• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/47

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

47 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)
Time Management (Knowledge Area)
Processes:

(1) Plan Schedule Management


(2) Define Activities


(3) Sequence Activities


(4) Estimate Activity Resources


(5) Estimate Activity Durations


(6) Develop Schedule


(7) Control Schedule

7 total, 6 Ps, 1 M&C


PSM, DA, SA, EAR, EAD, DS, CS

CPM
Critical Path Method - used to estimate minimum project duration & amount of scheduling flexibility - sequence of activities that represent longest path, zero total float
Critical Path Method - used to estimate minimum project duration & amount of scheduling flexibility - sequence of activities that represent longest path, zero total float


CPM /Precedence Diagramming
Float
Formula: Late FInish - Early FInish
CCM
Critical Chain Method - Allows buffers on any project schedule path to account for limited resources and project uncertainties, resource-constrained critical path

Project Buffer - At end 


Feeding Buffer - placed on activities that feed critical...
Critical Chain Method - Allows buffers on any project schedule path to account for limited resources and project uncertainties, resource-constrained critical path



Project Buffer - At end




Feeding Buffer - placed on activities that feed critical chain



Plan Schedule Management (Process)
Establishing policies, procedures, and documentation for how to manage the schedule

Output: Schedule Management Plan

Schedule Management Plan (Output)

Components:

(1) Schedule Model Development - methodology & tool

(2) Level of accuracy - acceptable range for duration estimates


(3) Units of measure - defined for each resource


(4) Org procedures links - provides framework


(5) Schedule model maintenance - process for updates to schedule


(6) Control thresholds - percentage deviations for monitoring performance


(7) Rules of performance measurement - Earned Value Management


(8) Reporting formats - format and frequency


(9) Process descriptions - for each schedule management process

Output of "Plan Schedule Management"

Define Activities (Process)
Identifying and documenting specific actions to be performed to produce project deliverablesTools: Decomposition & Rolling wave planning, expert judgment

Outputs:


(1) Activity list


(2) Activity attributes


(3) Milestone list

Rolling Wave Planning (Tool)
Iterative planning technique, near term work detailed, future work higher level
Activity List (Output)
Includes all schedule activities required on project, activity identifier, and scope

Output of "Define Activities"

Activity Attributes (Output)
Extended description - person responsible, activity type, location of work, etc

Output of "Define Activities"

Milestone List (Output)
List of milestones, zero durations, significant point or event in project

Output of "Define Activities"

Sequence Activities (Process)
Relationships among project activities to obtain greatest efficiency given all constraints



Tools: PDM, Dependency determination, leads & lags

Outputs:


(1)Project schedule network diagram


(2) Project documents updates

PDM
Precedence Diagramming Method - constructing a schedule model represented by nodes (Ex. AON)



4 types of dependencies (FS, FF, SS, SF)

FS
Finish to Start - successor cannot start until predecessor has finished
FF
Finish to Finish - Successor cannot finish until predecessor has finished (Ex. Writing document, editing document)
SS
Start to Start - Successor cannot start until predecessor has started (Ex. Leveling concrete, pouring foundation)
SF
Start to Finish - Successor cannot finish until predecessor has started (Ex. Security guard shifts, hand off)
AON
Activity-on-Node - type of Project Schedule Network Diagram
Activity-on-Node - type of Project Schedule Network Diagram




Dependency Determination (Tool)
Mandatory (Hard) or Discretionary

(Preferred/Preferential/Soft)




Internal or External

Lead
Amount of time a successor can be advanced with respect to predecessor
Lag
Amount of time successor will be delayed with respect to a predecessor
Project Schedule Network Diagrams (Output)
Graphical representation of logical relationships/dependencies
Graphical representation of logical relationships/dependencies




Output of "Sequence Activities"

Estimate Activity Resources (Process)
Estimating type and quantities of material, human resources, equipment/supplies to perform each activity - more accurate cost and duration estimates



Tools: Alternative Analysis, Published estimating data, Bottom-up estimating

Outputs:


