• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/100

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

100 Cards in this Set

  • Front
  • Back

Facilitation Technique

Brainstorm


Problem Solve


Conflict resolution

Project Management Information System

Tool to direct and manage project work



Part of EEF: Hardware, software, databases, web interfacess, work authorization system.



How do you communicate information?
IM, phone, webex, etc.

Work Performance Data

Raw data from observations and measurements - lowest level of detail that gets passed on to monitor/control phase.



Does not provide PM with % complete



Ex: KPI report, actual cost, actual duration, performance measures.

Flow of Metrics:
WPD (raw data) > WPI (lead creates) > WPR (PM creates)

Rough Order of Magnetude

Cost estimate during project charter



Project is similar to past project:


-25% to +75%



Project is unique:


-50% to +50%

Constraint

Qualitative/quantitative (costs with proof)



Scope, time, cost, risk, resource, quality

Assumption

Elements of risk without proof (known-unknown)


ex: market changes

Stakeholder register

A list of all internal/external stakeholders



Started in the project charter

Project Management Plan

Project phases



Processes required for each phase



Process improvement, milestone list, resource calendar, scope/time/cost/quality baselines, and risk register

Enterprise Environmental Factors

Internal and external factors that affect a project, used as an input for most planning processes



RISC:


Resources - people, equipment


Infrastructure - facilities, IT, processes


Standards - regulations, code of conduct


Culture - business/organization culture

Work Performance Information

Actual of what is completed (% complete) and forecast report of estimate to completion



Team lead provides WPI to PM



Contains status, forecast, progress (ex: 50% complete, not "server installed")

Analytical Techniques

Failure Mode Effect Analysis (FMEA)


Fault Tree Analysis (FTA)


Trend Analysis


Variance Analysis


Scheduling Tools


Estimating Tools


Methodology

Change Control Board

Decision making body to approve or deny change requests.



PM is part of and in charge of CCB

Administrative Closure uses expert judgment to perform...

CALA:


Collect all records


Audit success or failure


Lessons Learned


Archive



- Customers are not present during closure


- Customer should accept w/o comments. If comments are made dont close

Explain integration management

Integration of the subsidary plans (scope, time, cost, etc.).



Setting up guidelines

Statement Of Work

High level details of project and business goal



Does not contain budget, only ROM

Cost Estimate Accuracy
When more details are known

-5% to +10%

Explain the monitor and control process

Monitor: Process of measuring actual against the plan/baseline



Control: Take corrective/preventative actions to control project performance

The Steps to close a phase or project are...

Administrative closure: formally closing the project of phase.



Done even if the project/phase is terminated.



Must get final approval from customer (external) and sponsor (internal) without comments.



CALA: Collect, audit, lessons, archive

Phase Gates / Kill Points

When the project is divided into phases, a phase gate sits between each phase for the sponsor/manager to determine whether the project should move forward or be terminated.

Scope Management Plan

How scope is defined, developed, monitored, controlled, and approved.



Process to manage change to scope



Process for formal acceptance of deliverables

Requirements Management Plan

How requirements will be analyzed, documented, and managed.



How activities are planned, tracked, and reported



Created during initiate scope process

Facilitated Workshops

1. Cross functional participation (meeting of all stakeholders)


2. Voice of Customer (VOC)


3. Joint Application Development (JAD)


4. Quality Function Deployment (QFD)

Group Creativity Techniques

Brainstorming


Mind Mapping


Affinity diagram (grouped ideas)


Nominal group voting technique

Group Decision making techniques

DELPHI technique:


1. develop questionaire


2. consult experts


3. maintain annonymity


4. Unanimity



Used in time estimates and scope planning

Prototype Techniques

Working model


Proof of concept (POC)


Voice of cusomter (VOC)


Cross functional participation

Requirements Documentation

Project Management plan (high level) WITH a detail description of scope



Created during plan scope process

Requirement Traceability Matrix

table providing traceability to business needs, scope, deliverables, etc. (ex: like accounting for every piece of an assembled plane)



Created during plan scope process

Product Analysis

product breakdown structure of tangible deliverables

Alternative Generation

Different approaches to achieve the same desired results

Project Scope Statement

Describes what will be delivered and how, much more detailed than SOW. Created during plan scope by the customer.



