• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/120

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

120 Cards in this Set

  • Front
  • Back
Role of project sponsor during project initiation is to assist in:
-Defining projects objectives in both business and technical terms
-Developing the project plan
-Performing the project feasibility analysis
-Performing project cost-benefit analysis
Defining projects objectives in both business and technical terms
Role of project sponsor during project execution:
-Validate project's objectives
-Validate execution of plan
-Make all project decisions
-Resolve problems/conflicts that can’t be resolved elsewhere in the organization
Resolve problems/conflicts that can’t be resolved elsewhere in the organization
Role of the project sponsor during the closure of the project or a life-cycle phase of the project is to:
-Validate that profit margins are correct
-Sign off on acceptance of deliverables
-Administer performance reviews of project team members
-All of the above
Sign off on acceptance of the deliverables
Document that officially sanctions a project:
-Project charter
-Project plan
-Feasibility study
-Cost benefit analysis
Project charter
Work breakdown structure control points for the management of a project:
-Milestones
-Work packages
-Activities
-Constraints
Work packages
One of most common reasons projects undergo scope changes:
-Poor work breakdown structure
-Poorly defined statement of work
-Lack of resources
-Lack of funding
Poorly defined statement of work
Cannot be validated using a work breakdown structure:
-Schedule control
-Cost control
-Quality control
-Risk management
Quality control
Performance measurement baseline is most often composed of three baselines:
-Cost, schedule, risk
-Cost, schedule, scope
-Cost, risk, quality
-Schedule, risk, quality
Schedule, cost, scope
Benefits of developing WBS to low levels:
-Better estimation of costs
-Better control
-Less likely for things to fall through cracks
-All of the above
All: Better estimation of costs, better control, less likely for things to fall through cracks
Baselines, once established, identify:
-What the customer and contractor agree to
-What the sponsor and customer agree to
-What the customer wants done but not necessarily what the project manager plans to do
-What the project manager plans to do, not necessarily what the customer has asked for.
What the project manager plans to do, not necessarily what the customer has asked for.
Financial closeout is used to:
-Close out all charge numbers
-Close out all charge numbers for work performed and completed
-Amend work authorization forms
-None
Close out all charge numbers for work performed and completed
Contractor asking to conduct only eight tests rather than 10 tests required by spec. PM first action should be:
-Change scope baseline
-Ask contractor to initiate a change request
-Look at penalty clauses in contract
-Ask sponsor
Ask contractor to initiate a change request
Contractor sends email to use high quality raw materials to be value added and improve quality. PM should:
-Change scope baseline
-Ask contractor to initiate a change request
-Ask sponsor
-Change WBS
Ask contractor to initiate a change request
Maximum number of subsidiary plans a program management plan can contain:
-10
-15
-20
-Unlimited
Unlimited
Change control board approves significant scope change. First document PM should update would be:
-Scope baseline
-Schedule
-WBS
-Budget
Scope baseline
Shortest time necessary to complete all activities in a network is called:
-Activity duration length
-Critical path
-Maximum slack path
-Compression path
Critical path
Cannot be identified after forward and backward pass:
-Dummy activities
-Slack time
-Critical path activities
-How much OT is planned
How much OT is planned
Not a commonly used technique for schedule compression:
-Resource reduction
-Reducing scope
-Fast tracking activities
-Use of OT
Resource reduction
Disadvantage of using bar charts to manage a project
-Do not show dependencies between activities
-Ineffective for projects under one year
-Are ineffective for projects under $1 million
-Do not identify start and end dates of schedule
Do not show dependencies between activities
Reducing peaks and valleys in manpower assignments to obtain relatively smooth manpower curve:
-Manpower allocation
-Manpower leveling
-Resource allocation
-Resource commitment planning
Manpower leveling
Activities with no time duration:
-Reserve activities
-Dummy activities
-Zero slack activities
-Supervision activities
Dummy activities
Optimistic, pessimistic and most likely times are associated with:
-PERT
-GERT
-PDM
-ADM
PERT
Most common “constraint” or relationship in precedence network is:
-Start-to-start
-Start-to-finish
-Finish-to-start
-Finish-to-finish
Finish-to-start
Network based technique that allows for branching and looping:
-PERT
-GERT
-PDM
-ADM
GERT
If activity on critical path takes longer than anticipated:
-Activities not on the critical path have additional slack
-Activities not on the critical path have less slack
-Additional critical path activities will appear
Activities not on critical path have additional slack.
Which of the following is a valid way of obtaining proper project performance information?
-First hand observations
-Oral and written reports
-Review and technical interchange meetings
-All of the above
All:
-First hand observations
-Oral and written reports
-Review and technical interchange meetings
Proper graphical display of information can result in:
-Reducing paperwork costs
-Reducing reporting costs
-Reduce time for routine decisions
-All of the above
All:
-Reducing paperwork costs
-Reducing reporting costs
-Reduce time for routine decisions
Which is a valid way to evaluate financial feasibility of a project?
-Return on investment
-Net present value
-Internal rate of return
-All
All:
-Return on investment
-Net present value
-Internal rate of return
3 common classification systems for estimates include all except:
-Parametric estimates
-Quick and dirty estimates
-Analogy estimates
-Engineering estimates
Quick and dirty estimates
Most accurate estimates are:
-Parametric estimates
-Quick and dirty estimates
-Analogy estimates
-Engineering estimates
Engineering estimates
Which is a bottom-up estimate rather than a top-down estimate?
-Parametric estimates
-Analogy estimates
-Engineering estimates
-None
Engineering estimates
Which would be considered as a cost-estimating relationship (CER)?
-Math equations based on regression analysis
-Learning curves
-Cost-cost or cost-quality relationships
-All
All:
-Math equations based on regression analysis
-Learning curves
-Cost-cost or cost-quality relationships
If a worker earns $30/hr in salary, but project is charged $75/hr for every hour they work; overhead rate is:
-100%
-150%
-250%
-None
150%
Information supplied to a customer to support financial data provided in a proposal is:
-Backup data
-Engineering support data
-Labor justification estimates
-Legal rights estimates
Backup data
Estimating pitfalls can result from:
-Poorly defined SOW
-Failure to account for risks in estimates
-Using wrong estimating techniques
-All
All:
-Poorly defined SOW
-Failure to account for risks in estimates
-Using wrong estimating techniques
Source of many estimating risks is:
-Poorly defined requirements
-Inexperienced PM
-Lack of management support during estimating
-All
All:
-Poorly defined requirements
-Inexperienced PM
-Lack of management support during estimating
Project where scope evolves as work takes place is called either progressive planning or:
-Synchronous planning
-Continuous planning
-Rolling wave planning
-Continuous reestimation planning
Rolling wave planning
Calculation of the total cost of product, from R&D to operational support and disposal, is called:
-Birth to death costing
-Life cycle costing
-Summary costing
-Depreciation costing
Life cycle costing
In earned value measurement, earned value is represented by:
-BCWS
-BCWP
-ACWP
-None
BCWP
If BCWS = 1000, BCWP = 1200, ACWP = 1300, the project is:
-Ahead of schedule, under budget
-Ahead of schedule, over budget
-Behind schedule, over budget
-Behind schedule, under budget
Ahead of schedule, over budget
If BAC = 20K and project is 40% complete, earned value is:
-5K
-8K
-20K
-Cannot determine
8K
If BAC = 12K and CPI=1.2, variance at completion is:
-(2K)
-2K
-(3K)
-3K
BCWP/ACWP = 1.2
12/x=1.2
1.2x=12
12/1.2 = 10k = ACWP

