Which of the following is NOT something the project planning board allows you to do?
a) Plan, check, and change dates b) Calculate costs c) Determine and distribute work d) Create capacity schedule e) Plan, schedule, and check resources |
d) Create capacity schedule
________________________________________________ You can compare capacity, but not create it |
|
Materials establish a link between the Project System and what three modules?
|
Sales and Distribution (SD), Materials Management (MM), and Production Planning and Control (PP)
|
|
Which of the following are settlement types? (Choose 2)
a) Direct Settlement b) Indirect Settlement c) Single-level Settlement d) Multi-level Settlement e) Manual Settlement |
a) Direct Settlement and d) Multi-level settlement
|