Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
60 Cards in this Set
- Front
- Back
Triple constraint
|
scope/quality
time cost/resources |
|
standard
|
specification in place for an item or process that is suggested and typically common
|
|
regulation
|
more like a law, in that compliance is required
|
|
5 main process groups
|
Initiating, planning, execution, monitoring and controlling and closing
|
|
plan-do-check-act
|
ASQ cycle as an approach to process development
|
|
phase gate
|
review process undertaken to determine if a project is likely to succeed; also known as the kill point
|
|
project management team
|
anyone who is working on project management-related items
|
|
project coordinator
|
acts as the communications link to senior management and has some limited decision making abilities
|
|
project expeditor
|
someone who verifies that some assignment is complete, checking on the status of some undertaking. Do not have decision making abilities
|
|
matrix organization types
|
weak matrix
balanced matrix strong matrix |
|
organizational process assets
|
inputs to many processes that deal with variables external to the project such as information systems and company policies and procedures
|
|
enterprise environmental factors, EEFs
|
inputs to many process that potentially influence project success; thus they should be known and taken into consideration during project planning
|
|
PMIS
|
Project management informaion system; a repository that holds knowledge; knowledge base
|
|
Project charter
|
no charter - no project
|
|
Project selection tools
|
Mathematical model
Benefit measurement model |
|
Return on Investment ROI
|
select the largest number or precentage
|
|
Net Present Value NPV
|
select the largest number (disregard the number of years as years are already factored in)
|
|
Benefit Cost Ratio (BCR)
|
select the largest ratio
|
|
baseline
|
the original estimate plus any approved changes
|
|
Project management plan
|
the plan that allows the team to know what work to do and when
|
|
work authorization system
|
formal or informal system used in project management to ensure that work is done as planned; right work done in the right order and by the right people; helps control cost; used to minimize or eliminate gold-plating
|
|
lessons learned
|
can occur at the end of each project phase and or at the end of each project
|
|
Sequence of closure
|
1. complete any close project activities
2. deliver reports associated with closure 3. close contracts with vendors 4. perform lessons learned 5. complete archives of project files 6. release resources |
|
management by objectives
|
helps determine where a project fits intot he "big picture" of planning at the company
|
|
Delphi Technique
|
technique which involves trying to gain a consensus of the experts by keeping their identities protected and working in iterations
|
|
Work package
|
the lowest level of the work breakdown structure (WBS). Subsequent decomposition results in creating activity lists
|
|
WBS dictionary
|
Result of the create WBS process; Complements the WBS by documenting the work packages, control accts and listing org responsible for completion of work
|
|
Work Breakdown structure
|
describes the work breakdown and restricts its content to listing only project work
|
|
control account
|
point placed in the WBS above the work package and planning package to help with estimating when all the details are not available at the work package level
|
|
Inspection
|
validates that the correct work has been done
|
|
rolling wave planning
|
concept that utilized the processive elaboration concept in planning
|
|
precedence diagramming method (PDM)
|
shows the activities on the blocks or boxes with arrows connecting them
|
|
arrow diagramming method (ADM)
|
uses the arrow for the activities and dots to connect them
|
|
Applying leads and lags
|
Shows a true duration of the various paths of the network diagram
|
|
network diagram
|
tool used to evaluate schedule compression techniques such as crashing and fast tracking
|
|
hard/mandatory logic
|
constraint that must be completed before subsequent items can start
|
|
soft/discretionary logic
|
constraint that should be started but is not required to be completed before subsequent items can start
|
|
external contraints
|
constraint placed by something external to the project team or organization
|
|
precedence diagrammin method
|
activity on the node;
no dummies; F-S, S-S, F-F and S-F |
|
arrow diagrammin method
|
activity on the arrow;
dummies allowed; F-S |
|
lag
|
delay between activities
|
|
lead
|
an accelerant of an activity
|
|
Estimating methods
|
analogous/ top down;
bottom up; parametric; computerized/ Monte Carlo |
|
PERT (Program evaluation review technique)
|
(O + P + (4*R))/ 6
o= optimistic p= pessimistic r= realistic |
|
slack/float
|
if an activity has no slack it is on the critical path;
negative and positive float can exist |
|
critical path
|
the longest path on the project network diagram
|
|
negative slack
|
project or activity is behind schedule
|
|
positive slack
|
activity or project is ahead of schedule
|
|
forward pass calculation
|
method to determine the critical path of the project network diagram; FIB
F= forward pass I= increment B= choose the bigger value |
|
backward pass calculation
|
opposite of FIB;
decrement and choose the smaller value |
|
standard deviation
|
(P - O)/6
|
|
variance
|
((P - O)/6)2(squared)
|
|
direct cost
|
cost spent only on project work
|
|
indirect cost
|
cost needed for a project but not restricted to it (eg electricity)
|
|
fixed cost
|
cost that is consistent on a project regardless of the number used
|
|
variable cost
|
cost that fluctuates with what is produced
|
|
future value, FV
|
the value at a specific point in time in the future
FV = PV * (1+r)^n pv=present value r=interest rate n=number of periods |
|
present value, PV
|
value of something today
PV= FV/ (1+r)^n |
|
sunk cost
|
cost that has already been spent on a project; do not consider sunk cost when making future project decisions
|
|
standard depreciation (straight line)
|
performed with basic division
|