+2k
If BAC = 12K and CPI = .8, variance at completion is:
-(2K)
-2K
-(3K)
-3K
BAC/BCWP = 12k
CPI = .8 = BCWP - ACWP
.8 = 12k-ACWP
.8ACWP = 12k
12k/.8 = 15k

-3K
If BAC for a work package is 10k and BCWP = 4K, work package is:
-40% complete
-80% complete
-100% complete
-120% complete
40% complete
If CPI= 1.1 and SPI = .95, then the trend for the project is:
-Running over budget, ahead of schedule
-Running over budget, behind schedule
-Running under budget, ahead of schedule
-Running under budget, behind schedule
Running under budget, behind schedule
Document that describes a work package, identifies cost centers allowed to charge against it, and establishes the charge number is:
-Code of accounts
-Work breakdown structure
-Work authorization form
-None
Work authorization form
Unknown problems such as escalation factors are often budgeted for using:
-PM charge number
-Project sponsor charge number
-Management reserve
-Configuration management cost account
Management reserve
EAC, ETC, SPI, CPI most often appear in which report?
-Performance
-Status
-Forecast
-Exception
Forecast
If BAC=24K, BCWP =12K, ACWP = 10K, CPI = 1.2, cost that remains to finish project is:
-10k
-12k
-14k
-Cannot determine
10k
Several purposes for 50/50 rule, but primary purpose is to calculate:
-BCWS
-BCWP
-ACWP
-BAC
BCWP
When a project is completed, which must be true?
-BAC=ACWP
-ACWP=BCWP
-SV=0
-BAC = ETC
SV=0
In March CV = (20K), April CV = (30K). To tell whether situation has deteriorated because of larger unfavorable cost variance, need to calculate:
-CV in %
-SV in $
-SV in %
-All
SV in %
If PM is looking for revenue from value added scope change, first choice would be:
-Management reserve
-Customer funded scope change
-Undistributed budget
-Retained profits
Customer funded scope change
Project was originally scheduled for 20 months. If CPI is 1.25, then the new schedule date is:
-16 months
-20 months
-25 months
-Cannot determine
Cannot determine
The cost or financial baseline of a project is composed of:
-Distributed budget only
-Distributed and undistributed budgets only
-Distributed budget, undistributed budget & management reserve only
-Distributed budget, undistributed budget & management reserve and profit only
Distributed budget, undistributed budget only
BUDGETED COST FOR WORKED SCHEDULED (BCWS)
Budgeted amount of cost for work scheduled to be accomplished + amount of level of effort scheduled in a given time period

