Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
36 Cards in this Set
- Front
- Back
activity list
|
serve as key input to the sequencing of project activities.
|
|
activity on arrow
|
Older network diagramming methods used _________ to represent the activities and their relationships.
|
|
activity on node
|
It’s the most common approach to network diagramming since it’s used by most project management information systems, but can also be done manually.
|
|
activity sequencing
|
relies on several inputs to create the schedule.
|
|
analogous estimating
|
relies on historical information to predict what current activity durations should be.
|
|
crashing
|
This approach adds more resources to activities on the critical path to complete the project earlier.
|
|
critical chain method
|
aims to eliminate Parkinson’s Law by eliminating bottlenecks that hold up project progression.
|
|
critical path method
|
It uses a “forward” and “backward” pass to reveal which activities are considered critical.
|
|
discretionary dependencies
|
allow activities to happen in a preferred order because of best practices, conditions unique to the project work, or external events.
|
|
fast tracking
|
arranges activities to happen in tandem rather than in succession, which increases risk.
|
|
finish-to-finish
|
This relationship means Task A must complete before Task B does.
|
|
finish-to-start
|
This relationship means Task A must complete before Task B can begin.
|
|
float
|
is the amount of time a delayed task can delay the project’s completion. Also called slack.
|
|
FNET
|
This somewhat unusual constraint requires the activity to be in motion up until the predetermined date.
|
|
fragnets
|
The portions of a network template are also known as subnets
|
|
hard logic
|
the mandatory relationships between activities: the foundation must be in place before the house framing can begin.
|
|
lag
|
positive time added to a task to indicate waiting.
|
|
lead
|
negative time added to a task to “hurry up.”
|
|
mandatory dependencies
|
the natural order of activities. For example, you can’t begin building your house until your foundation is in place.
|
|
Monte Carlo analysis
|
typically a computer
program to estimate the many possible variables within a project schedule. |
|
network templates
|
Used to streamline the planning process or to conform to a predetermined standard.
|
|
parametric estimating
|
use a mathematical model to calculate how long activities should take based on units, duration, and effort.
|
|
Parkinson’s Law
|
“Work expands so as to fill the time available for its completion.”
|
|
precedence diagramming method
|
the most common method of arranging the project work visually. The _____ puts the activities in boxes, called nodes, and connects the boxes with arrows.
|
|
project calendar
|
determines when the project work may take place.
|
|
resource calendar
|
reflects when the project resources (project team members, consultants, and so on) are available to complete the project work.
|
|
resource leveling heuristics
|
a method to flatten the schedule when resources are over-allocated.
|
|
schedule control
|
the process of managing changes to the project schedule
|
|
schedule management plan
|
must be consulted when project schedule changes occur, are proposed, or are needed.
|
|
schedule variance
|
An accumulation of differences between scheduled and actual dates
|
|
SNET
|
This constraint requires that the project or activity not start earlier than the predetermined date.
|
|
soft logic
|
allows the relationship and order of activities to be determined based on conditions, preferences, or other factors.
|
|
start-to-finish
|
requires that Task A start so that Task B may finish.
|
|
start-to-start
|
This relationship means Task A must start before Task B
can start. |
|
subnets
|
often associated with repetitive actions within a network diagram
|
|
three-point estimate
|
requires that for each activity an optimistic, most likely, and pessimistic estimate be created.
|