(1) Activity resource requirements


(2) Resource breakdown structure

Resource Calendars
Calendar that identifies working days and shifts on each specific resource availability

Output from "Acquire Project Team" and "Conduct Procurements"

Activity Resource Requirements (Output)
Identify types and quantities of resources required for each activity in a work package

Output of "Estimate Activity Resources"

Resource Breakdown Structure (Output)
Hierarchical representation of resources by category and type (labor, material, equipment, supplies)

Output of "Estimate Activity Resources"

Estimate Activity Durations (Process)
Estimating number of work periods needed to complete individual activities with estimated resources - major input to Develop Schedule process

Output: Activity duration estimates

Expert Judgment (Tool)
SME knowledge, historical information for estimates
Analogous Estimating (Tool)
Historical information, storytelling



3 lesses (Accurate, Time, Cost)

Parametric Estimating (Tool)
Algorithm used to calculate cost or duration based on historical data and project parameters - unit of measure x amount or cost (ex. sq. footage in construction)
Three Point Estimating (Tool)
Program Evaluation and Review Technique (PERT) - 3 estimates to define approximate range for activity duration (P-M-O)



tP - Pessimistic, worst-case scenario


tM - Most likely


tO - Optimistic, best-case scenario

Expected Duration (tE)
Triangular (Average) - (P+M+O)/3



Beta (Weighting) - (P+4M+O)/6

Variance Estimate
Formula: ((P-O)/6)squared
Standard Deviation Estimate
Formula:(P-O)/6
Group Decision Making Techniques (Tool)
Delphi - Anonymous voting



Nominal - Voting with ranking




Dictatorship

Reserve Analysis
Contingency Reserve (Time Reserves/Buffers) - Known Unknowns



Management Reserve - Unknown Unknowns, unforeseen work within scope, not in schedule baseline but part of project duration requirements

Activity Duration Estimates
Do not include leads or lags, assessment of likely number of timer periods to complete activity (ex. 2 weeks +/- 2 days)

Output of "Estimate Activity Durations"

Develop Schedule (Process)
Iterative process - generate schedule model with planned dates for completing project activities



Tools: Schedule network analysis, CPM, CCM, Resource optimization techniques, modeling techniques, schedule compression

Outputs:


(1) Schedule baseline


(2) Project Schedule


(3) Schedule Data


(4) Project Calendars

Resource Optimization (Tool)
Resource leveling - move dates to accommodate resources



Resource smoothing - Move resources to meet project dates

Modeling Techniques (Tool)
What-If Scenario Analysis - predict effect (positive or negative) on project.assists with contingency and response planning



Simulation - calculating multiple project durations with different sets of activities (Monte Carlo analysis)

Schedule Compression (Tool)
Crashing - Add resources, increases cost



Fast Tracking - Parallel activities, increases risk

Schedule Baseline (Output)
Approved version of schedule model, only changed through change control processes, used for basis of comparison to actual results

Output of "Develop Schedule"

Project Schedule (Output)
Schedule Presentations: Bar charts, milestone charts, Project schedule network diagrams (AON diagram)

Output of "Develop Schedule"

Control Schedule (Process)
Monitoring the status of project activities to update project progress and manage changes to schedule baseline - provides means to recognize deviation from plan/minimize risk

Outputs:


(1) Work Performance Information


(2) Schedule forecasts


(3) Change requests

Performance Reviews (Tool)
Trend Analysis - Examines performance over time, improving or deteriorating



Critical Path Method (CPM) - Comparing progress along the critical path to determine schedule status




Critical Chain Method (CCM) - Comparing amount of buffer remaining to amount of buffer needed




Earned Value Management (EVM) - Schedule Variance (SV) and Schedule Performance Index (SPI) - assess magnitude of variation to original schedule baseline

Schedule Forecasts (Output)
Estimates/predictions of conditions and events in project's future based on current knowledge at time of forecast, updated and reissued based on work performance info

Output of "Control Schedule"