1. 1.1 You can use WBS elements to structure your projects at the individual level based on what three main aspects (but not limited to)?
|
1. Phases-based
2. Functions-based 3. Organizational-based |
|
2. 1.1 What are the nine important functions of work breakdown structures in the SAP system:
|
1. Planning and entering dates
2. Cost planning and account assignment of documents 3. Planning and invoicing revenues 4. Planning and monitoring payment flows 5. Hierarchical budget management 6. Material stock management 7. Various period-end closing tasks 8. Monitoring a project's progress 9. Aggregated data analysis |
|
3. 1.1 Access control lists describe which ____________, ___________, and __________ are supposed to have administrative, change, or display authorizations or even no authorization at all for a specific object.
|
1. User
2. User group 3. Organizational units |
|
4. 1.2 t/f You cannot reassign a WBS element that is based on a specific project definition to another project definition.
|
1. True
|
|
5. 1.2 During the creation process you must specify a unique identification for the project definition, which may consist of a maximum of __#__ charac¬ters.
|
1. 24
|
|
6. 1.2 You must assign your project to a _____________ at the project defini¬tion level.
|
1. Controlling area
|
|
7. 1.2 t/f The assignment to a company code can be changed for each individual WBS element.
|
1. True
|
|
8. 1.2 ____________ enable employees in different departments to use project structures on the basis of the type and usage of projects.
|
1. Coding Masks
|
|
9. 1.2 t/f You should consider using coding masks when you first implement SAP Project System and before you create the first project.
|
1. True
|
|
10. 1.3 A network consists of a ___________ and ___________.
|
1. Network Header
2. Activities |
|
11. 1.3 Activities can be linked to each other via ___________.
|
1. Relationships
|
|
12. 1.3 _________ enable you to further detail or complement activities.
|
1. Activity elements
|
|
13. When creating a network header, you must specify a __________, __________, and __________.
|
1. Network Profile
2. Network Type 3. Plant (used to identify the associated company code and controlling area). |
|
14. 1.3 In the context of networks, what are the four activity types defined by the ___________?
|
1. Internally processed activities
2. Externally processed activities 3. Services 4. Costs 5. Control Key |
|
15. Relationships allow you to define the sequence of activities. What are the four types of relationships?
|
1. FS Finish-start
2. SS Start-start 3. FF Finish-finish 4. SF Start-Finish |
|
16. 1.3 _________ element for planning and entering performances of capaci¬ties of your own company
|
1. Internal
|
|
17. 1.3 ________ element for planning and procuring external services.
|
1. External
|
|
18. 1.3 ________ element for planning and procuring external services using service specifications.
|
1. Service
|
|
19. 1.3 ________ element for planning and assigning additional primary costs to accounts.
|
1. Costs
|
|
20. 1.3 t/f In contrast to an activity, an activity element doesn’t contain any relationships and is therefore not relevant for time scheduling.
|
1. True
|
|
21. 1.4 _________ can be used to map events of particular importance, such as the completion of critical project stages.
|
1. Milestones
|
|
22. 1.7 You can use the __________ (Transaction CJ20N) to create, modify, and display project structures.
|
1. Project Builder
|
|
23. 1.7 The _______ _______ displays the hierarchical structure of the WBS as a graphic.
|
1. Hierarchy Graphic
|
|
24. 1.7 The _______ _______ provides a graphical display of the activities of one or several networks.
|
1. Network Graphic
|
|
25. 1.7 Under Display Activities, the network graphic can dis¬play what six characteristics?
|
1. IDs
2. Descriptions 3. Control keys 4. Duration 5. Planned dates 6. and Floats |
|
26. 1.7 The ____ ______ ______ enable you to create, modify, and display work breakdown structures and assigned networks.
|
1. Project Planning Board
|
|
27. 1.7 The ______ _______ is the graphical section of this overview displays requirement dates and, if needed, delivery and goods movement dates for assigned material components. You can navigate to the detail screen of a mate¬rial component by double-clicking on it.
