Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
15 Cards in this Set
- Front
- Back
Standard of Care (CH2)
|
-to go above the law and regulations
-reasonable effort to sure safety/health/welfare -dividing line between negligence and non-negligence |
|
Negligence (CH2)
|
-not intent, don't have to show knowledge of likely harm, just have to show lack of professional standards
-could be absense of an action (sometimes forgotten) |
|
Intentional Liability (CH2)
|
forethought and planned harm, established intent
|
|
Reckless Liability (CH2)
|
not necessarily intent, but reasonably expected to know what might/would cause harm
|
|
Holding Individuals Liable Pros (CH2)
|
-won't taint innocent parties
-brand not tainted -weeding out bad apples (maybe won't address problem) |
|
Holding Corporations Liable Pros (CH2)
|
-Avoid misallocating blame
-avoid scapegoting -more resources to deal with program -maybe a policy vs. person is responsible -allows for some amount of risk taking at large organization |
|
Columbia Case Physical Design Issues (CH2)
|
-insulation broke off and damaged wing during liftoff
-flame damaged wing and engulfed shuttle -killed crew |
|
Columbia Case Personal Choices (CH2)
|
-no investigation
-crew weren't informed till right before re-entry -managers denied the request by the engineers for more information about the insulation failure |
|
Columbia Case Overall Point (CH2)
|
-NASA culture blamed
-Organizations can be liable for dangerous failures |
|
Hyatt Case Physical Design Issues (CH2)
|
-During construction, departure from blue prints wasn't authorized from head engineer
-walkway collapses during grand opening, which killed many |
|
Hyatt Case Personal Choices (CH2)
|
-Head engineer was sued and charged with negligence
-Successfully found negligent, he was expected to keep monitoring progress of walkway -SOC wasn't met |
|
Hyatt Case Overall Point (CH2)
|
-high level required to meet SoC
|
|
CitiCorps Case Physical Design Issues (CH2)
|
-Building passed existing regulations of wind resistance (90 degree tests)
-Structural joints bolted intead of welded |
|
CitiCorps Case Personal Choices (CH2)
|
-after building up and running head engineer did 45 degree tests
-not required tests -building tests failed -building was patched up by welding the bolted joints |
|
CitiCorps Case Overall Point (CH2)
|
-SoC was met
-SoC required going over and above existing rules and codes |