C1064: For concrete with aggregates less then 3”, the thermometer must remain in the fresh concrete sample a minimum of 5 min or until the temp reading stabilizes. True or False |
False: 2-5 minutes |
|
C1064: The temperature measuring device must be accurate to within 0.1 Degrees.
True or False? |
False: 1 degree Fahrenheit |
|
C1064: The temperature measuring device shall have a capacity of measuring temperature of freshly mixed concrete throughout a range of? |
1 degree Fahrenheit/ 30-120 degrees Fahrenheit |
|
C1064: A composite sample is not needed if only the temperature test is being run.
True or False? |
True. |
|
C1064: The temperature of fresh concrete in a placement must be measured by inserting a thermometer into the top 6” of concrete.
True or False? |
False- Top 3” |
|
C1064: The temperature of the concrete is recorded to the nearest? |
1 Degree Fahrenheit |
|
C1064: ASTM C1064 states the container used to measure temperature of concrete must be large enough to provide at least 5” of concrete around the sensor.
True or False? |
False- 3” of concrete |
|
C1064: Calibrate the temperature measuring device at least________, or whenever there is a question of_________. |
Annually/Accuracy |
|
C1064: After the thermometer is placed in the concrete: A. Gently press concrete around the thermometer. B. Cool the surface of concrete with water. C. Tap the side of the container 10-15 times. D. All the above |
A. Gently press concrete around the thermometer. |
|
C1064: According to ASTM C1064, what is the one reason to take the temperature of concrete? |
To verify conformance. |
|
C1064: It is allowable to remove the temperature measuring devices from the freshly mixed concrete to read the temperature if you cannot see the reading. True or False? |
False- Do not remove the thermometer while reading the temp. |
|
C1064: The temperature of concrete may be measured in a wheelbarrow. True or False? |
True. |
|
C1064: The temperature of concrete may be measured in a wall form. True or False? |
True. |
|
C1064: What must be done to the sample container prior to sampling the concrete? |
Dampen the container with water. |
|
C1064: How long must the temperature measuring device remain in the freshly mixed concrete? |
2-5 minutes |
|
C1064: After the temperature of the concrete is read, what is then required? |
Report the temperature. |
|
C1064: A maximum temperature of freshly mixed concrete is specified in Test Method C1064. True or False? |
False |
|
C1064: The sample of concrete used for temperature determination must be rodded 25 times. True or False? |
False |
|
C172: The maximum allowable time between obtaining the first and last portions of the composite sample may not exceed 5 minutes. True or False? |
False- 15 minutes |
|
C172: Start molding specimens for strength tests within 30 minutes after fabricating the composite sample. True or False? |
False- 15 minutes |
|
C172: The composite concrete sample must be protected from sun, wind, contamination and rapid evaporation. True or False? |
True |
|
C172: If the concrete contains aggregate larger than those that are appropriate for a size of mold or equipment used, the sample should be wet-sieved before making the test. True or False? |
True |
|
C172: If the concrete contains aggregate larger than those that are appropriate for a size of mold or equipment used, the sample should be wet-sieved before making the test. True or False? |
True |
|
C172: The composite sample should not be remixed before beginning any tests. True or False? |
False |
|
C172: Sampling should normally be performed, as the concrete is discharged from the mixer. True or False? |
True |
|
C172: If the concrete contains aggregate larger than those that are appropriate for a size of mold or equipment used, the sample should be wet-sieved before making the test. True or False? |
True |
|
C172: The composite sample should not be remixed before beginning any tests. True or False? |
False |
|
C172: Sampling should normally be performed, as the concrete is discharged from the mixer. True or False? |
True |
|
C172: ASTM Method C172 includes sampling from stationary mixers, paving mixers, truck mixers, agitators, and non-agitating equipment. True or False? |
True |
|
C172: After sampling is completed, start the tests for slump and air content within: A. 2 1/2 min B. 10 min C. 15 min D. None of the above |
A. 2 1/2 min |
|
C172: If the concrete contains aggregate larger than those that are appropriate for a size of mold or equipment used, the sample should be wet-sieved before making the test. True or False? |
True |
|
C172: The composite sample should not be remixed before beginning any tests. True or False? |
False |
|
C172: Sampling should normally be performed, as the concrete is discharged from the mixer. True or False? |
True |
|
C172: ASTM Method C172 includes sampling from stationary mixers, paving mixers, truck mixers, agitators, and non-agitating equipment. True or False? |
