Variance
|
VAR =BAC – AC
|
|
Earned Value
|
EV =% complete ×BAC
|
|
Cost Variance
|
CV =EV – AC
|
|
Schedule Variance
|
SV =EV – PV
|
|
Cost Performance Index
|
CPI =EV/AC
|
|
Schedule Performance Index
|
SPI =EV/PV
|
|
Estimate at Completion
|
EAC =BAC/CPI
|
|
Estimate to Complete
|
ETC =EAC – AC
|
|
Variance at Completion
|
VAC =BAC – EAC
|