Standard vertical Dowel spacing in CHB |
400mm |
|
CHB layers required prior to horizontal dowel installation |
3 layers |
|
Meters of allowance/spacing required prior to stiffiner column |
3m |
|
Layer of CHB required prior to lintel beam construction |
13 layers |
|
Standard size of lintel beam and stiffener column |
150 x 400 mm |
|
Standard tickness of smooth plaster |
2cm |
|
2 preparation done prior to structural slab topping |
Removal of concrete laitances Provision of wire mesh |
|
Class A concrete mixture ratio |
1 cement : 2 sand : 4 gravel |
|
3 preparation done before tile installation |
Clean the area Begin Layout Putting adhessive (5mm thick) |
|
Which comes first wall or floor tiles installation |
Wall, to avoid cracks or damage to the tiles on floor |
|
Gypsum board ceiling accessories |
Hanger rod Carrying channel Double furing channel W-clip Gypsum board Black screw (1") |
|
5 application done before painting gypsum board |
Mesh tape application Boral application Sanding Primer application Top/final coat |