• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/20

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

20 Cards in this Set

  • Front
  • Back

PERT

(P+4M+O)/6

Sigma

(P-O)/6

Vofa

(P-O)/6**2


Sigma al cuadrado


COST VARIANCE CV

EV-AC


EARNED VALE - ACTUAL COST

SV SCHEDULE VARIANCE

EV-PV


EARNED VALUE - PLANNED VALUE

CPI COST PERFORMANCE INDEX

EV / AC


EARNED VALUE / ACTUAL COST

SPI SCHEDULE PERFORMANCE INDEX

EV / PV


EARNED VALUE / PLANNED VALE

EAC ESTIMATE AT COMPLETION


Past estimated assumptions are not valid

AC + ETC


ACTUAL COST + ESTIMATED TO COMPLETE

EAC ESTIMATE AT COMPLETION


Variances are typical

AC + (BAC-EV)


ACTUAL COST + BUDGET AT COMPLETION - EARNED VALUE

EAC ESTIMATE AT COMPLETION


Variances will be present at future

AC+(BAC-EV) / (CPI * SPI)

EAC ESTIMATE AT COMPLETION


Initial point. Not earned value, not actual costs, projected CPI

BAC / CPI

ETC ESTIMATED TO COMPLETE taking on account what we have actually spent

EAC - AC


ESTIMATE AT COMPLETION - ACTUAL COST

ETC ESTIMATED TO COMPLETE taking on account performance

BAC - EV / CPI


BUDGET AT COMPLETION- EARNED VALUE / COST PERFORMANCE INDEX

Sigma 1

68.26

Sigma 2

95.46

Sigma 3

99,73

Sigma 6

99.99

Canales

(N*(N-1))/2

VAC


variance at completion

BAC - EAC


Budget at completion - Estimate at completion

TCPI


To complete performance index


BAC-EV / (BAC - AC)



BAC-EV / (EAC - AC)