• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/36

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

36 Cards in this Set

  • Front
  • Back
activity list
serve as key input to the sequencing of project activities.
activity on arrow
Older network diagramming methods used _________ to represent the activities and their relationships.
activity on node
It’s the most common approach to network diagramming since it’s used by most project management information systems, but can also be done manually.
activity sequencing
relies on several inputs to create the schedule.
analogous estimating
relies on historical information to predict what current activity durations should be.
crashing
This approach adds more resources to activities on the critical path to complete the project earlier.
critical chain method
aims to eliminate Parkinson’s Law by eliminating bottlenecks that hold up project progression.
critical path method
It uses a “forward” and “backward” pass to reveal which activities are considered critical.
discretionary dependencies
allow activities to happen in a preferred order because of best practices, conditions unique to the project work, or external events.
fast tracking
arranges activities to happen in tandem rather than in succession, which increases risk.
finish-to-finish
This relationship means Task A must complete before Task B does.
finish-to-start
This relationship means Task A must complete before Task B can begin.
float
is the amount of time a delayed task can delay the project’s completion. Also called slack.
FNET
This somewhat unusual constraint requires the activity to be in motion up until the predetermined date.
fragnets
The portions of a network template are also known as subnets
hard logic
the mandatory relationships between activities: the foundation must be in place before the house framing can begin.
lag
positive time added to a task to indicate waiting.
lead
negative time added to a task to “hurry up.”
mandatory dependencies
the natural order of activities. For example, you can’t begin building your house until your foundation is in place.
Monte Carlo analysis
typically a computer
program to estimate the many possible variables within a project schedule.
network templates
Used to streamline the planning process or to conform to a predetermined standard.
parametric estimating
use a mathematical model to calculate how long activities should take based on units, duration, and effort.
Parkinson’s Law
“Work expands so as to fill the time available for its completion.”
precedence diagramming method
the most common method of arranging the project work visually. The _____ puts the activities in boxes, called nodes, and connects the boxes with arrows.
project calendar
determines when the project work may take place.
resource calendar
reflects when the project resources (project team members, consultants, and so on) are available to complete the project work.
resource leveling heuristics
a method to flatten the schedule when resources are over-allocated.
schedule control
the process of managing changes to the project schedule
schedule management plan
must be consulted when project schedule changes occur, are proposed, or are needed.
schedule variance
An accumulation of differences between scheduled and actual dates
SNET
This constraint requires that the project or activity not start earlier than the predetermined date.
soft logic
allows the relationship and order of activities to be determined based on conditions, preferences, or other factors.
start-to-finish
requires that Task A start so that Task B may finish.
start-to-start
This relationship means Task A must start before Task B
can start.
subnets
often associated with repetitive actions within a network diagram
three-point estimate
requires that for each activity an optimistic, most likely, and pessimistic estimate be created.