*Subtracted to find schedule variance
*PV
*How much of the work should be done?
BUDGETED COST FOR WORK PERFORMED (BCWP)
Budgeted amount of cost for completed work, + budgeted for level of effort activity in a given time period

*Earned value
*Point of comparison for cost and schedule variance
=% complete * BAC
*How much of the work is done?
ACTUAL COST FOR WORK PERFORMED (ACWP)
Amount reported as actually expended in completing work accomplished in a given time period.

*Subtracted to find cost variance
*Actual cost
*How much did the "is done" work cost?
COST VARIANCE
CV =BCWP - ACWP

*Compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished.
*Negative variance = cost overrun
*Measures efficiency: to correct, emphasize productivity (burn rate) at which work is being performed
SCHEDULE/PERFORMANCE VARIANCE
SV = BCWP - BCWS

*Provides a comparison between planned and actual performance but does not include costs.
*Negative variance = behind schedule
*To correct, emphasize speed at which work is being performed
SCHEDULE VARIANCE % = (SVP)
(SV/BCWS) * 100
COST VARIANCE % = (CVP)
(CV/BCWP) * 100
Estimate at completion (EAC)
EAC = (ACWP/BCWP) * BAC (Budget at completion)

The estimate at completion is the best estimate of the total cost at the completion of the project.
*What do we now expect the total job to cost?
The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified.
CPI (cost performance index)
BCWP/ACWP

*If <1, unfavorable (being accomplished at higher cost than planned)
SPI (schedule performance index)
BCWP/BCWS

*If <1, unfavorable (being accomplished at slower rate than planned)
BAC - budget at completion/total budget
What was the total job supposed to cost?
Variance at completion
VAC = BAC - EAC

VAC = BAC - [(ACWP/BCWP)*BAC]
Tradeoffs are almost always necessary because:
-PMs are incapable of planning correctly
-Line managers are unable to provide accurate estimates
-Executives are unable to properly define project objectives
-Circumstances can change, thus mandating tradeoffs take place
Circumstances can change, thus mandating tradeoffs take place
The person who may ultimately be responsible for approving tradeoffs is:
-Project manager
-Line manager
-Project sponsor
-Customer
Customer
Most common tradeoffs occur over:
-Time, cost, quality
-Risk, cost, quality
-Risk, time, quality
-Scope, quality, risk
Time, cost, quality
If start date of project is delayed but budget and specs are fixed, what would the project manager trade off first?
Quality
The two components of risk are:
Uncertainty and impact
Risk management is normally performed by
Developing contingency plans
Future outcomes that provide favorable opportunities are called:
Opportunities
The cause of a risk event is usually referred to as:
A hazard
If there's a 40% chance of making 100k and 60% chance of losing 150k, the expected monetary outcome is:
-50000
Assumption, mitigation and transfer are examples of risk:
Responses
In which life cycle phase would project uncertainty be the greatest?
Initiation
In which life cycle phase would financial risks of a project be the greatest?
Closure
Identifying a risk as high, moderate, or low would be an example of which risk assessment?
Qualitative
Monte Carlo simulation is an example of which risk assessment?
Quantitative
Which of the following is not a valid reason for managing a risk?
Providing a late as possible warning system
Which of the following is generally not part of overall risk management?
Selecting the PM
A technique for risk evaluation that uses a questionnaire, series of rounds, and reports submitted in confidence and then circulated with the source unidentified is called:
The Delphi Technique
Risk symptoms or early warning signs are called
Triggers
Which of the following is not a risk quantification tool or technique?
Objective setting
A technique that depicts interactions among decisions and associated events is called:
Decision tree analysis
Varying one risk driver at a time, either in small increments or from optimistic to pessimistic estimates while keeping all other drivers fixed, is called:
Sensitivity analysis
A risk response strategy that generally reduces the probability or impact of the event without altering the project's objectives is called:
Mitigation
Earned value measurement is an example of:
Risk monitoring and control
The difference between being proactive and reactive is the development of a:
Contingency plan
According to learning curve theory, learning takes place at a fixed rate whenever the production levels
Double
Learning curve theory is most appropriate for estimating which costs?
Manufacturing
On a 90% learning curve, the 100th unit required 80 hours. How many hours would the 200th unit require?

