Plan Schedule Management |
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. |
Planning Process Group |
|
Define Activities |
The process of identifying and documenting the specific actions to be performed to produce the project deliverables. |
Planning Process Group |
|
Sequence Activities |
The process of identifying and documenting relationships among the project activities. |
Planning Process Group |
|
Estimate Activity Resources |
The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity. |
Planning Process Group |
|
Estimate Activity Durations |
The process of estimating the number of work periods needed to complete individual activities with estimated resources. |
Planning Process Group |
|
Develop Schedule |
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. |
Planning Process Group |
|
Control Schdule |
The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. |
Monitoring and Controlling Process Group |