|
1. Component Overview
|
|
28. 1.7 The ________ _______ is the graphical section displays planned costs and, if available, planned and actual revenues of WBS elements as a totals curve.
|
1. Cost Overview
|
|
29. 1.7 The ________ __________ compares the available capacity of work centers assigned to activities with the (total) capacity requirement for differ¬ent periods as a bar chart or histogram. You can display the work cen¬ters by double-clicking on them.
|
1. Capacity Overview
|
|
30. 1.7 The _________ _________ _________ is the graphical section of this overview displays the dates of plant main¬tenance orders that you have assigned as subnetworks to activities.
|
1. Plant Maintenance Overview
|
|
31. 2.1 When creating a project, you can enter a planned start and end date for the project in the _______ ________.
|
1. Project Definition.
|
|
32. 2.1 Dates for WBS elements can be scheduled in (1)_______ ________ in the WBS elements detail screen, in the (2)______ ______ _______, or via the special maintenance functions, either in a (3)_________ format or, in the Project Plan¬ning Board, in a (4)__________ format.
|
1. Project Builder
2. Project Planning Board 3. Tabular 4. Graphical |
|
33. 2.1 Using the ________ ________ function, you can shift the planned dates of indi¬vidual WBS elements, or of entire subtrees, or of your entire project.
|
1. Shift Dates
|
|
34. 2.1 If you work with WBS without assigned networks, the scheduled dates of WBS elements, that is, their earliest and latest start and end dates, are only relevant if you use ___________, the dates of which are derived from the WBS element dates.
|
1. Milestones
|
|
35. 2.1 Depending on the transaction you used to trigger the scheduling, you use (1)__________ _________, (2)_______ ______, or (3)______ ___________.
|
1. Network Scheduling
2. Overall Network Scheduling 3. WBS Scheduling |
|
36. 2.1 What is Network Scheduling?
|
1. Only one network is scheduled
|
|
37. 2.1 What is Overall Network Scheduling?
|
1. Several networks are scheduled at the same time (provided they are linked via relationships or subnetworks).
|
|
38. 2.1 What is WBS Scheduling? (2)
|
1. Select one or more WBS elements, or the entire project, and trigger the sched-uling process.
2. The system then selects only those activities for scheduling that are assigned to the selected WBS elements and calculates their dates. |
|
39. 2.1 t/f In SAP Project System, start and end dates for scheduling can be specified in the network header or the WBS elements to the day only. Scheduling types with a reference to the time of the day cannot be implemented in SAP Project System.
|
1. True
|
|
40. 2.1 What are the four Scheduling Types displayed at the network header level?
|
1. Forward
2. Backward 3. Current Date 4. Only Capacity Requirements |
|
2.1 The parameters for WBS scheduling include the Scheduling Method field with the following two options:
|
1. Network Determines Dates
2. WBSD Determines Dates |
|
42. 2.5 For projects, you can plan revenues on the _______ _______ level or, if you use the integration into SD, using ______ ________ linked to projects.
|
1. WBS elements
2. Sales documents |
|
43. 2.5 WBS elements for which you want to plan revenues must be identified as _______ _______.
|
1. Billing elements
|
|
44. 2.5 A billing plan always references a _____ _____ that you must store in the planning profile of the project.
|
1. Revenue element
|
|
45. 3.0 A budget can only be assigned to ____________ elements in SAP Projects.
|
1. WBS
|
|
46. 3.1 The management of budgets for individual projects is controlled by the _______ ________ in the Project Definition.
|
1. Budget Profile
|
|
47. 3.1 The ______ ________ costs can be copied to be used as the Original Budget.
|
1. Planned Total
|
|
48. 3.1 Instead of changing the original budget (Create Original Budget CJ30), use _____ ______ that allows for a distinction between budget supplements, budget returns, and budget transfers.
|
1. Budget Updates
|
|
49. 3.1 Each budget release is documented by a budget _____ _____, to which you can enter a descriptive document text before you save the release.
|
1. Line item
|