17 Cards in this Set
- Front
- Back
- 3rd side (hint)
AC |
Asset Cost |
|
|
ARO |
Annual rate of occurrence |
|
|
ALE |
Annual loss expectancy |
|
|
AV |
Asset value |
|
|
CPI |
Cost performance indicator |
|
|
EF |
Exposure factor |
|
|
EV |
Earned value |
|
|
PV |
Planned value |
|
|
SLE |
Single loss expectancy |
|
|
SPI |
Schedule performance indicator |
|
|
SV |
Schedule variance |
|
|
What's the formula for calculating risk? |
Threats X Vulnerability X Impact Level |
T X V X I |
|
Calculate single loss expectancy (SLE) |
AV X EF |
Involves exposure factor |
|
Calculate Annual loss expectancy (ALE) |
SLE X ARO |
Involves ARO |
|
Calculate Cost performance indicator (CPI) |
EV/AC |
Involves earned value |
|
Calculate Schedule performance indicator (SPI) |
EV/PV |
Involves earned value |
|
Calculate schedule variance (SV) |
EV - PV |
Involves planned value |