Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
21 Cards in this Set
- Front
- Back
BAC
|
No one formula exists. BAC is derived by looking at the total budgeted cost for the project.
How much did we BUDGET for the TOTAL project effort? |
|
PV
|
(Planned % Complete) X (BAC)
What is the estimated value of the work planned to be done? |
|
EV
|
EV = (Actual % Complete) X BAC
What is the estimated value of the work actually accomplished? |
|
AC
|
Sum of the costs for the given period of time.
What is the actual cost incurred for the work accomplished? |
|
CV
|
CV = EV – AC
(-) defines over budget. (+) defines under budget. |
|
SV
|
SV = EV – PV
(-) defines behind schedule. (+) defines ahead of schedule. |
|
CPI
|
CPI = EV /AC
You are getting $__ worth of work out of every $1 spent. (<1) is bad (>1) is good |
|
SPI
|
SPI = EV / PV
You are only progressing at ____ % of the rate originally planned. (<1) is bad (>1) is good |
|
EAC
|
EAC = BAC / CPI
What do we currently expect the TOTAL project to cost? |
|
ETC
|
ETC = EAC – AC
From this point forward, how much MORE do we expect it to cost to finish the project? |
|
VAC
|
VAC = BAC - EAC
How much over(-) or under(+) do we expect to be at the end of the project? |
|
BCR
|
Benifit Cost Ratio
The biggest ratio of the benefit/cost |
|
IRR
|
Internal Rate of Return
Biggest % of Biggest $ amt |
|
NPV
|
Biggest $$ project
|
|
Three Point Estimate
|
PERT
Pessimistic + (4 x Realistic) + Optimistic / 6 |
|
Standard Deviation
|
Pessimistic – Optimistic / 6
|
|
Communication Channels
|
N(N-1) / 2
|
|
1 Sigma
|
68.26
|
|
2 Sigma
|
95.46
|
|
3 Sigma
|
99.73
|
|
6 Sigma
|
99.9997
|