• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/20

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

20 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)
Total Float
LS - ES
or
LF - EF
Time Management
Cost Variance (CV)
EV - AC
Cost Management
Schedule Variance (SV)
EV - PV
Cost Management
Cost Performance Index (CPI) or Cumulative CPI (CPIc)
EV / AC
or
EVc / ACc
Cost Management
Schedule Performance Index (SPI)
EV / PV
Cost Management
Estimate at Completion (EAC) - 1
AC - Bottom-up ETC
Cost Management
This formula calculates the actual plus a new estimate for the remaining work. It is used when the original estimate was fundamentally flawed.
Estimate at Completion (EAC) - 2
BAC / CPIc
Cost Management
This formula is used if no variances from the BAC have occurred or you will continue at the same rate of spending.
Estimate at Completion (EAC) - 3
AC + (BAC - EV)
Cost Management
This formula calculates actual to date plus remaining budget. It is used when current variances are thought to be atypical of the future. It is essentially AC plus the remaining value of work to perform.
Estimate at Completion (EAC) - 4
AC + (BAC - EV) / CPIc x SPIc
Cost Management
This formula celculates actual to date plus the remaining budge modified by the performance. It is used when current variances are thought to be typical of the future. It assumes poor cost management performances and a need to hit a firm completion date.
To Complete Performance Index (TCPI)
(BAC - EV) / (BAC - AC)
Cost Management
Estimated to Complete (ETC)
EAC - AC
Cost Management
Variance at Completion (VAC)
BAC - EAC
Cost Management
Communication Channels
N (N-1) / 2
Communications Management
Planned Value
PV
Cost Management
As of today, what is the estimated value of the work planned to be done?
Earned Value
EV
Cost Management
As of today, what is the estimated value of the work actually accomplished?
Actual Cost (total cost)
AC
Cost Management
As of today, what is the actual cost incurred for the work accomplished?
Budget at Completion (the budget)
BAC
Cost Management
How mich did we BUDGET for the TOTAL project effort?
Estimate at Completion
EAC
Cost Management
What do we currently expect the TOTAL project to cost (at forecast)?
Estimate to Complete
ETC
Cost Management
From this point on, how much MORE do we expect it to cost to finish the project (a forecast)?
Variance at Completion
VAC
Cost Management
As of today, how much over or under budget do we expect top be at the end of the project?