• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/63

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

63 Cards in this Set

  • Front
  • Back

What is a project?

A unique transient endeavour undertaken to achieve planned objectives

The 5 characteristics of projects

1. Unique endeavour


2. Specific defined objectives


3. Defined time/cost/quality


4. Cross team functional working


5. Uncertainty and risk

What is a project lifecycle?

The inter-related phase of a project which provides structure for governing the work

Project Life Cycle

Concept


Definition


Development


Handover & Closure


Extended: as above plus Operation & Benefits Realisation


Product: as above plus Termination

What is change control?

The process through which all requests to change the baseline scope of a project are captured evaluated and then approved, rejected or deferred

What is change control?

The process through which all requests to change the baseline scope of a project are captured evaluated and then approved, rejected or deferred

What is the change control process?

Request


Review


Assess


Decide


Implement

What is the requirement management process?

Gather


Analyse


Justify


Baseline

Formulae for:


EV


SV


CV

EV=BAC/%age complete


SV=EV/PV


CV=EV/AC

The formulae for


SPI


CPI

SPI = EV/PV


CPI = EV/AC

Calculate outturn of cost

OOC=AC/%age complete


Or


OOC=BAC x AC/EV

Calculate outturn of time

OOT=Duration x PV/EV

What are the COST and SCHEDULE calculations in EVM?

Steph Eats Pears


SPI=EV/PV SV=EV-PV


Cassie Eats Apples


CPI=EV/AC CV=EV-AC

Types of project reporrs

Routine


Exception


Request


Special

What is project reporting?

The collection and dissemination of project information, which requires and understanding of SH needs. Reporting requirements are planned in the definition stage of the PLC

What is the purpose of the PMP?

To pull all plans and information together in one central set of document in the PMP

What should be in the PMP?

Baseline for project to allow deviations from the plan to be analysed. Content includes:


Who / What / When / Where / How / £


Includes all other plans eg benefits, change, comms, risk etc

What are the 4 types of contractual relationships?

1. Distanced - little or no contact / exchange. Traditional buyer/seller little or no risk


2. Turnkey - supplier provides compete package, works with customer. Little risk.


3. Preferred - buyer/seller good history, managed thru key account manager, build/ strengthen relnship


4. Partnering/Alliance/ JV - work together mutual trust shared objectives. Appear as one company. Large/complex projects

Types of supplier reimbursement

1. Firm price


2. Fixed price - tariff for scope


3. Cost plus - cost with profit


4. Per unit quantity - hours/days/kgs


5. Targets cost (TCIF) - share pain and gain w supplier


6. Max price - caps cost plus at a firm price

What are the content of a procurement strategy?

Purchase requirement - make rent of buy?


Supplier arrangement (single/multiple)


Supplier relationship


Selection (tender) procedures


Form of contract


Method of payment/pricing

What are the steps in supplier selection process?

1. Research


2. PQQ


3. Tender


4. Award


5. Manage


6. Close

What are the 5 steps of the risk mgmt process?

Initiate


Identify


Assess


Plan responses


Implement responses

What are 5 methods of risk identification?

Brainstorm


Assumption analysis


Constraint analysis


Delphi technique


What if scenario planning

What are the risk responses?

Avoid - design out


Reduce - mitigate


Transfer - to another party


Accept - deal with it

What are the opportunity responses?

Exploit - design in


Enhance - increase prob


Share - with another party


Accept - deal with when it happens

What are 5 benefits of risk management?

Better informed plans/schedules/budgets


Leads to suitable contract


Assess contingencies better


Identifies responsibility to best owner


Common understanding

What is the difference between a risk and an issue?

An issue has or will happen and is escalated to the Sponsor for action

What are the advantages of risk /issue escalation?

Allows sponsor to consider mitigation


Essential as otherwise issue will impact on project


Increases visibility of project status, aids good project governance

What are the disadvantages of risk / issue escalation?

Can lead to adverse reaction through transparency


May lead to increased cost and time


Erode PM authority / decision

What are the advantages of a functional organisation?

+ strong specialist skills


+ efficient use of resource


+ clear comms


+ simple reporting


+ central control

What are the advantages of a functional organisation?

+ strong specialist skills


+ efficient use of resource


+ clear comms


+ simple reporting


+ central control

What are the disadvantages of a functional organisation?

- concentration on specialists


- poor integration


- slow to change / adapt


- poor customer focus


- narrow view

What are the advantages of a matrix organisation?

+ balance between projects and BAU


+ integrates projects in functions


+ visible priorities


+ flexible use of resources


+ develops and retains specialist knowledge

What are the disadvantages of matrix organisation?

- divides loyalties


- authority difficult


- complex structure / reporting


- balance difficult


- increased stress / conflict

What is the benefits management process?