ABCDE-AC


Assumptions, Boundaries (scope), Constratints, Deliverables, Exclusions (out of scope), Acceptance Criteria

Decomposition Technique

Dividing the deliverables into the lowest definable level (work packages = WPD) so cost and time can be better estimated. Used for execute scope (creating the WBS)



Divided into 8 or 80 hours work packages

Work Breakdown Structure

Hierarhcy of all of the projects deliverables


Man-hour based, not time (calendar) based


Code of accounts


Created during execute scope phase


Developed by team, not PM


Prevents scope creep


Uses decomposition technique to divide deliverables into the work packages


Code of Accounts

Unique number assigned to each deliverable within the work breakdown structure

Work Authorization System

Used to authorize execution of work packages, thus controlling scope within the work breakdown structure

Scope Baseline

Approved project scope statement


Approved work breakdown structure


Approved work breakdown structure dictionary



Created during execute scope phase, in the project management plan

Work Breakdown Structure Dictionary

Time based document created after WBS:


work packages


start/end date


man hours


order of magnetude


staff assignments


quality requirements

Explain Control Scope

Weekly meeting that assures changes go through perform integrated change control (PICC)

Variance Analysis

Comparing planned vs. actual (impact of change in scope/cost)



Find the cause of variance and take corrective action if needed



Used during Control Scope/Cost process


What should be updated if the Work Performance Information is positive during the Control processes
Project document updates (stakeholder registry, issue log)

Organizational Process Assets updates (lessons learned)

What should be updated if the Work Performance Information is negative during the control processes

Change requests (to address variances)
Project management plan updates (STCRRQ)
Project document updates (stakeholders/issue log)
Organizational process assets updates (lessons learned, causes of variance, action taken)

The validate scope process is when...

Customer accepts the delierables


Customer pays for the deliverables


Happens after User Acceptance Testing



*Is completed even for terminated projects

Verified/Accepted Deliverables are...

Completed verified deliverables from UAT in the Control Quality Process

Inspection

Verifying the results match the acceptance criteria which is performed by the external customer (as opposed to audits by the internal sponsor)

Scope Validation

Performed after UAT is completed



Process of inspecting the results of the control quality process



Deliverable > UAT > Inspection > Accept/reject

Schedule Management Plan

Created during Initiate Time process



Describes the activites for developing and managing the schedule

Rolling Wave Planning

Progressive planning which elaborates activities as the project progresses

Activity List

A breakdown of the WBS (but not part of WBS) that lists all of the schedule activites that are required to complete the project.



Has activity identifier, scope, and details of what needs to be done.



Output of Plan Time process

Activity Attributes

Individuals responsible for each activity

Lowest level of activity list is...

The activities within work packages

Lowest level of the WBS is...

work packages

Precedence diagramming method

Used in the Sequence Activities plan time process.



Uses activity on node (AON) to draw network diagram:


Start to Start (SS) - activites begin at same time


Start to Finish (SF) - start one to end another


Finish to Start (FS) - end one to start another


Finish to finish (FF) - both finish at the same time

Dependency Determination

Used in sequence activities in the plan time management process.



Mandatory Dependency: Hard stop, must wait



Discretionary Dependency: Soft stop, advisable



External Dependency: government regulations

Lags vs. Leads

Lags: delaying the start of activity after end of another (ex: +1)



Leads: starting activity before the end of another (ex: -1). Fast tracking/work in parallell, schedule compression, schedule acceleration

Graphical Evaluation Review Technique (GERT)

Uses network diagram in the loop



For testing activities that need to be repeated



Two or more network diagrams connected without disturbing each other

Project Schedule Network Diagrams

Diagrammatic display of scheduled activites (PDM/Network Diagram)

Bottom-Up Estimating

Completed by the team (not PM)



If the resource estimation for a scheduled activity cannot be done, the activity must be divided into further smaller activities.



Activities resource estimates are then aggregated

Activity Resource Requirements

Type and number of resources required for each activity of a work package which is then totaled to determine resources for each work package.



Created in the Plan Time (estimate activity) process



Can be done in parallel with activity duration estimates

Analogous Estimating

Top-down activity duration/cost estimates by PM based on previous projects:



Faster, costs less, NOT accurate

Paramatric Estimating

Bottom-up activity duration/cost estimates by team based on units (installations/hour)



Activity duration = quantity of work * productivity rate



More expensive and takes longer than analogous, still not accurate due to skills varying

Three Point Estimate

Activity duration/cost estimates performed by team


Most accurate since risk is considered


Pessimistic (P), Optimistic (O), Most-Likely (M)



Beta (PERT) = (P + 4M + O) / 6


*Used for large volumes



Triangular = (P + M + O) / 3

Program Evaluation and Review Technique

PERT aka three point esimate



(P + 4M + O) / 6

Reserve Analysis

Time/cost buffer added on top of three point estimate.



Time/cost estimate contingency reserve performed by team for known-unknown (assumptions) regardless of the estimating technique used.

Activity Duration Estimates

Quantitative estimates of time required to complete activities determined in the plan time process.



Includes range of possible results (2 weeks +/- 2 days with a 15% chance of exceeding 3 weeks)



Can be completed in parallel with resource estimate

Management Reserve

Added on top of the three point estimate AND contingency reserve for "unknown-unknown" risks.



PM does not have access to this money.



