• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/10

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

10 Cards in this Set

  • Front
  • Back
Which of the following is generally not regarded to be a motivator according to Frederick Herzberg?

Working conditions and interpersonal relations.
Responsibility for enlarged task.
Interest in the task.
Recognition for achievement.
Answer: A
A project manager performs Earned Value Analysis and finds the following results:
AC: 220,000, PV: 250,000, EV: 220,000.


CV = 0.
CV = 30,000.
CV = -30,000.
CV = 1
Answer:
A
Regarding Delphi Technique all of the following statements are true except

It is a way to reach a consensus of experts.
Experts are identified but participate anonymously while a facilitator uses a questionnaire to solicit ideas.
The experts are encouraged by the facilitator to make direct contact with each other during the assessment process to create a higher number of feedback loops.
The responses are submitted and are then circulated to the experts for further comment.
Answer: C
A summary activity in a network logic diagram is often referred to as a

Hammock.
Dangler.
Milestone.
Subtask.
Answer: A
Ongoing project planning is also known as ________.

Rolling wave planning
Buildup planning
Activity planning
Project processes
a
Which of the following is the correct formula for calculating present value of a business or organization?
Note: R = Interest rate, n = time periods


Present Value = Future Value/(1+R)n
Present Value = Future Value/(1-R)n
Present Value = (1+R)n
Present Value = (1-R)n / Future Value
a
Configuration management is:

used to ensure that the description of the project product is correct and complete.
the creation of the work breakdown structure.
the set of procedures developed to assure that project design criteria are met.
a mechanism to track budget and schedule variances.
Answer:
A
Your most recent project status report contains the following information: BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:

+ 1,000.
+ 500.
- 500.
- 1,000.
Answer
: D
Risk identification outputs include the following except:

decision trees.
inputs to other processes.
risk symptoms.
potential risk events.
Answer:
A
All of the following are contract types except:

unit-price.
make-or-buy.
cost reimbursable.
lump sum.
b