• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/16

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

16 Cards in this Set

  • Front
  • Back
What is the response of the Containment Atmosphere Control System when a valid high charcoal temperature alarm is actuated? A. The affected unit fan stops, reducing air flow across the charcoal filters.B. When air stream temperature reaches 300 degrees, the affected unit fan stops.C. The outlet damper throttles air flow reducing the reaction rate in the charcoal bed to maintain temperature below 2000F.D. Automatic fire protection will initiate to cool the charcoal bed.
A
Which of the following subsystems of the Containment Hydrogen Control System is used to obtain periodic sampling of the containment atmosphere? A. Hydrogen MixingB. Hydrogen RecombinersC. Hydrogen PurgeD. Hydrogen Monitoring
D
Which of the following describes the purpose of the Containment Hydrogen Control System Hydrogen Purge Subsystem? A. Provides a means of lowering Containment pressure prior to personnel entry.B. Provides a means to lower Containment Hydrogen concentrations by atmosphere replacement.C. Provides a flowpath to the Containment Hydrogen Recombiners.D. Provides a means of assessing the amount of Zirc-Water reaction following a LOCA.
B
Which of the following describes the significant sources of hydrogen gas in containment following a LOCA? A. Radiolytic decomposition, Noble Gas, hydrogen dissolved in RCS.B. Zirconium-Water Reaction, Zinc based corrosion products, Dissolved hydrogen in the RCS.C. Radiolytic decomposition, Zirconium-Water reaction, and corrosion of metals and paints.D. Corrosion of paints and metals, Noble Gas radiolysis, Free hydrogen in RCS.
C
What is the motive force that causes air to flow through the Containment Hydrogen Control System Hydrogen Recombiners? A. Hydrogen Mixing FansB. Containment Cooling FansC. Natural convectionD. Control Rod Drive Mechanism fan
C
Which of the following will cause the sample lines to isolate in the Containment Hydrogen Control System Hydrogen Monitoring Subsystem? A. Containment Isolation Signal Phase B (CISB)B. Safety Injection SignalC. Containment Purge Isolation Signal (CPIS)D. Containment Isolation Signal Phase A (CISA)
D
The Hydrogen Monitoring System of the Containment Hydrogen Control System is designed to be operated __________________________. A. during modes 1, 2, 3 and 4; onlyB. during refueling outages onlyC. from the Main Control Board.D. automatically upon receipt of a Safety Injection Signal
C
Which of the following describes when sufficient electrical power will be available after a LOCA, to allow both Hydrogen Recombiners to be turned on? A. 36 hoursB. 24 hoursC. 8 hoursD. 16 hours
B
The Mini-Purge Subsystem is used to reduce the concentration of _____________ within the containment prior to and during personnel access or to ___________ internal pressure. A. hydrogen gas / increaseB. hydrogen gas / equalizeC. noble gases / increaseD. noble gases / equalize
D
Which combination of INOPERABLE monitors would prevent a CTMT Purge release?* * GT RE-22, Containment Purge Exhaust Monitor* GT RE-31, Containment Air Supply Monitor* GT RE-32, Containment Air Supply Monitor* GT RE-33, Containment Purge Exhaust Monitor A. GT RE-22 and GT RE-33B. GT RE-22 and GT RE-31C. GT RE-31 and GT RE-33D. GT RE-32 and GT RE-33
A
The unit is operating at 100% RTP. One of the two Required Channels for Containment Hydrogen Concentration Level Function of Post-Accident Monitoring (PAM) Instrumentation is declared inoperable at 0900 on 5/25.What are the required TS Actions for PAM Instrumentation? A. Initiate action to submit a PAM report within 14 days.B. Restore the channel to OPERABLE status within 7 days.C. Be in Mode 3 in 6 hours and Mode 4 in 12 hours.D. Restore the channel to OPERABLE status within 30 days.
D
Which signal will NOT cause a Containment Purge Isolation Signal (CPIS) to occur? A. Fuel Building Isolation SignalB. Manual from Main Control Board CPIS actuate buttonC. Containment Purge High-High RadiationD. Containment Isolation Signal Phase "A" (CISA)
A
The unit is operating at 100% RTP. - At 0900 on 6/1, one of the two Required Channels for Containment Hydrogen Concentration Level PAM instrument function is declared inoperable. - At 0400 on 6/15, one of the two Required Channels for Containment Radiation Level PAM instrument function is declared inoperable.If the Containment Hydrogen Concentration channel is restored to OPERABLE status at 0900 on 6/20, when must the required Containment Radiation Level channel be restored to OPERABLE without being required to submit a PAM report? Include any extensions that are permitted by Technical Specifications. A. 0900 on 7/1B. 0400 on 7/1C. 0400 on 7/15D. 0900on 7/20
C
The unit is operating at 100% RTP.* At 0400 on 5/1, one of the two Required Channels for Containment Hydrogen Concentration Level Function of Post-Accident Monitoring (PAM) Instrumentation is declared inoperable.* At 0900 on 5/1, the second Required Channel for Containment Hydrogen Concentration Level Function of PAM Instrumentation is declared inoperable.* At 0900 on 5/4, a unit shutdown is commenced because neither required channel is restored to OPERABLE status.Do Technical Specifications permit entry into Mode 2 with both channels inoperable, why? A. Yes, changes in Modes to comply with TS Actions shall NOT be prevented.B. No, there are NO exceptions to NOT meeting the LCO statement prior to making the Mode change.C. No, the Required Actions do NOT permit operation for an unlimited period of time.D. Yes, the Required Actions do permit operation for an unlimited period of time.
A
Why are the Shutdown Containment Purge air supply and exhaust dampers required to be closed and blind flanged during power operations? A. The valves are not seismically qualified to operate during a design basis earthquake.B. The valve actuators do not have class 1E penetration conductor over-current protection devices.C. The valves do not meet containment integrity requirements.D. The connecting ductwork outside containment is not seismically qualified.
C
The plant is in Mode 5. Preparations for CTMT entry are in progress with the S/D purge system in service.What is the response of the containment S/D purge system if a manual CPIS is initiated on 'B' train? A. Containment S/D purge supply air unit fan remains running, S/D purge exhaust fan remains running.B. Containment S/D purge supply air unit fan trips, S/D purge exhaust fan remains running.C. Containment S/D purge supply air unit fan remains running, S/D purge exhaust fan trips.D. Containment S/D purge supply air unit fan trips, S/D purge exhaust fan trips.
C