Added during budgetting, not estimating

Resource Calendar

A calendar that reflects the working hours, vacations, holidays, etc. of all resources required to complete the work packages activities

Critical Path Method

Calculates the early start/finish and late start/finish for all activities on a network diagram using forward and backward pass technique on diagram.



Total float and Free float are calculated



Critical path has zero slack and float

Total Float

Applies to all activities in a path - the amount of time an activity can be delayed without delaying the project (cannot be longer than the critical path).



TF = ES - LS or TF = EF - LF

Free Float

Applies to one activity in a path - the amount of time an activity can be delayed without delaying the early start of the next activity.



Is zero unless there is a lag or it is the last activity in a path.

Resource Optimization Technique

Resource leveling - borrowing non-critical path team resources to the critical path team (must have the skills needed)



Resource smoothing - adjusting the activites without changing scope to ensure completion time

Schedule Compression Technique

Performed on the critical path to shorten the project schedule without changing the scope by using Crashing or Fast Tracking.

Resource Crashing

Schedule Compression technique



Adding more resources to critical path: shortens time but increases cost

Fast Tracking (lead technique)

Schedule compression technique



Adding lead to activites to work on them in parallel: reduces time and reduces quality (increases rework).



Can only be performed if the dependencies are discretionary and not mandatory.

Modeling Technique (What-if-scenarios / Monte-Carlo Analysis)

Used to assess feasability of schedule under adverse conditions so that risk mitigation and contingency reserve can be planned during schedule development.



Calculating different project durations based on different activity scenario's

Critical Chain Method

Duration buffers added to network diagrams (EF of 12 becomes 10+2).



Helps to modify the schedule to account for limited resources.

Project Schedule Baseline

Output from developing schedule - resource details like duration and length of commitment



- Milestone schedule baseline (senior management)


- Hammock - Summary of work packages in bar/gannt charts (middle management)


- Detailed activity bar/gannt charts (lower mgmt)

Resource crashing vs. Optimization

Crashing = adding resources



Optimization = moving resources

Performance Reviews
Used to control the schedule/cost through earned value analysis, variance analysis, and trend analysis.

Comparing planned vs. actual

Cost of Quality

Conformance + nonconformance = cost of quality



Conformance Cost = preventing failure


Nonconformance cost = rework from failure

Activity Cost Estimates

Likely costs of resources required



Definitive activity cost estimates = -5% to 10% accurate

Cost Aggregation

Cost estimates of work packages calculated by aggregating the costs of the activities it contains

Funding Limit Reconciliation

Rescheduling work = funding limits - planned expenditures

Budget/Cost Baseline (budget at completion)
Basis to measure, monitor and control cost performance (Excludes management reserve)

Baseline is an S-Curve

-10% to 10% accurate

Cost Estimate Accuracies

Rough order of magnetude = -25% to +75%



Cost Estimate = -5% to +10%



Cost Budget/Baseline = -10% to 10%

Earned Value Management technique

Helps to assess variance from baseline



Consists of:


- Planned value vs. earned value


- Actual cost


- Schedule variance


- Status Report (schedule variance / cost variance)


- Progress Report (CPI / SPI)`

Schedule Performance Index

Actual completion vs. Planned completion:



SPI = Earned value / Planned value

Cost Performance Index

Actual cost vs. budgetted cost (for every dollar spent, what was earned)



CPI = Earned value / Actual Cost

Cost Variance

Cost Variance = Earned value - Actual cost

Schedule Variance

Schedule variance = earned value - planned value

Forecasting Technique

Estimate at completion - are we on budget?



Estimate to completion - what is needed to finish?



To Complete Performance Index - cost performance on remaining work

Trend Analysis

Used in performance reviews to trend if the planned vs. actual is improving or deteriorating

Earned Value Analysis

Cost Variance



Cost Performance Index



Schedule Variance



Schedule Performance Index

To Completion Performance Index

Calculated projection of cost performance on remaining work



Based on Budget at Completion:


(BAC - EV) / (BAC - AC)



Based on Estimated at Completion:


(BAC - EV) / (EAC - AC)

Net Present Value

NPV = total benefits - cost



Always pick the highest NPV, despite timeframe

Expected Present Value

Net Present Value but also assumes risk

Present Value

Determining the value of resources N years from now with R as an interest rate:



PV = future value / (1 + R)^n

Sunk Cost

Do not consider the money already spent in order to decide whether to continue with a troubled project

Internal Rate of Return

The interest rate at which the project revenue and project outflows are equal.



Always select the project with the highest IRR

Return on Investment

ROI = total costs - accrued value

Direct Cost vs. Indirect cost

Direct cost can be measured and applied (ex: travel cost, team wages, supplies, etc.)



Indirect costs are administrative expenses not project specific (ex: rent for building, lighting, etc.)