True |
|
C172: After sampling is completed, start the tests for slump and air content within: A. 2 1/2 min B. 10 min C. 15 min D. None of the above |
A. 2 1/2 min |
|
C172: In any case, do not obtain samples until: A. All water and admixtures have been added to the concrete. B. 200 revolutions of the drum have been obtained. C. 1/2 of the water has been added. D. None of the above. |
A. All water and admixtures have been added to the concrete. |
|
C172: If the concrete contains aggregate larger than those that are appropriate for a size of mold or equipment used, the sample should be wet-sieved before making the test. True or False? |
True |
|
C172: The composite sample should not be remixed before beginning any tests. True or False? |
False |
|
C172: Sampling should normally be performed, as the concrete is discharged from the mixer. True or False? |
True |
|
C172: ASTM Method C172 includes sampling from stationary mixers, paving mixers, truck mixers, agitators, and non-agitating equipment. True or False? |
True |
|
C172: After sampling is completed, start the tests for slump and air content within: A. 2 1/2 min B. 10 min C. 15 min D. None of the above |
A. 2 1/2 min |
|
C172: In any case, do not obtain samples until: A. All water and admixtures have been added to the concrete. B. 200 revolutions of the drum have been obtained. C. 1/2 of the water has been added. D. None of the above. |
A. All water and admixtures have been added to the concrete. |
|
C172: No samples shall be taken before_______ or after________ of the batch has been discharged. A. 10% or after 90% B. 20% or after 90% C. 20% or after 80% D. None of the above |
A. 10% or after 90% |
|
C172: When strength tests are to be made, the minimum size of the composite sample shall be: A. 1/4 cubic foot B. 1 cubic foot C. Any convenient size D. 1 wheelbarrow |
B. 1 cubic foot |
|
C172: Sample the concrete from the chute of a truck mixer by: A. Raising the chute to stop the flow and scoop concrete from there into the slump cone and cylinder molds. B. Passing a receptacle completely through the discharge stream or by completely diverting the discharge into the sample container. C. Holding a shovel in the flow and direct half into a bucket. D. None of the above. |
B. Passing a receptacle completely through the discharge stream or by completely diverting the discharge into the sample container. |
|
C172: Sample the concrete from the chute of a truck mixer by: A. Raising the chute to stop the flow and scoop concrete from there into the slump cone and cylinder molds. B. Passing a receptacle completely through the discharge stream or by completely diverting the discharge into the sample container. C. Holding a shovel in the flow and direct half into a bucket. D. None of the above. |
B. Passing a receptacle completely through the discharge stream or by completely diverting the discharge into the sample container. |
|
C. Two or more regular |
C. Two or more regularly spaced intervals during discharge of the middle portion of the batch. |
|
C172: Sample the concrete from the chute of a truck mixer by: A. Raising the chute to stop the flow and scoop concrete from there into the slump cone and cylinder molds. B. Passing a receptacle completely through the discharge stream or by completely diverting the discharge into the sample container. C. Holding a shovel in the flow and direct half into a bucket. D. None of the above. |
B. Passing a receptacle completely through the discharge stream or by completely diverting the discharge into the sample container. |
|
C. Two or more regular |
C. Two or more regularly spaced intervals during discharge of the middle portion of the batch. |
|
C172: The elapsed time between obtaining the first and final portions of the composite sample, according to ASTM C172, shall not exceed: A. 10 min B. 20 min C. 30 min D. None of the above. |
D. None of the above. |
|
C172: When sampling from a stationary mixer, the batch must be sampled at_____ or more regularly spaced intervals. |
2 |
|
C172: When sampling from a stationary mixer, the batch must be sampled at_____ or more regularly spaced intervals. |
2 |
|
C172: When sampling from a paving mixer, obtain samples from at least_____ different portions of the pile and combine them into one composite sample for test purposes. |
5 |
|
C172: When sampling from a revolving drum mixer, sample the concrete by collecting_____ or more portions taken at regularly spaced intervals during discharge of the middle portion of the batch. |
2 |
|
C172: When concrete contains aggregate larger than that permitted for a particular test method, the sample of concrete must be_______ before making a test. |
Wet-sieved |
|
C172: Fresh concrete to be sampled at the job site should be sampled from? |
Two or more regularly spaced intervals during discharge of the middle portion of the batch. |