts are both methods to improve ____________ .

productivity

What does SPI stand for?

Schedule Performance Index

True or False



The customer has the right to refuse a job if quality expectations aren't met.

True

It is important to have a ______ door policy for individual status meetings.

open

Vendors are often pre________ for knowledge work.

prepaid

Which level of authority uses crash tables?

Project

_________________ estimating is also known as top down estimating.

Apportioning

True or False



A milestone is something your project team does.

False



It is a thing that happens

The goal of rearranging task assignments is to reduce the length of the _________ ________ .

critical path

Who benefits more financially when walking overtime, a worker with a salary or a worker with an hourly wage?

hourly wage - paid time and a half

You are currently printing the signatures of a novel while the cover is still being designed, which is risky but decreases your schedule by a day. What is this step in the business case level are you implementing?

Fast-Tracking

Lowering the price of a job can win projects but it also lowers _______ .

profit

True or False



Changes at the lowest threshold typically affect the cost or schedule.

False

What is phased product delivery?

delivering the completed portions of the job while still working on the others

What are the 4 communication needs of team members?

responsibility, coordination, status, authorization

Blueprints and a detailed plan are both examples of _________ documents.

control

A second threshold change effects what 3 things?

cost, schedule, functionality

What does CPI stand for?

Cost Performance Index

The 0-50-100 rule is an alternate method than _____________ percentage completions.

subjective

True or False



There are benefits to re-estimating if the situation has not changed.

False

Schedules measure how much we have done not how ______ it was completed.

well

What does the 0 mean in the 0-50-100 rule?

task not started

A change board monitors the _________ threshold changes.

second

Who introduces themselves first in a kick off meeting?

the customer

True or False



A SPI greater than 1 means it is behind schedule.

False

Cost and schedule baselines represent the original project plan as approved by the _______________ .

stakeholders

What does EVR stand for?

Earned Value Reporting

True or False



It is always a good thing to have a project be a head of schedule and under budget.

False



could cause storage issues


means you didnt estimate correctly

CPI < 1.0 mean the project is ____ budget.

over

Don't count a job as finished until it is ________, not shipped.

paid

What represents preset variances that signal the severity of the problem?

escalation threshold

The members of a change board include:



project team rep


customer rep


function management rep


related _________ rep

products

At what time of the planning phase should you start balancing tradeoffs in the equilibrium?

should wait until the end