***
Shouldn't this be 72? Book says 90. How can it increase? Check.
Which of the following can be a source of improvement to a learning curve?
All of the above
The contractual statement of work is
A narrative description of the work deliverables to be accomplished and/or the resource skills required
A written or pictorial document that describes, defines, or specifies the services or items to be procured is
A specification document
The order of precedence is
The document that specifies the order/priority in which project documents will be used when it becomes necessary to resolve inconsistencies between project documents
In which type of contract arrangement is the contractor least likely to want to control costs?
Cost plus percentage of cost
In which type of contract arrangement is the contractor most likely to want to control costs?
Firm fixed price
In which type of contract arrangement is the contractor at the most risk of absorbing all cost overruns?
Firm fixed price
In which type of contract arrangement is the customer at the most risk of absorbing all cost overruns?
Cost plus percentage of cost
What is the primary objective the customer's project manager focuses on when selecting a contract type?
Creating reasonable contractor risk with provisions for efficient and economical performance incentives for the contractor
Which type of contract arrangement is specifically designed to give a contractor relief for inflation or material/labor cost increases on a long term contract?
Firm fixed price with economic price adjustment
Which of the following is not a factor to consider when selecting a contract type?
Type/complexity of requirement, urgency of requirement and price competition extent are all factors to consider
In a fixed price incentive fee contractor, the point of total assumption refers to the point in the project cost curve where:
The contractor assumes responsibility for every additional dollar that is spent in fulfilling the contract
A written preliminary contractual instrument prepared prior to the issuance of a definitive contract that authorizes the contractor to begin work immediately, within certain limitations, is a
Letter contract/letter of intent
A contract entered into after following normal procedures, e.g. negotiation of terms, conditions, cost and schedule, but prior to initiation of performance is known as a
Definitive contract
Which of the following is not a function of contract admin activity?
Selecting the PM
A fixed price contract is typically sought by the PM from the customer org when
The risk and consequence associated with the contracted task are large and the customer wants to transfer the risk
Which of the following are typical actions a customer would take if the customer received nonconforming materials or products and the customer didn't have the ability to bring goods into conformance?
Accept the shipment on the condition that the nonconforming products will be brought into conformance by the vendor at the vendor's expense
If a PM requires use of a piece of equipment, what is the breakeven point where leasing and renting are the same?
100 days
In which type of incentive contract is there a maximum or minimum value established on the profits allowed for the contract?
Cost plus incentive fee contract
In which type of incentive contract is there a maximum or minimum value established on the final price for the contract?
Fixed price incentive fee contract
A cost plus incentive fee contract has the following characteristics:
Sharing ratio 80/20
Target cost 100k
Target fee 12k
Max fee 14k
Min fee 9k

How much will the contract be reimbursed if cost of performing work is 95k?
Cost - 95K
Fee - 12K
20% of 5K savings under target cost - 1K
108K total
A cost plus incentive fee contract has the following characteristics:
Sharing ratio 80/20
Target cost 100k
Target fee 12k
Max fee 14k
Min fee 9k

How much will the contractor be reimbursed if the cost of performing the work is 85K?
Cost - 85K
Fee - 12K
20% of 15K savings under target cost, up to max total fee of 14K: 2K

99K
A cost plus incentive fee contract has the following characteristics:
Sharing ratio 80/20
Target cost 100k
Target fee 12k
Max fee 14k
Min fee 9k

How much will the contractor be reimbursed if the cost of performing the work is 120K?
120k cost
Fee - 12K
Minus customer savings for being over cost, up to min fee of 9K: (3K)

129K

132K
A fixed price incentive fee contract:
Sharing ratio 70/30
Target cost 100k
Target fee 8K
Price ceiling 110k

How much will contractor be reimbursed if cost of performing the work is 90k?
Target Cost 100k
Actual Cost 90k
Savings - 10k
Contractor Share - 10k (30%) = 3k
Fee = 8K

101k
A fixed price incentive fee contract:
Sharing ratio 70/30
Target cost 100k
Target fee 8K
Price ceiling 110k

How much will contractor be reimbursed if cost of performing the work is 102k?
Target cost 100k
Actual Cost 102k
Overrun - 2k
Contractor Deduction = $600

102k+8K-600

=109,400
A fixed price incentive fee contract:
Sharing ratio 70/30
Target cost 100k
Target fee 8K
Price ceiling 110k

How much will contractor be reimbursed if cost of performing the work is 105k?
Actual Cost 105K
Fee 8K
Overrun 5K
Contractor deduction =1500

Revised Fee 6,500
105K+6.5K = 111.5K - exceeds ceiling

Pay 110K