1. Define: Ben Mgmt plan


2. Identify: and structure Ben


3. Plan: Ben realisation


4: Track: implement change


5: Realise: the benefits

Identify sources of conflict in the project lifecycle

Concept: requirements / options / objectives


Definition: schedule/ resourcing / priorities


Development: contracts/payments / legal challenge / issues and changes


Handover & Closure: acceptance / payment


Benefits Realisation: meet objectives / expectations / review findings

What is a benefit?

A measurable and quantifiable improvement from completion of deliverables that are perceived as positive by stakeholders

Explain how the PESTLE tool assessed a project context

Political


Economic


Sociological


Technological


Legal


Environmental

List 5 responsibilities / activities of the project SPONSOR

Monitor project context


Delivery of project benefits


Approval of the BC and changes


Advocate for the project


Governance of the project done correctly

What are the key roles and responsibilities of the project manager?

Manages the PT


Produces BC on behalf of Sponsor with input from SHs


Owns and produces the PMP


To deliver the projects outputs to cost time and quality


Manages change in the project

Explain the benefits of conducting project reviews

Improves processes and procedures


Improves estimating and resourcing


Increases accuracy in reporting


Increases confidence in project delivery and plans


Better risk identification and management

Explain 5 factors that define an effective team

Common focus or goal


Commitment


Supporting each other


Shared motivation (values)


Collaboration

What is the purpose of the business case?

To document the justification for doing the proposed project considering the cost/benefit and risk to achieve the objective.


The business case defines


Why the project is reqd


What the change is


How it fits with strategy


How it contributes to the orgn goals

Define Quality Management

A discipline for ensuring the output and benefits (and processes by which they are delivered) meet SH requirements and are fit for purpose

What are the key benefits of quality management?

Confidence - poor quality damages SH confidence. Culture of quality breeds pride and confidence => right first time


Cost - cost ratio of correcting mistakes means applying quality reduces cost of failures especially by identifying quality issues early on in the project life cycle


Cost of correction is exponential:


Concept - 1


Definition - n


Implementation - nsquared


Handover - ncubed

What are the advantages of the project organisation?

+ Strong commitment


+ integration


+ clear mgmt / delegation


+ easy comms


+ precise project budgets

What are the disadvantages of project organisation?

- short termism no job security


- inefficient use of resources


- duplication of resources


- dilutes specialist expertise


- poor knowledge retention

What are the types and objective of resource management?

2 categories: Consumable and Re-usable


Obj: resources are made available to the project at the correct time

What is resource scheduling and three methods?

Resource scheduling are techniques used to calculate what resources required and when


Methods:


Display schedule (eg Gantt, Network)


Histogram


S Curve (cumulative cost/ resources)

What is the purpose of resource management and what techniques are used?

Resource management is used to align resource requirement with the resource availability by making adjustments to the schedule


Techniques:


Smoothing - adjust same end date


Levelling- changes end date due to resource constraint


Done by splitting or stretching tasks

Describe three investment appraisal techniques

Payback = time to recoup investment / cost


NPV = £ net profit or loss in today’s money


IRR = %age the discount factor which results in NPV = 0

Describe 5 benefits that a project office provides

Routine reporting frees up the PM


Consistency of approach across projects and programmes


Learning from other projects and progs


Continuous improvement


Central standards processes and information for the business

Describe 5 stages of the information management provess

Collection


Storage


Dissemination


Archiving


Destruction

What are the benefits of an information management system?

Comes with variety and volume of project information


Enables effective mgmt of info


Mapping of info to SHs ensures get right info at right time


Allows categorisation


Allows confidentiality and security


IMS enables planning and coordination of info

Describe 5 types of legislation and how a project should manage them

H&S- risk assessments, working practices, emergencies


FoI- respond to FoI requests


Data Protection- personal info, protect store and destroy


Employment law- equality and conditions


Environmental- flora and fauna, pollution, noise/light/dust

What is float?

The amount that activities can be moved without affecting the overall schedule / finish time

What is free float?

The amount of time an activity can be delayed without affecting the next activity.

What is a critical path?

The longest path through the network, it determines the the duration of the project and passes through activities that have no float

What is total float?

The difference between the early and late times for each activity. The amount of time a series of activities on the same path can be delayed before the project is delayed.

Explain the term leadership

Leadership is the ability to establish vision and direction, to influence and align other to a common purpose, and to empower /inspire people to achieve success

State 5 leadership qualities

Vision


Empowerment


Respect


Trust


Communicate/ Articulate

What are the four stages of team development?

Forming - testing, guarded, leader dependent


Storming - infighting, establish, power struggles, need to be focused


Norming - R&R clear and accepted. Consensus, delegation, socialise


Performing - shared vision and focus. Independence, autonomy.

Explain the importance of a robust procurement strategy

Legally compliant


Coherent with governance reqts


Affects risk


Affects relationship


Major component of PMP