Monitor & Control Risks Process
Inputs? |
Risk Register
Project management plan Work performance information Performance reports |
|
Monitor & Control Risks Process
Tools and Techniques? |
Risk reassessment
Risk audits Variance and trend analysis Technical performance measurement Reserve analysis Status Meetings |
|
Monitor & Control Risks Process
Outputs? |
Risk register updates
Organizational process assets updates Change requests Project management plan updates Project documentation updates |
|
What does Risk Register tranks and ranks?
|
individural risks, risk owner, risks triggers, residual risks, list of response plans and strategies.
|
|
What is in the Work Performance Information?
|
status of deliverables
costs to date cost changes schedule progress to date schedule changes scope changes |
|
What is in performance reports?
|
status reports
performance measurements forecasts |
|
What are the conditions to update the Risk Register
|
first is when a risk audit or reasessment id conducted some elements of the original risk info has changed.
second is when the risk needs to be closed. |
|
What is Planned value (PV) ?
|
budgeted cost of work scheduled (BCWS)
• Cost of scheduled work |
|
What is Actual Cost (AC)?
|
actual cost of work performed (ACWP)
• Cost of the work |
|
What is Earned Value (EV)?
|
budgeted cost of work performed (BCWP)
• Value of the work as compared to budgeted amount assigned |
|
What is the formula for Schedule Variance (SV)?
|
SV= EV-PV
|
|
What is the formula for Cost Variance (CV)?
|
CV = EV -CV
|
|
What is the formula for Schedule Performance Index SPI?
|
SPI = EV/PV
|
|
What is the formula for Cost Performance Index CPI?
|
CPI = EV/AC
|
|
In Forecasting what is the formula for Estimate at Completion EAC when new estimates are flawed
|
EAC = AC + ETC
|
|
In Forecasting what is the formula for Estimate at Completion EAC when atypical vaniance or assuming work completes at budgeting rate?
|
EAC = AC + (BAC -EV)
|
|
In Forecasting what is the formula for Estimate at Completion EAC when there is typical variance?
|
EAC=AC+((BAC-EV)/CPI)
|
|
In Forecasting what is the formula for Estimate at Completion EAC when cost performance is negative and schedule is firm?
|
EAC=AC +[(BAC-EV)/CPI X SPI)],
|
|
In Forecasting what is the formula for Estimate to Complete when there is typical variance?
|
ETC = BAC - cumulative EV/cumulative CPI
|
|
In Forecasting what is the formula for Estimate to Complete when there is atypical variance?
|
ETC = BAC - cumulative EV
|
|
How do you calculate TCPI when CPI falls below 1, all future project work must be performed at the TCPI level if the project is to meet cost performance goals?
|
BAC - EV/BAC -AC
|
|
How to calculate TCPI when with new EAC when BAC is no longer attainable?
|
BAC - EV/EAC - AC
|
|
Trend Analysis determines what?
|
whether project performance is improving or worsening over time.
|
|
What is variance analysis and what's the formula?
|
Difference between budget at completion and estimate at completions VAC = BAC -EAC
|
|
A delay to a noncritical path task will not delay the overall schedule and might not need corrective action. True of False?
|
True
|
|
Changes to approved schedule is called?
|
Revisions
|
|
Seven Ishikawa basic tools of quality
|
Cause and effect diagrams
Control Charts Flowcharing Histogram Pareto Chart Run chart Scatter Diagram |
|
Control Charts measure results of processes over ____? Mean must be met.
|
TIme
|
|
What is Viflredo Pareto's rule?
|
80/20. In PM 20 percent of causes creates 80 percent of the problems.
|
|
What does Run Charts show over time?
|
Variations.
|
|
Two variances in Run Charts
|
Common Cause - common to the process
Special Cause - not common to the process |
|
When a process is in control it should be adjusted?
|
No.
|
|
Scatter diagram's two variables. Name them.
|
Independent Variable (usually time)
Dependent Variable |
|
Inspection keeps errors in the product ____ the customer. Prevention keeps errors from ___ in the process.
|
reaching
occuring |
|
Two attribute sampling outcome.
|
confrorming
non-conforming |
|
What is Verify Scope's primary purpose
|
To formally accept the completed deliverable with sign off from stakeholders.
|
|
What is Control Scope's primary focus?
|
To monitor the status of botht he project and the product scope.
|
|
What is Control Scope's only Tool?
|
Variance Analysis
|
|
What is unapproved or undocumented changes that sometime make their way to a project?
|
Scope Creep
|
|
What are the two things that are hlepful in determing the impact of he schedule variations and in determining if corrective actions are necessary?
|
SV and SPI
|