- Front
- Back
Minimum distance of...
Berthing tents |
35 meters apart
|
|
Minimum distance of...
Latrines |
100 yds from water source
100 yds from galley 50 ft and downwind of berthing |
|
Minimum distance of...
Garbage pits |
100 yds from water source
35 yds from galley |
|
Max distance
Single/Single Bailey Bridge |
100' at 10 tons decreasing to 30' at 40 tons
|
|
Max distance
Double/Single Bailey Bridge |
140' at 10 tons decreasing to 50' at 80 tons
|
|
Max distance
Double/Double Bailey Bridge |
180' at 10 tons decreasing to 100' at 75 tons
|
|
Three types of MGB
|
Single story MGB
Double story MGB Linked reiforced MGB |
|
Max Load of Single Story MGB
|
MLC 60
|
|
Crew Size needed to build MGB
|
24-32 personnel
|
|
Max Load of Double Story MGB
|
MLC 70 at 102 ft, decreasing to MLC 16 at 162 ft
|
|
Max Load of LRS MGB
|
MLC 70 at 150ft, and MLC 60 at 162ft.
|
|
MLO priority code
A |
S3 approval, delivered within 24 hours
|
|
MLO priority code
B |
Company Commander, 2-3 day delivery
|
|
MLO priority code
C |
Company Commander, 3-5 day delivery
|
|
MLO 114car and PMSR
|
1114 card is the Stock Record Card