• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/17

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

17 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)

AC

Asset Cost

ARO

Annual rate of occurrence

ALE

Annual loss expectancy

AV

Asset value

CPI

Cost performance indicator

EF

Exposure factor

EV

Earned value

PV

Planned value

SLE

Single loss expectancy

SPI

Schedule performance indicator

SV

Schedule variance

What's the formula for calculating risk?

Threats X Vulnerability X Impact Level

T X V X I

Calculate single loss expectancy (SLE)

AV X EF

Involves exposure factor

Calculate Annual loss expectancy (ALE)

SLE X ARO

Involves ARO

Calculate Cost performance indicator (CPI)

EV/AC

Involves earned value

Calculate Schedule performance indicator (SPI)

EV/PV

Involves earned value

Calculate schedule variance (SV)

EV - PV

Involves planned value